PROJECT DETAILS

Catering & FM on SHURA island

CHECKLIST FOR:
Form No: R00-O02M06-
TESTING & COMMISSIONING OF FIRE-RESISTANT CABLES FOR EMERGENCY LIGHTS ACC-MTS-EL-0013
SUBCONTRACTOR CONTRACTOR Rev. No: C0
X
Page: 1 of 1
SECTION OF WORK: Electrical LOCATION: HE-02
LEVEL: GROUND FLOOR ITR No.:
STAGE ITEM Checked by Checked by Date

S/C CONT Consult.


Check Layout. Done Done
SETTING
OUT Check materials are as per the approved material Done Done
submittal.
MEP/CIVIL Check for Services Clearances Done Done

Done Done
1. Pre-commissioning checked and verified.

2. Visual inspection of all installed components for Done Done


damage, defects or any other issues that may
impact performance.
3. Verify proper installation of devices with Done Done
tagging/labelling.
4. Check that all devices are correctly installed and Done Done
Testing & Commissioning

connected to the system.


5. Verify that all detectors are mounted at the Done Done
appropriate heights and locations according to the
manufacturer's specifications.
6. Check the cable and wiring connections for proper Done Done
polarity and tightness
7. Test the battery backup system for proper voltage Done Done
and functionality.
8. Verify that all devices are correctly programmed Done Done
according to the fire alarm system design.
9. Verify that all devices can communicate properly Done Done
with the fire alarm control panel
10. Functional test like continuity, insulation & Voltage Done Done
drop tests are checked and verified
11. Perform a full functional test of the fire alarm system
including all smoke detectors, heat detectors, Done Done
manual pull stations, annunciators and control
panels.
12. Conduct a sensitivity test on all smoke detectors and Done Done
verify that they meet the required sensitivity levels.
13. Conduct a full acceptance test including initiating a Done Done
fire signal and verifying that the system responds
appropriately.
14. Verify that all audible and visual alarm signals are Done Done
functioning correctly and that the sound levels are
within the required range.
PROJECT DETAILS

Catering & FM on SHURA island

Sub-Contractor Main Contractor Consultant Rep.


Name: Name: Eng. Hassan Name: Sign:
Eng. Mohamad Malkawi El Arabi

Sign: Sign:
Date: 20/02/2023 Date: 20/02/2023 Date: