Professional Documents
Culture Documents
CH04 - Transportation Model
CH04 - Transportation Model
→ Concerned with determining an optimal strategy for A concrete company transports concrete from three plants, 1, 2
distributing a commodity from a group of supply and 3, to three construction sites, A, B and C. The capacity (in
centers, such as factories, called sources, to various tons) of the plants and the requirement (in tons) of construction
receiving centers, such as warehouses or stores, sites per week are as follows:
called destinations, in such a way as to minimize
total distribution costs. Plant Capacity Construction Requirement
→ Can also be used when a firm is trying to decide (Supply) Site (Demand)
where to locate a new facility. Good financial 1 300 A 200
decisions concerning facility location also attempt 2 300 B 200
to minimize total transportation and production 3 100 C 300
costs for the entire system. The transportation cost of 1 ton of concrete from each plant to
each construction site is shown below:
Objective: Minimize Cost = = X1AC1A + X1BC1B + X1CC1C + Prepare the initial feasible solution using the following methods
X2AC2A + X2BC2B + X2CC2C + X3AC3A + X3BC3B + X3CC3C and compute for the total transportation cost:
9|Page|MANSCI-Transportation Model
The remaining 100 tons requirement will be satisfied by the next In the last tableau, all the capacity of sources is exhausted to
source which is source 3. Since source 3 can supply a total of different destinations and all the requirement of destinations is
100 tons, it can satisfy all the remaining needs of destination C. fulfilled.
Since source 3 can supply 100 tons and destination A needs 200
tons, we can exhaust all the 100 tons capacity of source 3 leaving
destination A a need to 100 more tons.
1. From the remaining cells, the cell with the least cost
is x1A. Since source 1 can supply 300 tons and
destination A requires 100 remaining tons, it can
fulfill all the remaining needs of destination A and
will still have a remaining of 200 tons which it can Since all the capacity of source 3 is exhausted, it is not included
supply to other destinations. in the next computation of penalty.
2. From the remaining cells, the cell with the least cost
is x2B. Since source 2 can supply 300 tons while Penalty
destination B requires 200 tons, it can fulfill all the
needs of destination B and will still have a ROW/COLUMN 2nd Lowest Penalty
Lowest
remaining of 100 tons which it can supply to other
destinations. ROW 1 6 4 2
3. From the remaining cells, the cell with the least cost ROW 2 7 5 2
is x1C. Since source 1 can supply 200 remaining tons COLUMN A 7 4 3
while destination C requires 300 tons, all the COLUMN B 6 5 1
remaining 200 tons of source 1 will be exhausted, COLUMN C 9 8 1
leaving destination C a need to 100 more tons. The row or column with the highest penalty is column A. The
4. The last remaining cell is x2C. All the remaining cell in column A with the least cost is x1A. Since source 1 can
100 tons in source 2 will be exhausted to fulfill the supply 300 tons while destination A needs 200 tons, it can fulfill
remaining 100 tons requirements of destination C. all the needs of destination A and will still have a remaining of
100 tons which it can supply to other destinations.
10 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
cells and only one closed path for the most negative
cell is traced.
Illustration:
Since all the requirements of destination A are fulfilled, it is not 1. Stepping stone method
included in the next computation of penalty. a. Northwest corner rule
Penalty
Only column C remains with x1C with the least cost. Since
source 1 can supply 100 remaining tons while destination C
needs 200 tons, all the 100 remaining tons of source 1 will be
exhausted, leaving destination C a need to 100 more tons. This
remaining requirement will be fulfilled by source 2 which still
has 100 remaining tons to supply.
=5
METHODS OF ESTABLISHING OPTIMAL
FEASIBLE SOLUTION
11 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
Optimality Test - After computing all the improvement indices, Improvement index of unused cells:
and all the indices computed is greater than or equal to zero
(positive), an optimal solution has been achieved. x1B = +x1B – x2B + x2C – x1C | = 6 – 5 + 9 – 8 = 2
If not, an improvement must be done using the following steps: x2A = +x2A – x2C + x1C – x1A | = 7 – 9 + 8 – 4 = 2
1. Choose the closed path traced of the unused cell x3B = +x3B – x2B + x2C – x1C + x1A – x1C | = 5 – 5 + 9 – 8 + 4 – 4
with the most negative improvement index. =1
2. Choose the smallest value of transferred units from
the cells in the closed path with a minus (-) sign. x3C = + x3C – x1C + x1A – x1C | = 5 – 8 + 4 – 4 = -3
3. Add the value in step 2 in the value of transferred
units in cells with plus (+) sign and deduct such Since one of the indices is negative, improvement of tableau is
from the value of transferred units in cells with needed:
minus (-) sign.
1. X3C → X1C → X1A → X3A → X3C
Since one of the indices is negative, improvement of tableau is 2. X1C = 200, X3A = 100;
needed: 3. X3C = 0 + 100 = 100 X1C = 200 – 100 = 100
1. X1C → X1B → X2B → X2C → X1C X1A = 100 + 100 = 200 X3A = 100 – 100 = 0
2. X1B = 100, X2C = 200;
All the improvement indexes of all unused cells must be x2A = +x2A – x2C + x1C – x1A | = 7 – 9 + 8 – 4 = 2
computed again and check if all the indices is greater than or
equal to zero (positive). x3A = +x3A – x3C + x1C – x1A | = 4 – 5 + 8 – 4 = 3
x1B = +x1B – x2B + x2C – x1C | = 6 – 5 + 9 – 8 = 2 Since all the indices are greater than or equal to zero, thus,
Tableau 2 contains the optimal solution already. The minimum
x2A = +x2A – x2C + x1C – x1A | = 7 – 9 + 8 – 4 = 2 transportation cost is:
12 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
x3B = +x3B – x3C + x2C – x2B | = 5 – 5 + 9 – 5 = 4 4. Compute for marginal cost of each unused cell.
Since all the indices are greater than or equal to zero, thus, CELL Cij Ui Vj Eij
Tableau 1 already contains the optimal solution which has a total X1C 8 0 10 -2
transportation cost of P4,000. X2A 7 -1 4 4
X3A 4 -2 4 2
2. Modified distribution method
X3B 5 -2 6 1
a. Northwest corner rule
Optimality Test - After computing all the marginal cost, and all
the amounts is greater than or equal to zero (positive), an
optimal solution has been achieved.
U1 + VA = 4 (1) U2 + VC = 9 (4)
U1 + VB = 6 (2) U3 + VC = 8 (5)
U2 + VB = 5 (3)
3. Let U1 = 0, and compute for the value of all After the improvement of the tableau, marginal cost of the
variables. 4. Compute the marginal cost of each improved tableau must be computed again.
unused cell using the formula Eij = Cij – (Ui + Vj).
U1 = 0 1. Same variable assigned in respective rows and
columns.
U1 + VA = 4 (1) U2 + VB = 5 (3) U3 + VC = 8 (5) 2. U1 + VA = 4 (1) U2 + VB = 5 (4)
U1 + VC = 8 (2) U3 + VC = 5 (5)
0 + VA = 4 U2 + 6 = 5 U3 + 10 = 8 U2 + VC = 9 (3)
3. U1 + VA = 4 (1) U2 + VC = 9 (3) U3 + VC = 5 (5)
VA = 4 U2 = -1 U3 = -2 0 + VA = 4 U2 + 8 = 9 U3 + 8 = 5
VA = 4 U2 = 1 U3 = -3
U1 + VB = 6 (2) U2 + VC = 9 (4) U1 + VC = 8 (2) U2 + VB = 5 (4)
0 + VC = 8 1 + VB = 5
0 + VB = 6 -1 + VC = 9 VC = 8 VB = 4
13 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
ROUTE Tons Cost/ Total 4. Compute for marginal cost of each unused cell.
From To Shipped ton Cost
1 A 200 4 800 CELL Cij Ui Vj Eij
1 C 100 8 800 X1B 6 0 4 2
2 B 200 5 1,000 X2A 7 1 4 2
2 C 100 9 900 X3A 4 -3 4 3
3 C 100 5 500 X3B 5 -3 4 4
TOTAL 4,000 Since all the marginal costs are greater than or equal to zero,
Improvement was done from Tableau 1 with a total cost of thus, Tableau 2 contains the optimal solution already. The
P4,200 to Tableau 2 with a total cost of P4,000. minimum transportation cost is:
UNBALANCED TRANSPORTATION
PROBLEM
14 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
Illustration:
Determine the number of tons to be delivered from each plant to ROUTE Tons Cost/ Total
respective site that will obtain the minimum total transportation From To Shipped ton Cost
cost. 1 A 200 4 800
1 B 100 6 600
Use northwest corner rule and stepping stone method in solving 2 B 100 5 500
the problem. 2 C 200 9 1,800
3 D 100 0 0
• INITIAL FEASIBLE SOLUTION: TOTAL 3,700
NORTHWEST CORNER RULE
Note transportation cost of cell that contains ℇ is not computed
since it is assumed to have a very small non-negative number
Checking the illustration, the total capacity of all sources is 700
and will result to almost nothing. Technically, a total of 700 tons
tons while the total requirements of all destination sites is 600
are shipped but in substance, only 600 tons are shipped because
tons only. There is a surplus of 100 tons which will not have a
the shipment of 100 tons to destination D is just a dummy or
destination.
imaginary transfer.
Since the supply exceeds the demand, a dummy destination
Compute for the improvement index of unused cells:
must be added with a requirement of 100 tons (700 tons – 600
tons). All the transportation cost per unit going to destination D
x1C = +x1C – x1B + x2B – x2C = 8 – 6 + 5 – 9 = -2
(dummy) is zero.
x2A = +x2A – x2B + x1B – x1A =7–5+6–4=4
= 5 – 0 + 0 – 6 + 5 – 9 = -7
15 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l
From x2D, next step can be on x2C, then on x3C, but 3 C 100 5 500
no other step can be made after. TOTAL 3,100
Last option is from x2D, then on x2b, but no other Improvement was done from Tableau 1 with a total cost of
step can be made after. P3,700 to Tableau 3 with a total cost of P3,100.
3. Since there is no closed path can be traced on x2D, a
value ℇ can be assigned to this cell.
SUMMARY FOR TMP
=5–5+8–0+0–5=3
Since all the indices are greater than or equal to zero, thus,
Tableau 3 contains the optimal solution already. The minimum
transportation cost is:
16 | P a g e | M A N S C I - T r a n s p o r t a t i o n M o d e l