Professional Documents
Culture Documents
Measurement Considerations
Measurement Considerations
Considerations
3.1 INTRODUCTION
What do we actually mean by flow measurement? Do we want to measure the flow
rate in terms of its velocity – metres (or feet) per second? Or are we more interested in
how much in terms of capacity for example litres (or gallons) per second? Or are we
more interested in how much in terms of its mass kilograms (or pounds) per second?
Although there are a couple of technologies that measure the flow directly in terms
of capacity, most tend to measure the flow rate in terms of its velocity and then infer
the volumetric flow rate (capacity) or the mass flow rate.
Q = v⋅A (3.1)
Figure 3.2 illustrates the range of volumetric flow rates according to the flow
velocity and pipe diameter.
Unit of Time
Area (A)
FIGURE 3.1 Volumetric flow rate, Q, represents the total volume of fluid flowing through
a pipe per unit of time.
33
34 The Concise Industrial Flow Measurement Handbook
FIGURE 3.2 Different volumetric flow rates according to the flow velocity and pipe diameter.
PIPE SIZES
Pipes are rated according to their normal pipe diameter and given according
to a preferred series – referred to as their Nominal Pipe Size (NPS) or their
Nominal Bore (NB) – both based on inches.
The European equivalent to NPS is the Nominal Diameter (DN) measured
in millimetres (Table 3.1).
Measurement Considerations 35
TABLE 3.1
Preferred Series of ANSI and DN Pipe Sizes
Pipe Diameter Pipe Diameter (mm) Pipe Diameter (in) Pipe Diameter (mm)
(in) (ANSI – NPS) (DN) (ANSI – NPS) (DN)
0.5 15 8 200
0.75 20 10 250
1 25 12 300
1.5 40 14 350
2 50 16 400
3 80 24 600
4 100 36 900
6 150 48 1,200
It should be noted that, in this case, ‘nominal’ means just that – in other
words: approximate or ‘not necessarily corresponding exactly to the real value’.
Qm = Q ⋅ ρ (3.2)
or:
Qm = v ⋅ A ⋅ ρ (3.3)
Some flowmeters, such as Coriolis meters, measure the mass flow directly.
However, in many cases, mass flow is determined by measuring the volumetric flow
and the density and then calculating the mass flow as shown above. Sometimes the
Unit of Time
Area (A) Density (ρ)
FIGURE 3.3 Mass flow rate, Qm, represents the total mass of fluid flowing through a pipe
per unit of time.
36 The Concise Industrial Flow Measurement Handbook
density is inferred from the measurement of the pressure and temperature of the
fluid. This type of measurement is referred to as the inferred method of measuring
the mass flow.
3.4 TOTALISATION
Totalisation is simply a running total of how much of fluid (liquid, gas, or steam)
has flowed through the metering system in a given time – allowing the fluid to be
dispensed in set quantities.
The flow rate itself may be constant during this period (Figure 3.4a) or it may vary
(Figure 3.4b).
In any event, totalisation entails integrating the flow rate between two timed
intervals: t1 and t2:
t2
Total t 2 −t1 =
∫ t1
Q(t ) ⋅ dt (3.4)
In essence there are two basic metering systems: those that measure the flow rate
in fixed discrete packages (either directly or inferred) or measure the quantity on a
continuous (analogue) basis.
Positive displacement meters for example provide a pulse output for each measured
volume of the product. Consequently, totalisation entails counting the total number of
pulses generated during the timing period. Since this is not a continuous measurement,
there will be a resolution issue – how much of the medium is contained in each
discrete package – with the resolution determined by the ‘width’ of each sample
(Figure 3.5).
Many meters, such as turbines generate pulses according to the inferred flow rate.
Consequently, resolution will be based on the number of pulses that can be generated
during a single revolution of the turbine.
The measurement of flow rates from metering systems based on head loss,
ultrasonic, and electromagnetic technology provide a continuous analogue output
and totalisation therefore requires either some form of A to D conversion to generate
a pulse train or some form of electronic integration.
(a) (b)
Flow rate (Q)
FIGURE 3.4 During the timing period the flow rate (a) may be constant or (b) may vary.
Measurement Considerations 37
Discrete volumes
t1 t 2 Time (t)
FIGURE 3.5 Totalisation entails counting the total number of the pulses generated during
the timing period – with the resolution determined by the ‘width’ of each sample.
Expressed another way we are saying that we are 95% sure that the temperature
lies between 60°C and 70°C.
The confidence level is thus a statement of probability and we shouldn’t state an
uncertainty without it.
The generally accepted confidence level given for flow is 95%. This means that,
on average, we should expect that:
19 times out of 20
19/20 = 95/100 = 95%
the reading of the meter will fall within the bracket specified (e.g. ±1% of the actual
calibrated value).
If a flowrate of 50 ± 1 L/s was reported at a 50% confidence level we would only
expect repeated measurements to lie within the range 49 and 51 L/s half the time –
with half the results lying outside this interval.
3.6 ACCURACY
Despite the aforementioned problems associated with the term accuracy, it still
continues to be used by the majority of manufacturers and, by a more or less common
agreement, is generally used to express the maximum deviation between the meter’s
indication and the true value of the process being measured.
In flow measurement accuracy may be quoted in two ways:
• Relative accuracy – the proportion of the error to the whole value (i.e.
100 L/min ± 1%)
• Absolute accuracy – the quantity of the error (i.e. 100 ± 1 L/min)
Another common problem associated with accuracy is that it may also be subject
to what can only be described as ‘specmanship’ – an attempt to make the specification
appear better than it really is.
To illustrate this problem, consider three flowmeters:
The URL is defined as the highest flowrate that a meter can be adjusted to
measure – sometimes referred to as the Full Scale Deflection (FSD). Another term,
the Upper Range Value (URV) is defined as the highest flowrate that the meter is
adjusted to measure. In this example, each meter has a URL of 100 L/min, and is
calibrated 0 to 50 L/min.*
For the percentage of span instrument, the absolute error is determined at the 100%
span reading, and then used to determine the accuracy at lower flow rates. Since the
* In reality, few meters will actually measure down to a zero flow rate and, indeed, usually have some
form of low flow cut-off limit below which the readings are not considered to be reliable.
Measurement Considerations 39
Accuracy = 1% of span
100% of
span 50 L/min ±0.5 L/min = 1%
= ±0.5 L/min
FIGURE 3.6 In the percentage of span instrument, the absolute error is determined at the
100% span reading, and then used to determine the accuracy at lower flow rates.
span is 50 L/min the absolute error would be ±1% of 50 = ±0.5 L/min. Consequently,
the accuracy of the meter at 50 L/min would be 50 ± 0.5 L/min = ±1%. And at
25 L/min the accuracy at would be 25 ± 0.5 L/min = ±2% (Figure 3.6).
For the percentage of reading instrument, the absolute error is determined with the
actual reading, and varies with the flow rate. The absolute error at 50 L/min is ±1%
of 50, or ±0.5 L/min. The absolute error at 25 L/min is ±1% of 25, or ±0.25 L/min.
This means the meter has a constant accuracy of ±1% at all readings (Figure 3.7).
Accuracy = 1% of reading
100% of
Absolute error = 1% of 50 L/min
span
= ±0.5 L/min
FIGURE 3.7 In the percentage of reading instrument, the absolute error is determined at the
actual reading, and varies with the flow rate.
40 The Concise Industrial Flow Measurement Handbook
Accuracy = 1% of URL
100% of
Absolute error of ±1 L/min at 50 L/min
span
= 2%
FIGURE 3.8 In the percentage of URL instrument, the absolute error is determined at the
URL and then used to determine the accuracy at lower flow rates.
For the percentage of URL instrument, the absolute error is determined at the
URL and then used to determine the accuracy at lower flow rates. The absolute error
would be ±1% of 100, or ±1 L/min. The accuracy of the meter at 50 L/min would be
50 ± 1 L/min, or ±2%. The accuracy at 25 L/min would be 25 L/min at ±1 L/min,
or ±4% (Figure 3.8).
In the above example, all three meters would have the same accuracy, ±1%, when
calibrated at the URL, 100 L/min.
LRL URL
Minimum Maximum
Flow rate
Flow range
FIGURE 3.9 Flow range is the difference between the maximum and minimum flow rates
over which a meter produces acceptable performance within the basic accuracy specification
of the meter.
Measurement Considerations 41
LRL URL
0.3 m/s 12 m/s
Flow rate
Flow range
FIGURE 3.10 Measuring range of a magnetic flow meter might be 0.3–12 m/s within an
accuracy of 0.3%.
For example, the measuring range of a magnetic flow meter might be 0.3–12 m/s
within an accuracy of 0.3% (Figure 3.10).
For flowmeters that exhibit a minimum flowrate, the flow range is thus the interval
from the minimum flow rate to the maximum flowrate. If the meter does not exhibit
a minimum flow rate (very unlikely), the flow range is the interval from zero flow to
maximum flow.
The flow range is often (erroneously) referred to as rangeability.
3.7.2 Turndown Ratio
The turndown ratio is the ratio of the maximum flow rate to the minimum flow
rate for a measuring range that is within a stated accuracy. In the example of the
magnetic flow meter, given above, the measuring range extends from 0.3 to 12 m/s.
Consequently, the turndown ratio is 40:1 – within an accuracy of 0.3. If the measuring
range were extended from 0.2 to 12 m/s, within a reduced accuracy of 0.5% the
turndown ratio is 60:1. It is, therefore, meaningless to express the turndown ratio
without a specified accuracy.
3.7.3 Span
The term span relates to the flowmeter output signals and is the difference between
the upper and lower range values assigned to the output signal.
Again, in the example of the magnetic flowmeter having a 4–20 mA analogue
output the upper and lower range values might be assigned as:
The span is thus the difference between the two values, that is 8 – 3 = 5 m/s
(Figure 3.11). The minimum span is the lowest flowrate able to produce a full-scale
output and the maximum span is equal to the maximum range of the sensor.
3.7.4 Rangeability
The term rangeability is often used very loosely. By definition rangeability is a
measure of how much the range of an instrument can be adjusted and is defined as
the ratio of the maximum flow range (maximum span) and the minimum span.
42 The Concise Industrial Flow Measurement Handbook
4 mA 20 mA
3 m/s 8 m/s
Flow rate
Flow range
FIGURE 3.11 Span relates to the difference between the upper and lower range values
assigned to the output signal.
However, it is also often confused with the turndown ratio and users should be
careful as to what is actually meant when the terms are used.
Total error
(inaccuracy)
Repeatability Random error
(precision)
Target
Systematic error
(inaccuracy)
5%
Actual response
Output
Straight line
20% response
FIGURE 3.13 A 10% input near the top of the scale results in an output of only 5%. However,
when lower down the scale, the same 10% input results in an output of 20%.
3.8.1 Repeatability
Repeatability is thus defined as how close a second measurement is to the first, under
the same operating conditions and the same input. This measurement can also be an
indication of instrument consistency.
In some cases, repeatability is considered more important than accuracy.
3.8.2 Linearity
Linearity is a term that may be used for instruments that give a reading
approximately proportional to the true reading over their specified range.
Linearity refers to the closeness within which the meter achieves a truly linear or
proportional response – and is usually defined by stating the maximum deviation
or nonconformity for example ±1% of flow rate, within which the response lies
over a stated range.
The biggest danger associated with nonlinearity is that assumptions may be made
judged on a single measurement. As illustrated in Figure 3.13, a 10% input near the
top of the scale results in an output of only 5%. However, when lowering down the
scale, the same 10% input results in an output of 20%.
2.0%
Glycerine 200 cP
Glycerine 500 cP
1.5% Alcohol
Water
Polywolframate solution
1.0%
0.5%
0%
-0.5%
-1.0%
Specified accuracy
-1.5%
-2.0%
0.1% 0.2% 0.3% 0.4% 0.5% 0.6% 0.7% 0.8% 0.9% 1.0%
Flow in kg/s
FIGURE 3.14 Typical flowmeter envelope of a meter having a 10:1 turndown with an
uncertainty of ±1% of reading at a confidence level of 95%.
8.0%
6.0%
4.0%
2.0%
Qmin Qtransition Qnormal Qmax
0.0%
2% 20% 50% 100%
-2.0%
-4.0%
-6.0%
-8.0%
FIGURE 3.15 Envelope commonly used in the specification of water and gas meters.
Measurement Considerations 45
The envelope also includes an indication of the uncertainty spread for a variety of
different media. This is a reasonable performance for a flowmeter and would probably
satisfy many requirements in industry.
Figure 3.15 shows another type of envelope that is particularly common in the
specification of water and gas meters. Here, the meter has an uncertainty factor of
±2% of rate from full flow down to 20%. Below this value, the uncertainty is ±4%
of flow rate, down to 2% of range.
In practice, a meter might have more steps in its envelope.