Task Duration Start Date End Date

Project Initiation 15 days 01-May-24 15-May-24


Analysis of Speaker Issue 20 days 16-May-17 05-jun-24
Research and Development 60 days 06-jun-24 05-Aug-24
Testing Alternative Materials 30 days 06-Aug-24 07-Sep-24
Prototyping New Laptop Design 45 days 07-Sep-24 22-Oct-24
Manufacturing Process 75 days 23-Oct-24 08-Jan-25
Quality Assurance and Testing 20 days 9-Jan-24 28-Jan-25
Implementation of New Laptop 15 days 1-Feb-25 15-Feb-25
Feedback Collection and Review 15 days 16-Feb -25 01-Mar-25
Final Adjustments and Improvements 15 days 02-Mar-25 16-Mar-25
Project Closure 10 days 17-Mar-25 27-Mar-25

1-May-17 5 days
6-May-17 10 days
16-May-17 20 days
5-Jun-17 15 days

Manufacturing Process
20-Jun-17 10 days
30-Jun-17 30 days
30-Jul-17 15 days
14-Aug-17 10 days
24-Aug-17 5 days
29-Aug-17 7 days
5-Sep-17 3 days
15-Jan-17 6-Mar-17 25-Apr-17 14-Jun-17 3-Aug-17 22-Sep-17
The Gantt chart plays a pivotal part in the purpose of laying a rudder to execute

strategically a mission of repair that the MSI Laptops Eclipse speaker problem is causing. It

provides a framework for scheduling and delimitation of the best endeavour to sprinkle events at

the right time and allow an appropriate allocation of resources as well as the timely completion

of tasks. The Gantt chart outlined in the given task specifically addresses the speaker problem in

a way that breaks down the problem into stages that are interconnected and mutually dependent,

which is aimed at attaining the overriding goal of enhancing product quality and regaining

customer satisfaction.

Launching the project, the initiation phase includes doing many important tasks to set the project

on the right track, with these tasks including creating the charter and formulating a specific Gantt

chart. Here, the stakeholders get together and conjointly determine the project's purpose, goals,

and end outcome. This is a crucial stage that will be used for the upcoming activities. Through

creating a systematic plan that is also carefully carved out to this day-dream Gantt chart, we can

be sure to stay within the set boundaries and agenda.

Further, into the analysis phase of the project, an inspection of the audio speaker problem flaws

will happen followed by a detailed examination of primary causes and secondary factors. Issues

like device design, component quality or manufacturing process become the main points of

investigation for getting the essential knowledge behind the problem The obtained insights

therefore serve as grounds for the suggested remedial measures and solutions, which in turn
prompt the project to take the steps which lead to the effective problem solving without

unnecessary delays.

Entering the design phase, the solutions are constituted and formulated keeping in mind all the

insights related to the analysis phase. Teams form temporarily, taking the rich experience of the

seasoned members and an explorative approach of the novice, resulting in the creation of

detailed plans that showcase the architecture, functionality, and features.

This so-called development stage represents the necessary operationalization of ideas using

testing and finally accretion into physical products, instruments, or systems. This stage consists

of the implementation of both the front-end and back-end, with a strong emphasis on modern and

efficient technologies to fulfil the best performance requirements. Main activities such as coding,

testing, fixing bugs, and integration are as critical as the final step of producing the actual system

or the Beta version.

In the meantime, making user authentication solid is the most pressing part, as this defends the

info security of the system. The project teams are foolproofing to get the system authenticated

after watching the system through the processes of many tests and validation. They ensure that

the system meets rigid security standards and whatever regulations are required.

As the development is in the final stage of its completion, the project team enters the testing and

quality control stage where both the functionality and reliability of the proposed plan go through

thorough inspection. During completely operated tests and assortments, the teams can recognize
and eliminate any shortcomings before the final product which has to be met and even exceed

quality standers and users’ expectations.

On the successful verification of the testing stage, the implementation phase begins, and the

solutions installation process hits the end-users and stakeholders. The stage will be dedicated to

the detailed design and the coordination of activities between different structures, to ensure a

smooth transition from current systems to new solutions.

The whole way through the project lifecycle, the Gantt chart becomes a crucial tool for Project

Management and Supervision, which creates a guideline for the completion of the task that later

will be followed by the Project Team. Via visualization of work activities and milestones, the

Gantt chart offers an opportunity to allocate and monitor resources effectively besides being able

to track progress and ultimately make sure that the project is in line with the predefined time

framework and the set objectives.

In short, a Gantt chart becomes the key tool that the initiative 'Strategic plan to tackle the audio

speaker problem in the Eclipse line-up developed by MSI Laptops' uses to effectively guide its

users. With the intricate work use of contract agreements, and execution of the plan, the project

can ensure that we build superior solutions for product quality, customer satisfaction, and brand

reputation.
5.2.2 Self-regulations mechanisms

Speakers’ impediment in Seceptron, Eclipse series of MSI laptops, the regulators in the

first place are what is required to get high data accuracy, robust system reliability and last but

certainly not the least customer satisfaction. The mandatory audit of the management system can

be a way to check the accuracy of the recorded data and confirm its compliance with the

marketing standards. Through regular audits, any nonconformance or improvement avenues can

be quickly identified and responded thus leading to improved functionality and operation of the

system. In the same vein, the introduction of a feedback mechanism translates to a scenario

where administrators can have reports or issues from users which are pivotal in in-service

improvement and maintenance as well as increasing the integrity and reliability of the system.

Such feedback mechanism not only leads to better functioning and accuracy of the system but

also helps to create a higher trust level of the end-users. A powerful self-regulatory system

imperativeness to create large customer bases and achieve success for a long period.

5.2.3 Build and maintain support

A viable way to address an audio speaker problem with the Eclipse models from MSI

Laptops is via establishing and maintaining a customer service paradigm. It is crucial to integrate

intuitive communication properties that will simplify the log-on procedure and make the entire

user experience more interesting and rewarding. Implementing an easy communication channel

with the users can develop satisfaction like shock and will also boost the advantages of utilizing

the system. Direct marketing about maintenance built-in support uplifts the system’s goodwill

and brand personality in the market and among the users at the same time. In addition, if we put

in place a comprehensive communication strategy that helps keep all the stakeholders informed
throughout the project, the members of the community will be involved and engaged in the

project. Through tracking communications between stakeholders and implementing any

recommended changes, MSI Laptops would empower them to ensure that user concerns are

addressed and the system reconciled as it is deemed appropriate. Thus, reinforcing coping

mechanisms and providing clients with quality tools for communication are keys to solving the

audio speaker problem and ensuring product quality and client satisfaction.

6. Curriculum Components

The walk-through of the stepwise process of resolving the issue with the speakers of MSI

Laptops’ Eclipse series of laptops by just passing through the X Curriculum sequence

accompanied by the different concepts and subjects seems to be straightforward. Moreover, the

taxonomy of the management innovation concepts that we will indeed provide by the assignment

might be the basis to come up with historical data on the existing performance levels as well as

the driving factors behind the technological model choice. Strategy management centres on

principles, whereas strategic thinking helps build great power positions and long-term

development goals. While the use of technology in classes "Marketing Strategies" is a mandatory

part of creating genius and truly universal business plans, it is indeed a must. In the first place,

MSI was a memory-chip-dominant company, so it had designs as well as techniques that it

needed to use to get rid of its competitors.

If we are talking about successful business, the very important issues are good leadership and

using it together with new technologies and business problems must be solved by more

involvement of creativity, innovative thinking, and strategic management. Through analysis of


the management processes and governance mechanisms, managers learn the meteorological

process and its accomplishments on the strategic goals. I will explore the market execution that

has different strategies and product development by new technologies and innovations and use

the resources well. While Duhaime, Lyles and Hitt concede that problem finding and resource

matching are key components of the curriculum, strategies designing, which is also part of the

curriculum, are more important because strategy construction leads to solution finding.

What’s interesting is that while designing their product, it’s static made up of the four-step

market need and the progressive tech. The research demonstrates the strategic plan defining the

solutions for the firm's existing issues and then assuring the successful performance and

profitability in the targeted market. Phase I of our strategy plan will be looking into market

supervision as well as innovation, but all the plans will be concentrated on the audio speakers’

issues and MSI Laptops’ brand image enhancement as a leader in the industry.

7. Review and summary

Reviewing the performance test results this report presents, there is no doubt that interventional

strategy is complex and should involve using a variety of approaches. Nevertheless, the above-

mentioned issues still don’t frighten MSI anymore as today it is the concrete motivation from the

early years that keeps it in the market. Humanize the given sentence: The sample portrayal of

the company’s capability for overcoming hurdles and integrating new technology is proof

of MSI’s contribution to the technological revolution. The report highlights the firm's should to

evolve with the market demand realise its niche in the industry and strategically implement a

plan that boosts MSI's status.


The strategic plan will be the focus of this project and highlight the different areas requiring

attention: strategic management principles and resource allocation. The MSI plan includes both

intellectual property plans as it leaps to the production line in the process of technology

management and innovation. The emphasis is on the spotlight of the difficulties of business

distance when meeting new business environments, and technology use in business case

scenarios