Professional Documents
Culture Documents
Planning Scheduling Monitoring and Contr-6
Planning Scheduling Monitoring and Contr-6
Time now
(Data date)
Activity 1
Activity 2
Activity 3
Act. 2.1
Act. 2.2
Act. 2.3
Act. 2.4
216
Baseline
Time now
(Data date)
Activity 1
Activity 2
Activity 3
Act. 2.1
Act. 2.2
Act. 2.3
Act. 2.4
eliminating the schedule variance, i.e. the remaining work is re-scheduled with
the current actual cost and earned value retained. The customer should be
advised prior to (and may need to approve) re-planning.
Re-planning should only be considered in two instances:
217
Planning, Scheduling, Monitoring and Control
218
Baseline
Additional work*
Additional detail
Re-set budgets
Baseline maintenance √ √ √ ×x x× x×
Re-planning √ √ √ √ x× x×
Re-baselining √ √ √ √ √ √
219
Planning, Scheduling, Monitoring and Control
220
Performance
reporting
Chapter 22
221
Planning, Scheduling, Monitoring and Control
In general, the variance analysis techniques are simple to do and understand, but
they are backward-looking, often with no way of enabling projections and
forecasts. Performance analysis techniques are harder to set up and run, but do
have these forward-looking qualities. Most sophisticated projects will run both
forms of performance analysis, as even these are complementary and measure
different things. Variance analysis techniques are used to complement and help
communicate where necessary or useful.
222
Performance reporting
223
Planning, Scheduling, Monitoring and Control
224
Performance reporting
YEAR
Month Month Month Month
W1 W2 W3 W4 W5 W6 W7 W8 W9 W10 W11 W12 W13 W14 W15 W16 W17 W18 W19
Activity 1 Complete
If a project is perfectly on schedule, then the drop line remains vertical. Thus
the deviations clearly indicate which activities are ahead and which are behind.
Whilst this is a good way of looking at the detail, it is not adequate for complex
logic-linked schedules.
225
Planning, Scheduling, Monitoring and Control
• It is dificult to change the schedule, add data etc. Adding a new activity may
not be shown in a logical position if this is not done in scheduling software.
• Ultimately the schedule will not be a tool for proactively managing time, as it
will have become unrepresentative of a realistic approach to the work.
• Becomes even more unrealistic if re-sequencing takes place.
• Activity-based method that does not measure ‘work’.
• It measures time, but has no measure of cost versus value.
226
Performance reporting
Weeks 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15
Task one
Task two
Task three
Task four
Task five
Task six
Task seven
Task eight
Activity count
Activity count
Planned 1 2 2 2 3 4 3 3 3 3 5 5 6 6 4
Actual 1 2 2 2 3 4 2 3 2 0 2
Planned activity
Actual progress
227
Planning, Scheduling, Monitoring and Control
60
50
40
30
20
10
fix
fix
fix
1 st
fix
2 nd
completed
Units
ions
E 1 st
2 nd
ns
tio
tit
M&
M&E
rti
Par
Pa
Time
229
Planning, Scheduling, Monitoring and Control
230
Performance reporting
• May be used where environmental concerns limit usage (for example, lorry
movements in built-up areas).
231
(Project Name) CVR report
VALUE - CURRENT CONTRACT POSITION VALUE - FORECAST
233
Planning, Scheduling, Monitoring and Control
234
Performance reporting
235
Planning, Scheduling, Monitoring and Control
236
Performance reporting
Contract price
Management
Performance measurement baseline
reserve
Planning
Work packages
packages
237
Planning, Scheduling, Monitoring and Control
22.5.2.4.4 Risk
Risk is the budget allowed for known unknowns. As noted above, there is no
practical beneit in measuring risk budget, as there is not a 100% chance of it
being earned, and so it may distort performance measurement. However, it is
sometimes required to be included for completeness. There are a number of
ways of spreading the budget for risk. One way is across the remaining project
time, but that requires adjustment at every progress update. Alternatively, it can
be held in a ‘risk pot’ at the end of the project. In any event, risk money cannot be
earned; it can only be transferred into other work packages, in line with the risk
and change process.
238
Performance reporting
In either case a protocol must be agreed, but the second option is likely to be the
simpler.
239
Planning, Scheduling, Monitoring and Control
Planned value
Work
Time
240
Performance reporting
Planned value
Work
Earned value
Time
Note: It will be necessary to allow for accruals in the cost collection system.
Once the actual costs have been added to the schedule, the cumulative
actual costs can be plotted as shown in Figure 22.10. In the diagram, costs are in
Planned value
Work
Actual cost
Earned value
Time
241
Planning, Scheduling, Monitoring and Control
excess of what should be expected which would be parity with the earned
value line.
Planned
Work
Cost
Schedule variance
Actual cost variance
Progress Time
242
Performance reporting
600
100,000
400
Schedule variance
50,000
Cost variance
200
0 0
-200
-50,000
-400
-100,000
-600
-150,000 -800
Week 4
Week 8
Week 24
Week 28
Week 32
Week 44
Week 48
Week 64
Start
Week 12
Week 20
Week 36
Week 40
Week 52
Week 60
Week 16
Week 56
EVA measures schedule performance in terms of value as seen, but also in terms
of time: time variance can be calculated or read off the graph as in Figure 22.13.
This is the difference on the time axis between the quantity of work achieved to
date, or earned value, and the corresponding quantity on the planned value curve.
Measuring and expressing delay in this way may help to give an alternative
view of progress. It will also not suffer from the issue, already noted, that schedule
performance index (SPI) and SV tend towards parity as the project nears
243
Planning, Scheduling, Monitoring and Control
Planned
Work
Progress Time
completion. (Although it has been stated that this is a law in earned value
analysis, in reality we should expect project managers to be aware of approaching
completion dates!).
244
Performance reporting
Cost performance index (CPI) is the ratio of earned value over actual cost. A
igure greater than 1.0 indicates that the actual cost of the work achieved cost
less than planned.
CPI greater than 1 indicates a cost under-run
CPI equals 1 indicates on budget
CPI less than 1 indicates a cost over-run
SPI and CPI can usefully be plotted against each other to create a ‘Bulls eye’
chart, as shown in Figure 22.14.
150%
Trend
Period - 3
125%
Productivity (CPI)
Period - 2
100% Period - 1
This Period
75%
In Period
50%
50%
75%
100%
125%
150%
Performance (SPI)
245
Planning, Scheduling, Monitoring and Control
The shading indicates the BRAG rating that may also be allocated to the KPIs,
where
B=Blue: Performance over that expected (and needs investigating)
R=Red: Performance seriously below expected (needs immediate corrective
action)
A=Amber: Performance below expectation (needs planning or corrective action)
G=Green: performance within expectations (no action required)
Estimate at completion (EAC): The sum of the actual costs to date plus the
estimate to complete (ETC) (‘What is the project likely to cost?’).
EAC = Actual cost + ETC
Original Duration
(OD)
P lanned
Time
variance
Progress Time
246
Performance reporting
It has been shown (Webb, Alan (2003, 26) Using Earned Value, Gower) that
mathematically the formula for EAC can, in fact, be simpliied to:
Again, It has been shown (Webb, Alan (2003, 26) Using Earned Value, Gower)
that mathematically the formula for ETTC can, in fact, be simpliied to:
Proportional to
progress of a APPORTIONED EFFORT
section of work
247
Planning, Scheduling, Monitoring and Control
amount would be earned for Useful and clearly understood repeat items or products
units
Work that is necessary for Suitable for supervision Only appropriate for activity
Apportioned
248
Performance reporting
• Certainty of project position: what work has been achieved against plan; what
it has cost to reach that level of achievement.
• Whether the work achieved represents good value for money (i.e. has been
achieved eficiently).
• Gives early warning of whether the project is likely to inish on time and/or on
budget.
• Improved decision making: guides attention to problem areas that need
management decisions.
• Provides the basis for informed cost and/or time recovery actions.
• Ensures that a robust plan is established at the outset of the project.
• Management of scope creep through the change control system.
• Ensures cash-low is measured properly and optimised.
• Provides corporate governance (when done across the organisation).
• Business beneits include turnover, proit and cash being achieved on time or
as soon as practicable.
249
Cost control
Chapter 23
251
Planning, Scheduling, Monitoring and Control
252
Cost control
These changes will highlight cost variance. This is the difference between the
assumed costs of the project or activities in the performance measurement
baseline at the point of reporting, and the actual costs that the project is committed
to at that same point.
A recognised best practice around cost control is through the use of earned
value management where the cost performance index (CPI) is the key indicator
of project inancial performance. This process is described in detail insection
22.5.2. It is ideal for identifying where a project is not progressing eficiently.
253
Short-term
planning
Chapter 24
255
Planning, Scheduling, Monitoring and Control
Summary
schedule
Working
schedule
Method
3 Month Design Procurement Assurance
statement
look ahead tracker schedule tracker
tracker
4 week
look ahead
Sub
contractors
detailed plan
• the work planned over the next 3 or 4 weeks (with a strong emphasis on the
next week);
• the make ready needs for these activities (these are the start criteria for each
detailed task).
256
Short-term planning
257
Planning, Scheduling, Monitoring and Control
Design late
Procurement
Resources
Approvals
Optimistic planning
Late change
Altered priorities
MS not in place
Safety
258
Change
management
Chapter 25
• inside the project, such as risks impacting, adoption of wrong strategy, etc.,
where they will be funded from management reserve drawdown;
• outside the project, such as a new customer requirement, where they will
require additional funding;
• a change in legislation.
259
Planning, Scheduling, Monitoring and Control
• change in scope;
• changes in budgets;
• changes in timing of the project;
• changes in risks that are managed as part of the project;
• changes in expenditure.
Thus, it ensures that costs are known and that the supply chain receive fair
recompense for any additional work that they perform, whilst protecting the
client from paying for works that are not performed.
260
Change management
261
Raise change
request
Approval Initial
process evaluation
Provide Detailed
information evaluation
Update
change log
Update
baseline and Implement
budgets change
Update Communicate
reports change
262
Change management
263
Planning, Scheduling, Monitoring and Control
• unique ID number;
• status of the change;
• change description;
• detailed scope of the change;
• category of change;
• created by (the change originator);
• date raised;
• impact assessment – scope/budget/schedule/risk/safety, etc.;
• authority;
• funding/budget;
• decision: (approval/deferral/rejection) and date.
264
Change management
more information is required. Once that has been supplied, then the request
re-joins the process at detailed evaluation stage.
Once a change request has got through the initial evaluation, it proceeds into
the detailed evaluation.
This evaluation is usually carried out in a regular change review meeting. The
meetings would be attended by all the relevant parties on the project, but,
importantly, they require the project sponsor or authoriser for the change
request.
There are three possible outcomes for a change request:
• rejected;
• deferred;
• approved.
This section will address rejected and deferred (approved change being dealt
with in the next section).
265