Project : LIAO LIAO STORE

Location : U.P Town Center, Katipunan Ave., Diliman, Quezon City


Subject : Works Schedule
Date : April 16, 2024
WEEK 1 WEEK 2 WEEK 3 WEEK 4 WEEK 5
31 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30 31 01 02 03
ITEM SCOPE OF WORKS DURATION
OR WORK

A WALL PARTITION

1 CHB Double Wall 4

2 Dry wall Partition 3

3 Interior Partition 6

4 Plastering 8

B FINISHING WORKS
1 Waterproofing 3

2 Ceiling 8

3 Floor tiles 7

4 Wall Tiles 9

5 Painting wall 7

6 Painting Ceiling 7

7 Counter tops 3

8 Door Installation 2

C PLUMBING WORKS

1 Waterline 5

2 Sewer/Kitchen waste 5

D ELECTRICAL WORKS

1 Rough-in 7

2 Wire and Panel Installation 8

3 Light and outlet 5

E MECHANICAL WORKS

1 Aircon Installation 3