Professional Documents
Culture Documents
Quote For Unitile USF 1250 ND Bare Raised Access Floor System - Creation S Infra
Quote For Unitile USF 1250 ND Bare Raised Access Floor System - Creation S Infra
Bill To Ship To
CGST SGST
# Item & Description HSN/SAC Qty Rate % Amt % Amt Amount
1 USF 1250 HPL 1mm 600MM 73269099 172.00 4,915.00 9% 76,084.20 9% 76,084.20 8,45,380.00
SQM Sq.Mt
Supply of Unitile solid Filled
USF 1250 Grade,
600mmX600mmX35mm, Top
performance finish of Anti
static 1mm HPL with ESRG
Under structure Systems
height of 600 MM
2 Installation RAF Sq.Mt 995413 172.00 269.10 9% 4,165.67 9% 4,165.67 46,285.20
Installation Charges Sq.Mt
3 Unifold Panel SQM 73269099 40.68 3,430.00 9% 12,557.92 9% 12,557.92 1,39,532.40
Supply of Unitile solid Filled Sq.Mt
UNIFOLD UFP 1650 Grade,
600mmX600mmX30mm, Bare
Finish with ESRG Under
structure Systems height of
600 MM
4 Installation RAF Sq.Mt 995413 40.68 215.00 9% 787.16 9% 787.16 8,746.20
Installation Charges Sq.Mt
5 Air Flow Grill 76169100 30.00 5,700.00 9% 15,390.00 9% 15,390.00 1,71,000.00
Supply of UNITILE UAS Nos
600X600X35mm Powder
coated 46% Opening Air Flow
Grill with Aluminum Volume
Control Damper
6 Pedestal-600mm 73269099 55.00 175.00 9% 866.25 9% 866.25 9,625.00
Supply of Unitile ESRG Regular Nos
Pedestal Assembly - FFH
600mm (For Perimeter side
and Air Flow Grill)
7 Stringer 17X33mm 73269099 47.00 65.00 9% 274.94 9% 274.94 3,055.00
Supply of Unitile 17X33mm Nos
Box Stringer with CSK Screw
Sub Total 12,23,623.80
Total In Words
CGST9 (9%) 1,10,126.14
Indian Rupee Fourteen Lakh Forty-Three Thousand Eight Hundred
Seventy-Six Only SGST9 (9%) 1,10,126.14
Rounding -0.08
Terms & Conditions Total 14,43,876.00
1. Quoted price is for the supply and Installation of Unitile Raised Flooring
System.
2. Taxes - GST -18%
1
3. Payment - Supply - 100% against Advance
Installation - 100% after completion
4. Delivery- 3 to 4 Weeks against approved Drawing and PO
5. Local Transport Extra at actual. Authorized Signature
6. Unloading and shifting of material at job site on your scope only
7. This proposal is based on issuance of Site Drawing. In case of additional
material required over and above due to changes of dimension at site shall
be charged extra.
8. The Rates mentioned in the Work Order are for one-time Installation
only. Any realignment, removal, and refixing will be charged separately if
required to be executed.
9. The Installation at the site will be undertaken as per the fronts available
on site. Any delay due to other agencies will delay the Installation Schedule
and no Deductions will be accepted if the timelines of the Project are
extended due to the same..
10. Invoice to be raised against supplied materials only not wall to wall
measurement.
11.Installation charges Applicable for Chennai only