Sewage Itp
Sewage Itp
1.2 Document Submittal IF Exsist Compliance to Project's Contract, Prior to works DOS Form H R
Project Speces &
Specifications, Design Drawings and
BOQ &Codes
1.3 Approval Shop Drawing Relevant Codes & Standards Prior to works DWS Form H R
2-Matrial Stage
2.1 Precast Manholes B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.2 Curregated Pipes B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.3 Curregated Fitting B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.4 Manhole stairs B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.5 GRP Covers For Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.6 Solid Bloucks For Inspection Chamber B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.7 Warning Tap B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.8 Concrete For manhole Base B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.9 Rupper Strip B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.10 Internal Isulation for Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.11 External Isulation for Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.12 Sand For Bedding B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
2.13 Grout B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R
3-Inspection Stage :
3.1 Lining For Manhole And Pipe Lines As Per Sequence of work WIR H R
3.4 Bedding For Pipe line By Surveyor As Per Sequence of work WIR H R
3.5 Soil Replacment Under Manhole By Surveyor As Per Sequence of work WIR H R
3.6 Pour The Concrete Base For Manhole As Per Sequence of work CPR H W
3.8 Internal &External Insulation For Manhole As Per Sequence of work WIR H R
3.13 Install The Protective Sand Layer As Per Sequence of work WIR H R
3.15 Sand Cone Considered Every Bedding Layer As Per Sequence of work WIR H R
4-Test Stage