Sewage Network Inspection and Test Plan

Inspection Parties/Type of Inspection


Verifying ( Internal Checking ,Witness or Hold )
NO. Activity Reference Document Acceptance Criteria Frequency
Document
Contractor Consulatant

1-Document & Engineering Stage :

1.1 Material Submittal Prior to works MS Form H R

1.2 Document Submittal IF Exsist Compliance to Project's Contract, Prior to works DOS Form H R
Project Speces &
Specifications, Design Drawings and
BOQ &Codes
1.3 Approval Shop Drawing Relevant Codes & Standards Prior to works DWS Form H R

1.4 Method of Statement Prior to works DOS Form H R

2-Matrial Stage

2.1 Precast Manholes B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.2 Curregated Pipes B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.3 Curregated Fitting B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.4 Manhole stairs B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.5 GRP Covers For Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.6 Solid Bloucks For Inspection Chamber B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.7 Warning Tap B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.8 Concrete For manhole Base B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.9 Rupper Strip B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.10 Internal Isulation for Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.11 External Isulation for Manhole B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.12 Sand For Bedding B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

2.13 Grout B.O.Q Approval Submittal Compliance With Project Specification Prior to works MIR H R

3-Inspection Stage :

3.1 Lining For Manhole And Pipe Lines As Per Sequence of work WIR H R

Excavation bottom Level


3.2 As Per Sequence of work WIR H R
For Manhole And Pipe line (Civil)

Excvation Bottom Check


3.3 As Per Sequence of work WIR H R
For Manhole And Pipe Line By Surveyor

3.4 Bedding For Pipe line By Surveyor As Per Sequence of work WIR H R

3.5 Soil Replacment Under Manhole By Surveyor As Per Sequence of work WIR H R

3.6 Pour The Concrete Base For Manhole As Per Sequence of work CPR H W

3.7 Install the Manhole As Per Sequence of work WIR H R

3.8 Internal &External Insulation For Manhole As Per Sequence of work WIR H R

Project Specs,B.O.Q,ShopDrawing, Project Specs,B.O.Q,ShopDrawing,Relevant


3.9 Install The Manhole Stairs As Per Sequence of work WIR H R
Relevant Codes and standards. Codes and standards and method statement.

3.1 Install the Pipe Line As Per Sequence of work WIR H R

Leveling And Allignment For Pipe Line


3.11 As Per Sequence of work WIR H R
Installation By Surveyor then Fix With Sand

3.12 Test The Pipe Lines As Per Sequence of work WIR H R

3.13 Install The Protective Sand Layer As Per Sequence of work WIR H R

3.14 Install The Warrning Tape As Per Sequence of work WIR H R

3.15 Sand Cone Considered Every Bedding Layer As Per Sequence of work WIR H R

Back Filling &Compaction Layers Every 25 CM & Sand


3.16 As Per Sequence of work WIR H R
Con Every Laye considered

3.17 Install The Manhole Covers As Per Sequence of work WIR H R

4-Test Stage

4.1 Air Test For Pipes WIR H R

4.2 SlopTest By Water WIR H R

4.3 Water Test For Manhole WIR H R

Code Code Name


R Review
H Holdpoint
M Monitor
W Witniss