[QA] Plan
Project Name : Management Information System(MIS) for Indian Railway (Phase-I)
1.0 PURPOSE 4
2.0 ROLE & RESPONSIBILITY 4
3.0 RELATED DOCUMENTS 4
4.0 QUALITY ASSURANCE ACTIVITIES 5
4.1 PROCESS COMPLIANCE CHECK 5
4.2 WORK PRODUCT QUALITY CHECK 5
4.3 NON-COMPLIANCE RESOLUTION 5
4.4 QA REPORTING 6
4.5 ESCALATION 6
5.0 STAKEHOLDER INVOLVEMENT 6
6.0 MANAGEMENT OF QA WORK PRODUCTS 6
7.0 MONITORING OF QA ACTIVITIES 7
2.0 Goal
● In general, QA activities will be performed to manage good quality delivery to customer. To support the
goal, organization processes must be adhered to in System deployment.
QA Amit Dubey
● Develop QA plan
Responsible
● Conduct process compliance check
Process Users
● Participate in process compliance check as identified by QA
responsible.
Planning Process
● Project Plan
● QA Plan
● CM Plan
● MA Plan
● RSKM Plan
Design
● Design
Design
● Design Review Record
CM Process
● Configuration Status Report
Configuration Audit Report
Solution Deployment
● Traceability Matrix
● Functional Test
5.4 QA Reporting
There are three different reporting:
● Audit report (non-compliance): Audit result of non-compliances will be reported to project manager &
process users for resolution. It will be done within 7 days of conducting audit.
● Milestone reporting: NC details (total, open, closed) & Process compliance index (PCI) will be reported in
every milestone.
● QA status report: QA will report status of planned audit & completed audit & any issues such as non-
resolution of NC in project status meetings.
5.5 Escalation
Escalation for the unresolved NC will follow following rule:
● If NC is not resolved within 30 days, QA will discuss with responsible and try to get agreement on
another date.
● If NC is not resolved & QA understand that there is less chance of getting it resolved by process user, QA
will report it to Senior Management / EPG.