Rams Critical-Big Lift
Rams Critical-Big Lift
PROJECT DETAILS:
Project: MEERKAT + Area: CARNARVON, NORTHERN CAPE
Signature:
Date:
COMMUNICATE THIS SWMS TO ALL PERSONS INVOLVED IN TASK PRIOR TO WORK Overall Risk Rating After 4 Acute 3 High
COMMENCING Controls 2 Moderate 1 Low
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 1
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
1. Pre-Lift Lack of proper training and Risk of equipment failure or 4 Conduct thorough risk assessment 1
Preparation: certification of lifting collapse. and develop a detailed lifting plan.
equipment and crane.
Risk of load instability or Verify load weight and center of
Inadequate planning leading imbalance. gravity using appropriate tools.
to insufficient control
measures. Risk of collision or Inspect all lifting equipment for defects
entanglement. and ensure certification.
Incorrect assessment of load
weight and center of gravity. Risk of miscommunication Establish clear communication
leading to accidents. protocols and signals for lifting
Use of defective or operations
unsuitable lifting equipment.
Develop a lifting plan detailing the
Poor communication among sequence of tasks, roles and
lifting team members. responsibilities, communication
procedures, and emergency
protocols.
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 2
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
devices.
2. Setup and Inadequate ground stability Risk of crane tipping or Ensure ground beneath the crane is
Rigging leading to crane instability. overturning. stable, level, and capable of
supporting the load.
Improper rigging techniques Risk of load dropping or
causing load slippage or shifting during rigging. Rig the load securely using approved
failure. lifting accessories and techniques.
Risk of personnel being
Failure to establish exclusion struck by moving loads or Erect barricades or warning signs to
zones around the lifting area. crane components. restrict access to the lifting area.
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 3
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
manufacturer recommendations and
industry best practices.
3. Lifting Overloading of the crane or Risk of structural damage Monitor load weight and ensure it
Operations: lifting equipment. or failure due to does not exceed the crane's capacity.
overloading.
Failure to maintain control of Maintain constant communication
the load during lifting. Risk of dropped loads between crane operator and ground
causing injuries or property personnel.
Inadequate supervision and damage.
monitoring of lifting Use tag lines or guide ropes to control
operations. Risk of accidents due to load movement and prevent swinging.
lack of coordination or
Lack of visibility or supervision. Conduct a pre-lift briefing with the
communication between lifting team to confirm roles, signals,
crane operator and ground Risk of collisions or near and procedures.
personnel misses during lifting
operations. Communicate with the crane operator
or equipment operator using
standardized hand signals or radio
communication.
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 4
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
pinch points and swing areas.
4. Post-Lift Inadequate securing of the Risk of load shifting or Secure the load using appropriate
Procedures load after placement. falling after placement. restraints or fasteners after
placement.
Failure to inspect lifting Risk of using damaged or
equipment for damage or defective equipment in Inspect lifting equipment for damage
defects. future lifts. or wear and document any issues.
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 5
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
defects following the lifting operation.
Delayed response to Risk of further accidents or Provide first aid training to personnel
equipment malfunction or incidents during emergency and ensure adequate first aid supplies
incidents. procedures. are available.
Inadequate first aid training Risk of non-compliance with Establish clear reporting procedures
or supplies for treating regulatory reporting for incidents and near misses.
injuries. requirements.
Conduct regular drills and training
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 6
Control Measures - Steps To Respons
Risks R R
Task Steps Potential Hazards Follow ible
B A
Safety Checks & PPE Officer
NOTE: RB = Risk Rating before controls implemented - RA = Risk Rating after controls are implemented.
Failure to report and Risk of legal liability or exercises to practice emergency
document incidents properly financial penalties for failure procedures
to follow proper procedures
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 7
RISK ASSESSMENT
Step 1Determine Likelihood – What is the possibility that the effect will occur?
Likelihood Definition
Almost Expected to happen in A common and very possible
certain most circumstances. result
Likely Will probably occur in Known to have occurred and has
most circumstances. happened before
Possible Might occur at some Could occur and is likely it has
time happened before
Unlikely Could occur at some Not likely to occur
time
Rare May occur only in Very unlikely
exceptional
circumstances
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 8
Step 3 Determine the risk score Step 4 Record risk score (Note – Risk scores are only estimated and should not be
solely relied upon)
CONSEQUENCE
Score Action
LIKELIHO Insignific Minor Moderate Major Catastrop 4 URGENT – Act on and lower the risks immediately.
OD ant h ic A: Acute Demands immediate attention.
Almost 3 High 3 High 4 Acute 4 Acute 4 Acute 3
certain H: High Decisions required urgently by Management.
DOCUMENT NO: ACTIVITY: CRITICAL LIFT OPERATION REVIEW NO: 1 DATE: 05/02/2024
Authorised by: Site Manager Page 9