CHECKLIST FOR FORMWORK FIXING

Project:

Job No.:

Floor & Grid no.:

Date / Time of Inspection:

Contractor Engineer Inspection Date:

Name / Signature / Date:

CBRE Engineer Inspection Date: Time: To:


Re-inspection Date, if applicable: Time: To:
Checked by Description
Activity In of defects Re-inspection
STAGE SN. DESCRIPTION OF ITEMS TO BE CHECKED charge / X / X
/ X
1 Workmen unloading material shall wear hand gloves, mask
and goggles for dust and eye protection
2 Plywood should be film faced 12 mm shuttering ply-wood -
as per IS 4990 - BWP grade - testing for same to be done
from NABL approved laboratory for material approval
3 purpose
Plywood should be received with MTC for same lot
number and delivery challan
4 Plywood and formwork material shall be stored at the work
site in a building or a shed which is dry, leak-proof in such
a way as to keep about 150 mm to 300 mm clear above the
floor
5 Plywood for concrete shuttering work shall be dense,
smooth and the faces & back shall be free from harmful
Pre discoloration, pleats, overlaps, blisters and loose knots.
The edges shall be of smooth uniform finish.
6 Materials and components pertaining formwork shall be
always maintained in good condition and clean. (In case of
damages these should be repaired before reuse or replaced
with new ones)
7 Approval for scheme of centering shall be obtained well in
advance for formwork and supporting structure
8 Formwork should be sufficiently rigid during placing &
compaction of concrete and shall be such as to prevent loss
of slurry from concrete
9 Approval for scheme of centering shall be obtained well in
advance for formwork and supporting structure
10 All workmen shall wear hand gloves, mask and goggles for
skin, dust and eye protection
11 Working platform, climbing arrangements for checking
and working should be safe & okayed by EHS officer
Checked by Description
Activity In of defects Re-inspection
STAGE SN. DESCRIPTION OF ITEMS TO BE CHECKED charge / X / X
/ X
12 Staging should be done as per consultant approved
drawings and certified by EHS officer
13 Formwork release agent applied should be oil based -of
approved make, surfaces of formwork should be coated
with suitable mould oil which acts both as a parting agent
and also gives surface protection
14 Formwork should be sufficiently rigid during placing &
compaction of concrete and shall be such as to prevent loss
of slurry from concrete
15 Ensure that position and dimension of the footing, wall,
During beams, slab, sunk, staircases, chajjas, column etc. are as
per the GFC drawing
16 Ensure that slope (if any) is as per the GFC drawing
17 Ensure that verification of sleeves / pipes / inserts in slab
/beams are as per MEP drgs.
18 Ensure that location and dimensions of cut outs, and shafts
are as per the GFC drawing and are rigidly fixed
19 Ensure that alignment is checked and correct
20 Ensure that plumb/verticality is checked & ok
21 Ensure that all tie rods are secured with PVC pipes, PVC
caps & wing nuts
22 Ensure that horizontal & vertical bracings & supports are
as per scheme drawing
23 Ensure that shuttering top is in level
24 Ensure that shuttering surface is clean, free from cement
slurry / concrete laitance and other dirt
25 Ensure that on plywood timber/steel plate surface all
holes/gaps are sealed and is leak proof
26 Position of stopper / construction joint and rigidity of same
should be ensured
27 Cover spacer (kanda) is provided at the top of columns and
walls
28 De-shuttering after concrete should be done only as per IS
456 timelines & after approval from Engineer in charge
29 De-shuttered plywood and other supports should be kept
Post properly stacked and free from dampness
30 Tools and equipment's used shall be cleaned after each
days work and prior leaving the workplace unwanted
materials shall be disposed in waste bin

Checked by (J4C) Name & Sign:

Checked & Verified by (CBRE) Name & Sign :


Checked by Description
Activity In of defects Re-inspection
STAGE SN. DESCRIPTION OF ITEMS TO BE CHECKED charge / X / X
/ X
Remarks: