Professional Documents
Culture Documents
Screenshot 2023-10-06 at 7.57.54 AM
Screenshot 2023-10-06 at 7.57.54 AM
Engineering College
Department of Civil Engineering
Div: 7th Sem Civil
➢ A)Storage headworks
➢Dam is constructed on the river for the purpose of creating a large storage
(reservoir).
➢The storage works are required to store the water on a non-perennial river or
on a river with inadequate flow throughout the year.
➢On the other hand, in a diversion head works, there is very little storage.
Diversion Headworks
➢If the storage on the upstream of a diversion head works is significant, it is
called a storage weir.
TOPICS:
➢ WEIR AND BARRAGES
➢EXIT GRADIENT
➢To control the entry of silt into the canal and to control the
deposition of silt at the head of canal.
➢The elevation of site should be higher than the area to be irrigated for
gravity flow.
➢Site should be close to the crop land to minimize loss of water from canal.
2) Divide Wall
4) Approach Channel
5) Fish Ladder
7) Silt excluder
8) Silt ejector.
➢ Barrage is practically a low weir with an adjustable gate over this low weir.
Heading up of water is affected by gate.
Weir and Barrage
Weir
Weir
Barrage / Canal Head Regulator
Barrage
Comparison Between Weir & Barrage
Types of Weir
As per shape of crest
c) Ogee-type weir
➢ROCKFILL WEIRS.
➢Shutters are provided at the crest, which are dropped during floods so as to
reduce afflux.
➢Water is ponded up to the top of the shutters during the rest of the period.
➢Vertical drop weirs were quite common in early diversion headworks, but these
are now becoming more or less obsolete.
ROCKFILL WEIRS
ROCKFILL WEIRS
➢ In a rockfill type weir, there are a number of core walls. The space between the
core walls is filled with the fragments of rock.
➢ A rockfill weir requires a lot of rock fragments and is economical only when a
huge quantity of rock fill is easily available near the weir site.
➢ It is suitable for fine sand foundation. The old Okhla Weir across the Yamuna
river is a rockfill weir.
➢ It is used where difference in weir crest and downstream riverbed is not more than
3 m.
➢Hydraulic jump is formed when water passes over the sloping glacis. Weir of this
type is of recent origin.
CONCRETE GLACIS OR SLOPING WEIRS
➢ Concrete sloping weirs (or glacis weirs) are of relatively recent origin.
➢ The crest has glacis (sloping floors) on u/s as well as d/s. There are sheet piles
driven up to the maximum scour depth at the u/s and d/s ends of the
concrete floor.
➢ Sometimes an intermediate pile is also driven at the beginning of the u/s glacis
or at the end of d/s glacis.
➢ The main advantage of a sloping weir over the vertical drop weir is that a
hydraulic jump is formed on the d/s glacis for the dissipation of energy.
➢ Therefore, the sloping weir is quite suitable for large drops
hydraulic jump
Barrage
➢When the water level on the upstream side of the weir is required to be
raised to different levels at different time, then the barrage is
constructed.
Gate
Open
Closed
Divide Wall
➢A divide wall is constructed parallel to the direction of flow of river to separate
the weir section and the under sluices section to avoid cross flows.
➢The Divide Wall is a long wall constructed at right angle to the weir or barrage, it
may be constructed with stone masonry or cement concrete.
➢On the upstream side, the wall is extended just to cover the canal regulator
and on the down stream side, it is extended up to the launching apron.
Divide Wall
Function of Divide Wall
(a)To form a still water pocket in front of the canal head so that the suspended silt
can be settled down which can be cleared through the scouring sluices from
time to time.
(b) It controls the eddy current or cross current in front of the canal head.
➢For the movement of the fishes along the river, the fish ladder is essential.
➢In the fish ladder, the baffle walls are constructed in the zigzag manner and the
velocities of flow within the ladder does not exceed 3 m/s.
➢The width, length, and height of the fish ladder depends on the nature of the
river and the type of the weir or barrage.
Fish Ladder
➢The Fish Ladder is provided just by the side of the divide wall for the movement
of fishes(from U/S to D/S and D/S to U/S).
➢The suspended silt goes on the depositing in front of the canal head regulator.
When the silt deposition becomes appreciable the gates are opened and silt
and muddy water flows towards the downstream side through the scouring
sluices.
➢It consists of a number of piers which divide the total width of the canal into a
number of spans which are known as bays.
➢The gates are operated from the top by suitable mechanical device.
➢A platform is produced on the top of the piers for the facility of operating the
gates. Again, some piers are constructed on the downstream side of the canal
head to support the roadway.
Canal Head Regulator
Canal Head Regulator
l
Canal Head Regulator
Canal Head Regulator
Canal Head Regulator
Silt Excluder
➢When still pocket is formed in front of the canal head by constructing the
divide wall, then it is found that the lower layer of water contains heavy silt
➢The fine silt is very fertile, and it may be allowed to enter into the canal. But
➢To eliminate the suspended heavy silt, the silt excluder is provided. It consists
of a series of tunnels starting from the side of the head regulator up to the
divide wall.
Silt Excluder
➢Silt excluders are constructed on the bed of the river.
➢The clearer water enters the head regulator and silted water enters the silt
excluder.
➢So the silt is therefore removed from the water before in enters the canal.
Silt Ejector Silt Excluder
Silt Excluder
Silt Excluder
Silt Excluder
Silt Ejectors
➢Silt ejectors, also called silt extractors, are those devices which extract
the silt from the canal water after the silted water has traveled a
➢These works are, therefore, constructed on the bed of the canal, and
a) By piping or undermining
b) By uplift pressure
The combined effect of surface flow and sub-surface flow may cause the
failure of the weir or barrage.
Causes of Failure of weir or barrage on permeable foundation
➢The water from the u/s continuously percolates through the bottom of
the foundation and emerges at the d/s end of the weir or barrage
floor.
➢A hollow pipe like formation develops under the foundation due to hich
the weir or barrage may fail by subsiding. This phenomenon is known as
failure by piping or undermining.
➢When hydraulic gradient or exit gradient exceeds the critical value of
soil, surface soil at down end starts boiling first and is washed away by
percolating water.
U/S D/S
U/S D/S
Causes of Failure of weir or barrage on permeable
foundation
(i) Failure due to subsurface flow
a) By Piping or Undermining
U/S D/S
U/S D/S
Causes of Failure of weir or barrage on permeable foundation
➢If this uplift is not counterbalanced by the self weight of the structure, it
may fail by rapture.
Causes of Failure of weir or barrage on permeable foundation
U/S D/S
Causes of Failure of weir or barrage on permeable foundation
(i) Failure due to subsurface flow
(b) By uplift Pressure:
Causes of Failure of weir or barrage on permeable
foundation
(II) Failure by Surface Flow:
➢When the water flows with a very high velocity over the crest of the weir or over
the gates of the barrage, then hydraulic jump develops.
➢This hydraulic jump causes negative pressure on the d/s side which acts in the
direction of uplift pressure.
➢If the thickness of the impervious floor is not sufficient, then the structure fails by
rupture.
Causes of Failure of weir or barrage on permeable foundation
Negative
U/S D/S Pressure
Causes of Failure of weir or barrage on permeable foundation
(II) Failure by Surface Flow:
➢The gates of the barrage are kept open and the water flows with high velocity.
➢The water may also flow with very high velocity over the crest of the weir.
➢Both the cases can result in scouring effect on the d/s and on the u/s side of the
structure.
➢Due to scouring effect on the d/s and on the u/s side of the structure, its stability
gets endangered by shearing.
Causes of Failure of weir or barrage on permeable foundation
(II) Failure by Surface Flow:
(b) By Scouring During floods:
➢Sheet piles should be provided on the upstream side and the downstream side of
the impervious floor to increase to the length of percolating water.
➢As the length increases…the hydraulic gradient and exit gradient decreases.
Increase floor thickness
➢ Inverted filter should be provided with concrete blocks on the top so that
the percolating water does not wash out the soil particles.
Precautions Against Failure
Energy Dissipater Blocks