TIKARIA EXPANSION PROJECT, ACC Rev 1

HAZARD IDENTIFICATION RISK ASSESSMENT Doc. No. : ACC/TKP/HIRA/LNVT/


0001

MOS No. : ACC/TKP/MS/LNVT/0001


Title: Loading/Unloading of material by Crane Farana
Assessment Date: 4/1/2021

KEY POINTS:
1-All necessary permits to be obtained from ACC concerned person prior to work commences.
2-All persons must be Safety Inducted.
3-Mandatory job specific PPEs must be worn by all engaged person
4-Life saving talk must be conducted prior to start each shift, All person to be participate the task
5-All engaged person must be aware about their job, potential hazards and control measures
6-Rest Shelter to be provided for the workers
7-Welfare facilities to be provided according to workmen strength
8-Job specific Training to be provided, if required
9- Safety awareness signage to be displayed at site
10-Probability, Severity & risk Table is attached for reference

INITIAL RISK RESIDUAL RISK

Probability

Probability
Risk Level

Risk Level
Consequence

Severity

Severity
SN Job Steps Potential Hazards (who will harm) Current Control Measures Additional control measure Person responsible

1 Crane/Farana/ Topple of Operator, Area Assessment to be done before placement of crane/farana 2 4 8 One marshal man should be present with 2 2 4 Sire Engineer
trailer Placement crane/Farana, Property Area to be levelled and compacted flag or batten light, which is required for
Hitting to damage, All unwanted materials should be removed from unloading point control the equipment movement
existing Near by worker All lifting equipment must be checked by competent person Trailer engine to be in off condition and
properties All lifting equipment must be operated by identified and dedicated wheel chock to be provided
person FLRA must be prepared and discussed
Area should be isolated with barrication, Base plate for out rigger with concerned gang
must be available

2 Shifting of lifting Physical injury Workmen Tools and tackles to be shifted by only dedicated gang 2 2 4 Use Job Specific PPEs 1 2 2 Sire Engineer
tools & tackles at Tools and tackles to be shifted only as per required quantity and All workers should follow the ergonomics
unloading point according to material weight/approved lifting plan during handling of materials.
maintain body posture during shifting of tools tackles
use carrier vehicle for shifting of tools, if required
3 Releasing of Physical injury, Workmen A small ladder to be used for height approach till trailer bed 2 3 6 Before releasing of locking attachment 2 2 4 Sire Engineer
locking Fall of material Only dedicated person will perform the job from the material, must be slinging with
arrangement from from trailer bed Flash back arrestor must be installed at both point, if gas cutting used crane / farana hook
material for cutting of locking arrangement Gas cutting to be performed by only
Use job specific PPEs respective person
Only required person should be on trailer Area to be proper barricaded to avoid
Checked, colour coded slings to be used unwanted entry
Life line should be provided on trailer, if required
4 Slinging with Physical injury, Workmen, A small ladder to be used for height approach till trailer bed 2 3 6 Lifting plan to be signed by ACC 2 2 4 Sire Engineer
material Fall of material Property Only colour coded and tpi certified tools to be used for the job concerned person
from trailer bed damage All slinging activity to be performed by trained rigger/dedicated gang Area to be barricaded before start of
A soft packing to be placed for avoid to damage of slings activity
Tag line must be tied with material for control the swinging of Trailer driver must be present in his cabin
material and the trailer be in off condition

5 Unloading of Failure of lifting Workmen, Before slinging, make ensure all tools are to be in healthy condition, 2 4 8 Proper communication between signal 2 2 4 Sire Engineer
material from appliances, Property colour coded, checked by competent person man and crane operator while lifting the
trailer fall of material damage Strictly follow Approved lifting plan objects.
All rigging/slinging activities must be performed under dedicated Use tag lines to control the lifting load
rigger Use proper PPEs
Rigging Signal must be given by only dedicated person Area to be proper barricaded to avoid
make Ensure that the load is adequately Secured with slings, d unwanted entry
shackles and crane hook.
Lift within SWL
A soft packing to be placed for avoid to damage of slings
Use batten light, LED jacket during dark hour
Do not leave the object in suspended condition
If weather condition is not good, lifting activity must be postponed
Proper packing (wooden sleeper) to be provided under the material
for release the slings

6 Releasing of slings Physical injury, Workmen, Before release the slings make ensure the material have placed 2 3 6 Material resting/landing place must be 2 2 4 Sire Engineer
from material Fall of material Property securely clean/housekeeping
from resting damage A small ladder to be used for height approach for realesing of slings Area to be barricaded
point Only dedicated rigger will do the job A nylon rope or crane hook to be used for
After released the material, the tools and tackles should not throw lifting tools and tackles grounding
from height

7 Housekeeping Slips trip and Workmen Before lifting of material/equipment, material resting place to be 2 3 6 Adequate and correct stacking of 2 2 4 Sire Engineer
Falls cleaned from obstruction material materials.
All workers should follow the ergonomics during handling of Use proper PPE
materials

8 Work in dark hour slip/trip hazards Personal Injury Proper illumination to be provided at site 2 4 8 All connection to be checked by ACC 2 2 4 Sire Engineer
All power connection for illumination lamp to be get through concerned person
industrial plug top
All power cable must be in healthy condition

Prepared By Reviewed By Approved By