SWMS - PEB Dismantling & Floor Cutting
SWMS - PEB Dismantling & Floor Cutting
should be ensured
1.Follow PTW system
2.All required PPEs such as nose mask, Safety googles, safety
shoe safety harness & reflective jacket to be worn.
Existing PEB dismantling work with 1.Slip Trip & Fall, 3.Proper housekeeping to be followed
the help of boom lift. 2. Entanglement H 4.Ensure no overhead line crossing at work place. Site in
3. Fall from Height 5.The Boom lift and tools must get pre entry before using the charge/HSE
(Wall/Roof De-screwing, Roof/wall 4. Toppling of Vehicles same. personal
sheet removing, secondary supports 5. Material fall on persons 6.All documents related to vehicle to be available.
(i.e. purlins, sag rods, braces etc.,) 6. Hit Hazard 7.Signages and board to indicate machinery and manpower
removing, insulation, gutter, down 7. Electrocution activity is ongoing
take pipe removing. 8. Uneven ground & loose soil 8.Vehicle conditions to be checked before each activity start
9.Workers to be trained on hazardous material handling
10.Nose mask to be wear at all times while handling the dust
11.Regular Supervision Engineer/Supervisor
12.Engae trained personal only for doing work at height
1.It is ensured that vehicle is parked on even surfaces & should be
checked by execution & HSE team.
2.If required the area of loading/unloading shall be compacted if
surface is uneven by damping.
3.The mobile crane shall be inspected & TPI certified fit for use
4.Overloading shall be avoided.
5.When the load is lifted, sudden movement of vehicle shall be
avoided.
Personnel Summary
SUPERVISOR’S DETAILS
Supervisors Name & Qualifications: Name: Tamil Mannan
Experience: 10 years
Qualifications: B.E Civil
Supervisor’s Responsibilities: In addition to the above, the supervisor is to provide training in the use of this SWMS, issue PPE and provide training in the same, supervise the
work, ensure conformity with this SWMS, amend the SWMS when additional hazards are found (and if applicable, ensure all workers receive a
tool-box talk to discuss the control measures for the additional hazards).
DESCRIPTION OF TRAINING THAT HAS BEEN GIVEN TO PEOPLE INVOLVED WITH THE WORK
WORK ACTIVITY TRAINING: Ladder safety, Working at height, Manual handling & Operation of power tools, Vehicles, Road safety.
TICKETS, PERMITS or LICENCES REQUIRED to undertake this work (ie. Certificates of Competency, Confined Spaces etc):
Scaffolding & Power tools competency certificate
Serial Plant/Equipment Contractor Work Cover Plant Hazards Maintenance/service records and log books sighted
Registration No identified and by Principle Contractor prior to equipment being
(if applicable) controlled within used on site?
SWMS?
Yes No Sign Date
Cutting machine AB
Drilling machine
Screwing machine
Breaker machine
Hand tools
Boom Lift
Crane
ELECTRICAL EQUIPMENT USED DURING THE WORKS (Attach Electrical Equipment Register if applicable):
Item Tag/Item Testers Name & License Test Date Result Test Date Result
Number Signature Number
Cutting machine ____ /____ /____ ____ /____ /____
Drilling /
Hammering ____ /____ /____ ____ /____ /____
machine
Breaker
Machine
N.B. - All workers must be trained in the safe use of all chemicals and provided with the PPE required when using and storing these chemicals. Disposal is to be as per the waste disposal
methods in the MSDS. Spillage and leaks are to be cleaned up as per the spill/leak procedures identified in the MSDS.