P6 Abha Entertainment Complex

Client: Contractor: Assistant Engineer and Supervision Project Management Consultant


Consultant: and Engineer:

6ABHA09-INSPECTION TEST PLAN AND CHECK LIST FOR INSTALLATION AND TESTING OF CCTV SYSTEM
Review Sheet
Ref: 6ABHA09-ABHA-08-MBL-EV-ITP-00004 Revision 00 Date & Time 27 March 24
Client: Saudi Entertainment Ventures
Project Management Consultant and Engineer Saudi Consolidated Engineering Company - Khatib & Alami
Assistant Engineer and Supervision Consultant DAR International for Engineering Consultancy
Contractor Modern Building Leaders
Area / Location
Discipline:
☐ Civil ☐ Structural ☐ Architectural ☐ Mechanical ☐ GM ☐ Electrical ☐ HV ☐EV ☐ Plumbing ☐ Quality ☐ BIM
☐ Project Control ☐ Quality Management ☐ FLS/Safety ☐ General ☐ Other (specify if other):

Assistant Engineer and Supervision Consultant: DAR Engineering


Comments:
This ITP is Approved for Installation only for CCTV systems 1- ITP and checklist can be modified when required as
per site condition. 2- ITP inspection responsibility assignments can be modified when required as per site condition.
3- CCTV system and procedures shall be as per project specification, manufacturer recommendation. 4- Delivered
CCTV system and all its components will be properly packaged and adequately protected from
damage/deterioration during shipment, transportation, handling and storage. 5- Pre-testing: After installation,
align, adjust, and balance the system and perform complete pre-testing. Determine, through pre-testing, the
compliance of the system with requirements of the Drawings and Specification. Correct deficiencies observed in
pre-testing. Replace malfunctioning or damaged items with new ones, and retest until satisfactory performance
and conditions are achieved. Prepare forms for systematic recording of acceptance test results. 6- Report of Pre-
testing: After pre-testing is complete, provide a letter certifying the installation is complete and fully operable,
including the names and titles of witnesses to preliminary tests. 7- Final Test Notice: Provide a minimum of 10 days'
notice in writing when the system is ready for final acceptance testing. 8- Safety measurements and precautions
shall be covered.
1.The Method Statement , RA , ITP and Checklists related to Testing & Commissioning shall be submitted separately
referring to SEVEN template “SEV-QM-TEM-00090 Closed Circuit TV” 2.Contractor to follow the SEVEN template
“SEV-QM-PRO-00022-Installations Requirement Procedures” while preparing the Installation Checklists (CC) for
CCTV devices and cabling
Eng. Name: Ashraf Abdalrahim Signature: Date: 27 March 24
Submittal Status:

☐ A- Approved ☒ B- Approved with Comments ☐ C- Revise & Resubmit


Project Management Consultant and Engineer: Khatib and Alami
Comments:
Kindly proceed as commented.
Eng. Name: Nicolas Abboud Signature: Nicolas Abboud Date: 27 March 24
Submittal Status:

☐ Reviewed ☒ Reviewed with Comments


Client: Saudi Entertainment Ventures – SEVEN (IF REQUIRED)
Comments:

Page 1 of 2
P6 Abha Entertainment Complex
Client: Contractor: Assistant Engineer and Supervision Project Management Consultant
Consultant: and Engineer:

Eng. Name: Signature: Date: 27 March 24


Submittal Status:

☐ Reviewed ☐ Reviewed with Comments


IMPORTANT: Permission to proceed does not relieve the Contractor from full compliance with contractual obligations, responsibility, and the Local Authorities requirements.

Page 2 of 2
Client PMC LDC Contractor
Saudi Entertainment Ventures Khatib & Alami Dar International Engineering Consultancy Modern Building Leaders
Project name: Program 6: Abha Entertainment Complex
Location: Abha Contract No.:

INSPECTION TEST PLAN


6ABHA09-INSPECTION TEST PLAN AND CHECK LIST FOR INSTALLATION AND TESTING OF CCTV SYSTEM

New Submittal Submittals NO Submittals date Revision Previous submittal date

Resubmit 6ABHA09-ABHA-08-MBL-EV-ITP-00004 12-Mar-2024 00

Document purpose For Information For Notes For Approval

DECPLINE Sewage Struc. BIM Electronic Services/ELV

(Quality) (Method statement) (Time Schedule) (Safety)

Document type (Soil Report) (Policies) (Monthly Report) (General Report)

Weekly Report) INSPECTION TEST PLAN

Attachments 1 2 3

Sr. Document TITLE Document NO Document Status Notes

6ABHA09-INSPECTION TEST PLAN AND CHECK LIST


1 6ABHA09-ABHA-08-MBL-EV-ITP-00004 For Approval
FOR INSTALLATION AND TESTING OF CCTV SYSTEM

Sr.Project Manger (Contractor) Sr. Engineer (Contractor)

Name: Eng. Mohamed KotbTahoun

Signature: Technical Office Manager

Date: 12-Mar-24

Remarks:

Supervision Consultant representative PMC representative

Name: Ashraf AbdalRahim Signature: Name: Signature:

Position: Resident Engineer Date: Position: Date:

Document Status

(A) Approved As Submitted (B) Approved with Comments (C) Revise and Resubmit (D) Rejected

Issued by the contractor: Signature: From the consultant: Signature:


Date: Date:

FR-QC-CW0091-01 Issue Date 14 November 2021 Rev.00


ITP Submittal
Internal Review Checklist
Project Name: ABHA-P6 Entertainment Complex ITP no.: 6ABHA09-ABHA-08-MBL-EV-ITP-00004
Contract No: P6 Rev. no.: 0
Contractor: MBL Date: 12-MAR-24
Sub-Contractor: ICAD Discipline: ELV

ITP description : INSTALLATION & TESTING OF CCTV SYSTEM

No. Item Yes No N/A Comment

1 Has the scope of inspections & tests been well defined?

Has the mock-up inspection tests with frequency of the mock-up inspection tests been
2
included with Respecting W and H points?

3 Has the samples inspection tests been included with Respecting W and H points?

Are items to be inspected and tested including test stages identified and presented in a
4
logical construction order?

Are controlling documents such as test procedure, method statement, project


5
specification, related standards been included?
Are all Quality Control requirements including, pre-task quality brief, calibration, Shop
6 drawings,Redline drawing monitoring, clearance from other disciplines, and turn-over
review detailed as required?

Are acceptance criteria with a clear tolerance for each inspection and test been
7
specified?

8 Has the frequency of inspection and testing been included?

Are verifying documents has been identified with clear reference to applicable
9
checklists and forms?

Does the ITP include notification requirements for “Work Inspection Request” (WIR)/
10 Material inspection request (MIR)?(Minimum (24) hours for site work and (1) week in
advance for inspections requested during holidays and Fridays.

Does the ITP include specific code/ standard to be used for each inspection/ test in
11
accordance with the requirements of SEVEN List of Codes & Standards?

12 Are responsibilities related to inspection and test been included?

13 Are there references to Applicable procedures for testing & inspection.?

Are the 3rd party, MBL, LDC, PMC ,and SEVEN hold, witness review points been
14
established among all parties with a clear definition in the legend?

15 Does the ITP specify the percentage of tests to be done/ sampling plan?

16 Has SEVEN Project number been speicifed?

17 Are the reporting forms & checklist been included as an attachment to the ITP?

18 Are previous submittal comments have been addressed and replied?

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


ITP Submittal
Internal Review Checklist
Project Name: ABHA-P6 Entertainment Complex ITP no.: 6ABHA09-ABHA-08-MBL-EV-ITP-00004
Contract No: P6 Rev. no.: 0
Contractor: MBL Date: 12-MAR-24
Sub-Contractor: ICAD Discipline: ELV

ITP description : INSTALLATION & TESTING OF CCTV SYSTEM

No. Item Yes No N/A Comment

Has the inspection & test plan been signed off by designated competent preparer,
19
reviewer and approver?

Does the inspection & test plan format & language is as per project requirements and
20
easy to understand?

Does the inspection & test plan include the repair stage or contain a reference to a
21
separate Special Procedure for repairs?

Does the inspection and test plan require an activity for the protection of completed
22
work? If yes is the approved Method/procedure mentioned in the Reference?

Conclusion/ Remarks

Prepared by: Reviewed by: Accepted by:

Name Eng Rami Baydown Junaid Ahmad Mohammed Imaduddin

Designation Sr. Tech Engr. MBL QA/QC Elect Engg Sr. QA/QC Eng.

Signature

Date 12-MAR-24 12-MAR-24 12-MAR-24

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)

Utilized By
Document Number Document Type Contract Number
Document Title Inspection Test Plan Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date
2 .1 CCTV Cab les and W ires M aterial
Activity INSTALLATION & TESTING OF CLOSED CIRCUIT TELEVISION SYSTEM

ITP Number 6ABHA09-ABHA-08-MBL-EV-ITP-00004 Discipline ELV ITP Approval Date

2 .2 CCTV
Project Title Cameras
ABHA-P6 and
Entertainment A ccessories
Complex
WIR No M aterial
INSPECTION

2 .3 CCTV W ork Station and Softw are

CONTRACTOR
Third Party
ITEM
M aterial TASK/ACTIVITY Reference

Seven
PMC
Acceptance Criteria Frequency Check List Recording Document REMARKS

LDC
NO. /Controlling Document

1.0
2 .4 CCTV Serv er, Storage D ev ices,
DOCUMENTATION

1.1
Interface, Integration D ev ices and
PRE-QUALIFICATION OF SUB CONTRACTOR
Document Review (Spec)
As required N/A
Document Review (Spec)
Approved Prequalification N/A H R R R
A ccessories.
28 23 00 28 23 00

1.2 Shop Drawing Approval Document Review(IFC/Spec) Each Shop Drawing


4 .1 O TD R TestN/A/Fluk e Test CCTV cab les and W ires N/A
Approved IFC drawings/Spec
Shop Drawing
Transmittal
H R R R A p p rov ed M eth od Statement A p p rov ed
1.3
2 .5 CCTV System Cab le Tags and
Method Statement Approval
Document Review (Spec)
28 23 00 / Manufacturer of CCTV Cab les
Prior to Start of Activity N/A
Integrity
As per Specification Test
Approved Method Statement N/A H R/H R R D raw ings Test R ep ort
Recommendations

L ab els. Document Review (Spec)


As per Specification /
Material Sample Form /
A p p rov ed M eth od Statement A p p rov ed
1.4 Sample & Mockup Approval
4 .2 Testing of CCTV
Prior to Start of Activity N/A Approved Material Submittal / N/A H R/H H H
28 23 00
CCTV Cameras Functional
Mockup WIR
Method Statement
3 .1 Installation of CCTV System Cameras D raw ings Test R ep ort
2.0 RECEIVING INSPECTION
Test
2.1 Sup
Check the Material as perpapproved
orting A ccessories
submittal. Approved MTS/ MIR Per Delivery MBL-CL-ELV-CCTV System-004 Approved MTS MIR N/A H H S R

3 .2 Installation of CCTV Cab les and


3.0 INSTALLATION INSPECTION
4 .3 MBL-CL-ELV-Installation
Testing of CCTV W ork
3.1 INSTALLATION OF CABLING
W ires
As per approved
Prior to Commissioning of CCTV System Cabling-001 CCTV W ork WIRStation
Approved Shop Drawing and
N/A H H S R
Station and it’s A ccessories
(Check List) Method statement

As per approved Functional Test


Approved Shop Drawing and
3 .3 Installation of CCTV Cameras and (Check List)
3.2 INSTALLATION OF CCTV SYSTEM Prior to Commissioning MBL-CL-ELV-Installation Of CCTV System-002 WIR N/A H H S R
Method statement
4.0 TESTING & COMMISSIONING
A ccessories. Approved Shop Drawing and
4.1 TESTING & COMMISSIONING OF CLOSED CIRCUIT TELEVISION SYSTEM As per Approved Specification
4 .4 CCTV
Prior to Commissioning
System
MBL-CL-ELV-TESTING OF CCTV SYSTEM-003
Method statement
WIR with Attached Test report H H H S R

3 .4 Installation of CCTV W ork Station and CCTV System Functional


5.0 AS BUILT DRAWING
Functional Test Including
Softw are Test
WIR & Redline Drawing
Including Interface and
5.1 Maintain site as built drawing
Requirements set forth in
After
Interface and Integration
Completion of All N/A
Specification:
prepared based on
Approved TQ and Field N/A W R R R
3 .5 Installation of CCTV Serv er, StorageContract Documents
Works
Integration Approved
Section 01 77 00 - 2
Change Document

6.0 CLOSE OUT D ev ices, Interface, Integration D ev ices and

6.1
A ccessories.
Handover to main Contractor As per contract Document At End of Work N/A As per contract Document contract Document H H H H R

3 .6 P lacement of Cab le Tags and GENERAL NOTES


1 E q uip ment L ab els.
The first three incidents of each Inspection or testing activity listed require 100 % participation by the Consultant. After this period, the Consultant may adjust the levels of SEVEN participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
3 Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization representative is not present.
4 Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Consultant
LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test
S Surveillance
Page 1 of 1

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-
Activity: INSTALLATION OF CCTV SYSTEM CABLING INSTALLATION OF ELV
CCTV CABLING -001

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No

ITEM NO. Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement

C1 All Indoor cameras shall be wired through Category 6A cabling to the nearest TR.
Project specs. add h ere A deq uate clearance giv en from oth er
28 23 00-1 1.1 ( D.6 )
eq uip ment and sp ecified segregation b etw een
All Outdoor cameras shall be wired through Category 6A cabling to the nearest TR Project specs.
C2
and surge suppression shall be provided. 28 23 00-1 1.1 ( D.7 )
Inst. A nd E lect. Trays p rov ided.
Cameras that are connected using copper network cabling shall be powered by
Project specs. add h ere Cab le tray sup p orts securely fix ed and
C3 Power over Ethernet (PoE) or by the the use of a PoE power injector if the PoE
E xp ansionrequirements
joints fitted
exceed the network switch Poe capability.
28 23 00-7 2.4 ( C.1 ) adeq uate sp acing as p er draw ings
Cable Connections and controls shall be provided inside the camera housing such Project specs.
C4
that the cabling cannot be disconnected without opening the camera housing. 28 23 00-9 2.4 ( N.2 )
add h ere Ch eck cab le tray is free from sh arp edges.
C5 Install cables in pathways and cable trays except within desks, and counters.
Project specs. Insp ect all cut trays and fittings h av e b een correctly
27 05 00-24 3.3 (F.1)
Tray joints are effectiv ely and cov ered w ith ap p rop riate p rotectiv e coating.
Project specs.
C6 Install cables utilizing pathways or trays within cabinets and consoles.
p ermanently earth ed 27 05 00-24 3.3 (F.2)
add h ere L ocations and routings as p er ap p rov ed
C7
Conceal conductors and cables in accessible ceilings, walls, and floors where Project specs. draw ing and sp ecs for (routings )
possible. 27 05 00-24 3.3 (F.3)
Cab le sp acing correct
Terminate and
Conductors: runs
No cable shall contain un-terminated elements. Make Project specs.
C8
p arallel terminations only at outlets and terminals. 27 05 00-24 3.3 (F.7)
Do not exceed manufacturers pulling and installation limits for force and bend Project specs.
C9
radius. 27 05 00-24 3.3 (F.6)

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Project specs.
C10 Visually inspect wire and cable for faulty insulation prior to installation.
27 05 00-24 3.3 (F.13)
After installation, and before termination, all wiring and cabling shall be checked
Project specs.
C11 and tested to ensure there are no grounds, opens, or shorts on any conductors or
27 05 00-24 3.3 (F.15)
shields.
Do not exceed the recommended maximum pulling tension. Under tension the Project specs.
C12
bend radius shall be double. 27 05 00-24 3.3 (F.19)
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-
Activity: INSTALLATION OF CCTV SYSTEM. Installation Of CCTV ELV
System-002

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No

ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
The Installation as described in Section 27 05 00 "Common Work Result for Project specs.
C1
Communications" to apply to this Section. 28 23 00-18 3.4 ( A )

Installation shall be performed in accordance with the applicable standards, Project specs.
C2
requirements, manufacturers’ guidelines and any authorities having jurisdiction. 27 05 00-23 3.4 (D.5)

Installation instructions described in the Manufacturers installation manuals to be Project specs.


C3
followed. 27 05 00-24 3.4 (E.2)
Measure indicated mounting heights to bottom of unit for suspended items and Project specs.
C4
to centre of unit for wall or pole mounting items. 27 05 00-24 3.4 (E.3)
Headroom, if mounting heights or other location criteria are not indicated,
Project specs.
C5 arrange and install components and equipment to provide maximum possible
27 05 00-24 3.4 (E.4)
headroom consistent with these requirements.
All visible system components in public areas shall be installed and configured
Project specs.
C6 taking into account building limitations and aesthetic considerations of the
28 23 00-6 2.2 ( H )
Interior Architectural Team including colour
Project specs.
C7 Cameras and support constructions shall be installed level and plumb.
28 23 00-6 2.2 ( J )
Project specs.
C8 Cameras shall be flush mounted in the ceiling of the lift.
28 23 00-9 2.4 ( M.2 )
Cameras shall be installed in dome style housing semi-flush mount in Project specs.
C9
suspended ceiling. 28 23 00-10 2.4 ( O.4 )

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Camera shall be installed in dome style housing semi-flush mount in wall or Project specs.
C10
column cladding. 28 23 00-10 2.4 ( O.5 )
Camera housing shall be mounted without housing or cabling penetrating the Project specs.
C11
wall, column or ceiling. 28 23 00-10 2.4 ( O.6 )
After the proper layout of all equipment is accomplished, all components are to
Project specs.
C12 be labelled, and marked in accordance with Division 27 Section “Identification for
27 05 00-23 3.4 (D.8)
Communications Systems.”

The Video Server software shall be a package that shall be installed on a server
Project specs.
C13 running a database server software platform, and combined with the hardware,
28 23 00-11 2.7 ( A )
shall function as an IP based digital video surveillance and recording server.
Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE

MBL-CL-ELV-Testing of
Activity: TESTING & COMMISSIONING OF CCTV SYSTEM. ELV
CCTV System-003

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No

ITEM NO. Check Points Reference PASS FAIL N/A Remarks

A Handling and Storage


All materials shall be stored in covered areas and protected from dust and Project specs.
A1
dampness. 27 05 00
B Site Clearance
Ensure Structure, Civil, Architecture Clearance have been issued prior to start any Project specs.
B1
installation. 27 05 00
C Placement
Pre-Commissioning:
C1 SEV-QM-TEM-00090
Check whether all the units are free of damage.
Pre-Commissioning:
C2 SEV-QM-TEM-00090
Check all electrical connections & terminal strip connections for tightness.
Pre-Commissioning:
C3 Ensure that all products installed as per consultant’s/Manufacturer approval and SEV-QM-TEM-00090
that all cable test sheets are signed off and available.
Pre-Commissioning:
Project specs.
System wiring has been tested and verified as correctly connected as
27 05 00 3.7 (A.5.D) &
C4 indicated.
Manufacturer
Continuity testing
Recommendations
Fluke Testing
Pre-Commissioning:
Project specs.
C5 The test procedure shall confirm that cables, outlets and equipment have been
27 05 00-28 3.7 ( A.13 )
labelled before commencement of testing.
The Quality Control and Testing as described in Section 27 05 00 "Common Work Project specs.
C6
Result for Communications" shall apply to this Section. 28 23 00-18 3.8 ( A )
All test plans shall be approved in writing by the Client. To successfully complete a
Project specs.
C7 test, the test document shall be signed and dated by both the CONTRACTOR and
27 05 00-28 3.7 ( A.14 )
the Client.

C8 Check the power of each DVR & define the camera text based on the location. SEV-QM-TEM-00090

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


C9 Check whether the camera has corrected Field of View, FOV. SEV-QM-TEM-00091

C10 Check whether the live video frame rate of the camera is configured. SEV-QM-TEM-00092

C11 Execute Pan Tilt Zoom exercise to achieve point of angle and operation. SEV-QM-TEM-00093

C12 Check the video play back from the recordings. SEV-QM-TEM-00094

Real-time recording, frame rate recording (at each frame rate) and back-up
C13 SEV-QM-TEM-00095
recording.
Retrieval of video both short term and archive video. Test for retrieval of video
C14 SEV-QM-TEM-00095
based on time and date retrieval.
The Contractor shall confirm that the calculated storage requirements are correct Project specs.
C15
during the testing phase of the Project. 28 23 00-15 2.9 ( Q )
The system shall support an Application Programming Interface (API) and shall
Project specs.
C16 provide a Software Development Kit (SDK), for integration with 3rd party software
28 23 00-11 2.7 ( E )
systems.
Test according to the development planning. For instance, the core product may Project specs.
C17
be tested and deployed before the complete version of the System 27 05 00-28 3.7 ( A.8 )

The client shall review, witness and validate the execution of all format test
Project specs.
C18 procedures prepared by the tests cover all requirements and there is a conformity
27 05 00-28 3.7 ( A.15 )
between the conducted test, the test result and specification requirements.

Remarks:

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


Client SAUDI ENTERTAINMENT VENTURES Modern Building Leaders (MBL)
Document Number Document Type Checklist Utilized by Contract Number
Doucment Title Checklist Issued by MBL QA/QC DEPT SEVEN Project ID P6
Revision Number 00 Issue Date Start Date End Date

Check List Check List ITP Approval Date DISCIPLINE


MBL-CL-ELV-Material
Activity: MATERIAL RECEIVING FOR CCTV SYSTEMS Receiving of CCTV ELV
System-004

Project Title ABHA-P6 Entertainment Complex WBS CONTRACTOR/SUBCONTRACTOR


WIR No
ITEM NO. Check Points Reference pass Fail N/A Remarks

CHECK MATERIAL AS PER APPROVAL


Project specs.
C1 Check the Material as per approved Material submittal.
28 23 00
Product Data: Submit data on Closed Circuit Television system cable, Devices, fittings and Project specs.
C2
accessories. 28 23 00

Manufacturer's Certificate: Certify that products meet or exceed specified Project specs.
C3
requirements. 28 23 00
Project specs.
C4 Check Manufacturer Labeling on the products
28 23 00
Project specs.
C5 Country Of Origin As per Specifications and Approved MTS
28 23 00
Project specs.
C6 Shop Drawings: Include plans, elevations, details,
28 23 00

C7 Delivery note Manufacturer

Remarks:

SEVEN
MBL
Third Party (if applicable)
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Contractor QC Inspector LDC Supervision Consultant


The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
Name Signature Date Name Signature Date

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


CABLE RECORD SHEET : CCTV SYSTEM

Package

CAMERA COAXIAL / CAT6A CABLES Sheet ref. Package No Bldg Panel Sheet Of Rev
Camera From Cable To Cable Result REMARKS
number location ID location ID Pass / Fail

Readings by / date : Witnessed by : Accepted by (<authority> ) :

Test instrument(s): Date : Date :

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24


COMMISSIONING RECORD SHEET : CCTV SYSTEM

Package

CAMERA FIELD OF VIEW / HEADEND VIEW Sheet ref. Package No Bldg panel Sheet Of Rev

CAMERA TYPE Camera IP Compression


Bit Light White IR
Resolution Contrast
Number Fixed, PTZ Etc Coverage Address Quality Rate Level Balance ON / OFF

Readings by / date : Witnessed by : Accepted by (<authority> ) :

Test instrument(s): Date : Date :

Aconex Ref#6ABHA09-ABHA-08-MBL-EV-ITP-00004 Rev#00 Date: 12-Mar-24