Monitoring Plan:

Performance
Hierarchy of Targeted Results Operational Defintion Baseline Data
Indicators
236 HH self employed
Percentage of employment through 34 Professionally emplyed
Percentage of
the improvement of road 27 HH were considered unemplyed
employment
network

Increased
Impact
economic opportunities Number of active commercial entities 26 Commercial Establishments
Number of businesses
operating within the area Recorded as of 2024

Percentage on change of
Amount of Transportation cost due to road
PHP 50 based on 2024 fare matrix
Transportation Cost network
improvement

Number of individual utilized the


Number of travellers No data
accessibility of road
Enhanced
connectivity and
Outcome
accessibility
15min based on Barangay Officials and
Amount of travel time Number of hours spent in travel time
residence

Length of constructed Measured length of road completed


183.60m existing dirt road
road and accessible for public use.
Constructed Local
Output Access road at San Vicente,
Victoria, Tarlac Feedback from residents on the
Rate of satisfaction of
constructed local access road at No data
residents
San Vicente, Victoria, Tarlac
Regular
Number of meetings Conduct of monthly meetings with
Activities Stakeholders Consultations/ No data
conducted stakeholders
Meetings

Downloaded budget for the SGLGIF downloaded budget: PHP


Allocation amount
construction of road project 1,800.000
Financial and
Input
Manpower
Number of hours worked by laborers 720 working hours (90 CD) based on
Number of Labor Hours
on the road project project contract

Budget Consideration and Calculation


A. Evaluation Team Cost (professional fees, transpo, per diem)

Professional Fees:
Road evaluation engineer/consultant: ₱0.00

Transportation Cost:
Fuel, tolls, etc: ₱3,000

Per Diem:
for the team: ₱2,000
B. Monitoring Implementation and Data Collection Costs (transpo, translation, workshop, etc.)

Transportation Cost:
Transportation cost for monitoring team: ₱3,000

Translation Cost:
Translation cost for data analysist: ₱2,000

Workshop and Training Cost:


Training cost for monitoring team: ₱3,000

Other Data Collection Costs:


Cost for data collection equipment: ₱2,000
C. Monitoring Distribution Cost (report production, stakeholder meeting)

Report Production Cost:


Cost for report production (writing, editing, design): ₱0.00

Stakeholder Meeting Cost:


Cost for stakeholder meeting (venue rental and catering): ₱8,000

Other Distribution Costs:


Cost for distribution of reports and other materials (printing / shipping): ₱3,000
Frequency of Data
Performance Target Data Sources Data Collection Methods
Collection
10% or 26 HH self employed individuals
35% or 46 Professionally employed
Documents and Records from
100% or No HH unemployed PESO Annual
PESO
within the next 12 months due to Local Access
Road Concreting

20% or 32 active commercial entities operating Documents and Records from


MEO, MPDO, MENRO Annual
within the area for next 12 months MEO, MENRO, MPDC

Reduced fare matrix by 40% (from PHP 50 to PHP Residence of Barangay,


Annual Interview
30) due to concreted roads Barangay Officials, DILG

10% Increase of individuals utilizing the road Mayors Office / Documents and Records from
Annual
network within the next 12 months Barangay San Vicente Mayors Office / Barangay

33.33% mins reduction (from 15mins to 10mins)


travel time due to concreted roads Residence of Barangay,
Annual Survey
Barangay Officials, DILG
****Computation = (15-10) / 15 * 100 = 33.33%

Documents and Records from


183.60m concreted road MEO/ Contractor Monthly
MEO/ Contractor

100% of clients provided at least satisfactory rating Human Resource Monthly / Quarterly Interview
Documents and Records from
At least one (1) meeting per month with stakeholder MEO, DILG Monthly
MEO/ DILG

100% or PHP 1,800,000 budget utilized within the Documents and Records from
MEO, DILG, DBM Annual
(specified timeline) MEO, DILG, DBM

Documents and Records from


100% or 720 total worked hrs completed MEO, DILG Monthly
MEO, DILG

No. of Days Daily Rate


Professional Fees:
Road evaluation
engineer/consultant: ₱0.00

Transportation Cost:
3-day Fuel, tolls, etc: ₱3,000
road evaluation Per Diem:
project for the team: ₱2,000

Total Evaluation Team Cost:


₱5,000
Transportation Cost:
Transportation cost for
monitoring team: ₱3,000

Translation Cost:
Translation cost for data
analysist: ₱2,000

Workshop and Training Cost:


3-day Training cost for monitoring
team: ₱3,000
monitoring and
data collection Other Data Collection Costs:
Cost for data collection
project equipment: ₱2,000

Total Monitoring
Implementation and Data
Collection Costs: ₱10,000
Report Production Cost:
Cost for report production
(writing, editing, design): ₱0.00

Stakeholder Meeting Cost:


Cost for stakeholder meeting
(venue rental and catering):
₱8,000

Other Distribution Costs:


3-day evaluation Cost for distribution of reports
project and other materials (printing /
shipping): ₱3,000

Total Evaluation Distribution


Cost: ₱11,000

TOTAL MONITORING COST


Responsibility to
Collect Data

MPDO

MPDO

Barangay

MPDO

Barangay

Municipal Engineer/
MPDO

MPDO
MPDO

MPDO

MPDO

Total

₱15,000
(Total Evaluation
Team Cost:
₱5,000 x 3 days)
₱10,000
(Total Monitoring
Implementation and
Data Collection Costs:
₱10,000 x 3 days)
₱33,000
(Total Evaluation
Distribution Cost:
₱16,000 x 3days)

₱58,000
Evaluation Plan

Performance
Evaluation Items Main Evaluation Question Sub-Evaluation Questions
Indicators
What is the percentage reduction in
Amount of travel time
travel time?

Achievement of program Length of constructed What is the total length of constructed


road Did the Municipality of Victoria meet road?
objectives
it's objectives?
How many meetings were conducted to
Number of meetings
implement the road project?
conducted

How many labor hours were required to


Number of Labor Hours
implement the project?

Implementation Process How was the project implemented?

Was the allocated budget sufficient to


Allocation amount
complete the project?

What was the total number of jobs


Percentage of created during the project, and how
employment does this compare to the original
employment projections?

To what extent has the project led to an


Number of businesses increase in the number of businesses
operating in the region?

Effectiveness of project
How effective is the road project?
strategy and approach
Has the project increased the capacity
Effectiveness of project
Number of travellers How effective is the road project? of the road to accommodate more
strategy and approach
travellers

Amount of How does the project give impact the


Transportation Cost transportation cost in the area?

Rate of satisfaction of How well did the project improve the


residents quality of life for residents?

Efficiency
Coherence
Effectiveness
Relevance
Impact
Sustainability
Budget Consideration and Calculation
A. Evaluation Team Cost (professional fees, transpo, per diem)

Professional Fees:
Road evaluation engineer/consultant: ₱0.00

Transportation Cost:
Fuel, tolls, etc: ₱3,000

Per Diem:
for the team: ₱2,000
B. Monitoring Implementation and Data Collection Costs (transpo, translation, workshop, etc.)

Transportation Cost:
Transportation cost for monitoring team: ₱3,000

Translation Cost:
Translation cost for data analysist: ₱2,000

Workshop and Training Cost:


Training cost for monitoring team: ₱3,000

Other Data Collection Costs:


Cost for data collection equipment: ₱2,000
C. Monitoring Distribution Cost (report production, stakeholder meeting)

Report Production Cost:


Cost for report production (writing, editing, design): ₱0.00

Stakeholder Meeting Cost:


Cost for stakeholder meeting (venue rental and catering): ₱8,000

Other Distribution Costs:


Cost for distribution of reports and other materials (printing / shipping): ₱3,000

TOTAL EVALUATION COST


Data Needed Data Sources Data Collection Methods

Residence of Barangay,
Number or % of hours spent in travel time Survey
Barangay Officials, DILG

Measured length of road completed and accessible Documents and Records from
MEO/ Contractor
for public use. MEO/ Contractor

Documents and Records from


Conduct of monthly meetings with stakeholders MEO, DILG
MEO/ DILG

Number of hours worked by laborers on the road Documents and Records from
MEO, DILG
project MEO, DILG

Downloaded budget for the construction of road Documents and Records from
MEO, DILG, DBM
project MEO, DILG

Percentage of employment through the


Documents and Records from
improvement of road PESO
PESO
network

Number of active commercial entities operating Documents and Records from


MEO, MPDO, MENRO
within the area MEO, MENRO, MPDC
Number of individual utilized the accessibility of Mayors Office / Documents and Records from
road Barangay San Vicente Mayors Office / Barangay

Percentage on change of Transportation cost due


Residence of Barangay,
to road network Interview
Barangay Officials, DILG
improvement

Feedback from residents on the constructed local


access road at Human Resource Interview
San Vicente, Victoria, Tarlac

No. of Days Daily Rate Total


Professional Fees:
Road evaluation
engineer/consultant:
₱0.00

Transportation Cost:
Fuel, tolls, etc: ₱3,000
3-day ₱15,000
Per Diem: (Total Evaluation Team
road evaluation project for the team: ₱2,000
Cost:
Total Evaluation Team ₱5,000 x 3 days)
Cost:
₱5,000
Transportation Cost:
Transportation cost for
monitoring team: ₱3,000

Translation Cost:
Translation cost for data
analysist: ₱2,000

Workshop and Training


Cost:
Training cost for
monitoring team: ₱3,000

Other Data Collection


3-day Costs: ₱10,000
monitoring and data collection Cost for data collection (Total Monitoring
equipment: ₱2,000 Implementation and Data
project Collection Costs: ₱10,000 x 3
Total Monitoring days)
Implementation and
Data Collection Costs:
₱10,000
Report Production Cost:
Cost for report
production (writing,
editing, design): ₱0.00

Stakeholder Meeting
Cost:
Cost for stakeholder
meeting (venue rental
and catering): ₱8,000

Other Distribution
Costs:
3-day evaluation project
Cost for distribution of
reports and other
₱33,000
materials (printing / (Total Evaluation Distribution
shipping): ₱3,000 Cost: ₱16,000 x 3days)
Total Evaluation
Distribution Cost:
₱11,000

₱58,000 58