Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 17

WORK METHODOLOGY

FOR

CONCRETE
Work Methodology Holistic project: Addis Ababa Housing And
Development Project Office Working Methodology

PROJECT: LOW COST HOUSING

EMPLOYER: Addis Ababa Housing And Development Project Office

CONTRACTOR: HDP CONSTRUCTION PLC

CONSULTANT: MGM CONSULTING PLC

PLACE OF Work: ADDIS ABABA

WORK METHEDOLOGY FOR CONCRETE

INTRODUCTION:
Concrete is an artificial building material which is obtained by mixing
cement, fine aggregate (sand), coarse aggregate (crashed stone, crashed
bounder, gravel etc.…), water and sometimes admixture at a proportion with
a specified quality of ingredients. The mixture in green condition is workable
and plastic, when allowed to see, becomes as hard as stone. The strength of
concrete depends on its ingredients, their relative quantities (ratio), method
of mixing manual or mechanical and manner of placing

Basic Features
Concrete is the most common building material used in today's
construction industry. It can be cast in any desired shape and fashion and is
therefore applicable for most building purposes. Its long life and relatively
low maintenance requirements add to its popularity. Concrete does not rot,
rust or decay and is resistant to wind, water, rodents and insects. It is a
non-combustible material, making it fire resistant and able to withstand high
temperatures. In the road sector, concrete is used for a number of purposes,
including pavements, bridges, culverts, retaining walls and other structures.

Concrete is a mixture of cement, water and aggregate. The aggregate


consists of a mixture of various sizes of gravel and sand. When water is
added to cement, a chemical reaction takes place causing the mix to harden.
Cement is essentially made from a mixture of limestone and clay, which is
ground into a very fine powder and then burnt at a high temperature in a
rotating kiln, thereby fusing it into a material called clinker. The clinker is
cooled down and ground into a fine powder. Gypsum and various additives
are then added to the cement.

Concrete work
After accomplishing of each excavation, formwork of foundation footing
will be constructed engaging qualified carpenters and helpers.

Lean concrete: will be mixed with concrete mixers and casted inside a
formwork.

Reinforcement bars: of appropriate type, strength, length and shape will


be prepared in accordance with the structural drawing within the
construction yard and will be set in position, tied with wire inside foundation
formwork with the help of bar benders and setters.

Upon approval of the Engineer’s for all the required arrangements,


homogenous concrete will be produced making use of concrete mixers and
to be casted into the formwork vibrating with vibrators. Then, it will be left
for curing with showering the concrete for sufficient time.

Erection of re-bar, formwork construction & casting of the foundation column


will be performed in the same manner as described above and will be cured
with regular showering until it is properly cured.

Reinforcement steel is normally provided as individual steel bars or as steel


bars welded together into a mesh. The bars are used for beams and
columns, while the mesh is prepared for large surfaces such as slabs and
walls.

The reinforcement steel should be stored in a clean location, lifted off the
ground and away from mud and oil. It should be placed on a flat surface
with sufficient support so that the bars do not buckle, bend or sag. Different
dimensions should be stored separately so they are easily identified when
required.

The good performance of the steel bars depends on a proper bond between
the steel and the concrete. This requires the steel to be clean and in good
condition.

1. Materials and Storage

Cement is usually supplied in bags weighing 50kg. Loading and unloading


the bags should be done carefully – preferably by manual labor - to avoid
any damages to the bags. If a bag is torn, moisture enters the cement and
triggers the chemical action causing the cement to harden. Hardened pieces
found when using the cement must be removed, because the strength of the
concrete will be reduced if they remain inside the batch.

The cement should be stored in a dry place where the bags do not get
damp or wet. The floor should have a good clearance from the ground or
walls, to avoid moisture penetrating from below and secondly to allow for
good ventilation.

. Aggregate the aggregate is the main contributor to the strength of


concrete. Using aggregate consisting of particles with varying size provides a
more dense and strong concrete. Fine aggregate is normally made up of
sand with particle sizes ranging from 0.3 to 5 mm, while the coarse
aggregate may contain stone up to 40 mm.

1. Water

Good quality water is required for the mixing of concrete. Drinking water is
the best, however, water from rivers and lakes is normally of adequate
quality. Salt water should not be used for mixing concrete.

Water is used for both the mixing process as well as during curing. Before
the first of these activities commence, it is important to make sure that the
site has adequate supply of water for both the mixing as well as the curing.
This may involve arrangements such as stockpiling water to ensure there is
sufficient water for the entire period from mixing until the end of the curing
process
2. Safety

When handling cement or fresh concrete, it should not come in contact


with the skin or eyes. Wearing gloves, a long- sleeved shirt, full-length
trousers and boots reduces the exposure. Wet concrete, mortar or cement
should be washed from the skin immediately. Eyes need to be flushed with
lots of water for at least 15 minutes immediately after contact. The final
strength of the finished concrete depends on:of air space, with mortar and
small particles filling all voids.

Sand and gravel contain particles of different sizes with empty spaces in
between. Generally, it can be assumed that sand and gravel, in a dry
condition, consist of 60 percent solid matter and 40 percent empty spaces.
To obtain a dense concrete these empty spaces need to be filled. The empty
spaces between the sand grains are filled with cement, while the sand-
cement-water paste (mortar) fills the empty spaces between the gravel
particles. An extra 10 percent of mortar is necessary to "coat" the particles
complete.

3. Proportion of the Components


1) The proportions of the components, i.e. the quantities of gravel, sand,
cement and water;
2) The quality of the components;
3) The distribution of the grain sizes of the gravel and sand;
4) How the components are mixed;
5) How the mixture is transported, placed, compacted and cured. When
the mixture is prepared it is important to make sure that the
proportions of the aggregates used in the mixture are correct and that
the right quantities of cement and water are added. The ideal mixture
is one that solidifies with the minimum amount
4. Water to Cement Ratio

Aggregate particles together. Through a chemical process called hydration,


the paste hardens and gains strength. The strength of the paste is
determined by the applied ratio of water to cement.

The strength of concrete increases when less water is used during the
preparation of the mix. Although the hydration process consumes a certain
amount of water, wet concrete actually contains more water than required
for the hydration reactions. The excess water is added to provide the wet
mix with sufficient workability. Concrete needs to be workable so that it can
be mounded into the desired shapes and consolidated to the required
density.

The quantity of water divided by the amount of cement gives the water to
cement ratio. A low water to cement ratio leads to high strength but low
workability while a high water to cement ratio produces a low strength
concrete but good workability. A careful balance of cement to water is
therefore required when preparing the mix. Water/cement ratios in the
range between 0.4 and 0.6 provide a good workability without compromising
the quality of the concrete. Hand-mixed and hand-placed concrete requires
more water to secure sufficient workability (water/cement ratio between 0.5
and 0.65).

5. Mixing Concrete

Thorough mixing is essential in order to obtain a homogeneous mixture of all


the ingredients and achieving a suitable workability. The equipment and
applied work methods need to be able to effectively mix concrete containing
the specified size aggregate, obtaining a uniform mixture with the required
workability within an acceptable water cement ratio.

The term workability is used to describe the ease at which the concrete can
be placed and consolidated without segregation or separation. It takes a
greater effort to achieve a uniform and dense mass of concrete in structures
containing a considerable amount of reinforcement bars as compared to
mass concrete used in a foundation. The amount of large aggregate as well
as the water content will greatly Influence the workability of the concrete,
however, these are also factors determining the final strength of the
concrete. Another alternative to improve the workability of concrete is by
using additives.

The following steps describe a good way to mix by hand:

 Limit the size of the batch to approximately a third of a cubic meter.


 First place a layer of sand on the mixing platform on which the cement
is spread. Mix thoroughly by turning the heap over several times. This
is best done by two persons facing each other, working the mix from
opposite sides. Mix until the cement is evenly distributed in the sand,
i.e. until the mix has a uniform color.
 Add coarse aggregate and turn the mix until the batch is once again
properly mixed.
 Sprinkle the predetermined quantity of water gradually on top of the
mix while turning it over another three times, or until the water is
evenly distributed.
 Use the wet concrete immediately after it has been mixed. Make sure
it is placed and compacted straight away, avoiding that it starts setting
before it is used.

5.1. Hand Mixing


When mixing is carried out by hand it requires a suitable surface (metal
sheets, boards or lean concrete slab) to ensure that the mix is not
contaminated with soil. The surface should be level to prevent water or fluid
material from running off the mixing area. The space needs to be sufficiently
large to allow for the required size of batches to be mixed without spilling
into surrounding areas.

Collecting the prepared materials, tools, equipment’s and the proportion


indicated above mixing by hand using the following procedures

1. place one half of the sand on to the mixing plate


2. place one half of course aggregate on top of the sand
3. now place approximately half of the cement on top of the aggregate
4. repeat procedures number 1-3
5. dry mix the aggregate and cement, proceed as follow and uniform
color
6. using the shovel make a circle of the mix and a hole in the center for
the water
7. now fill the hole with water
8. using the shovel turn the mix outside to center
9. continue mixing until the mix attains the specified consistency
(uniform color)
10. finally clean your tools, equipment’s before storing them

5.2. Mechanical Mixing


There exist a large number of different types and sizes of concrete mixers.
The most commonly found type on construction sites is the tilting drum
mixer. Depending on their size, these mixers can be manually driven or
powered by electrical or diesel/petrol engines. The drum on the mixers can
be positioned at different angles for charging, mixing and discharging. The
drum rotates on an inclined axis when Mechanical mixing produces a more
homogeneous and better mix. The concrete mixer should never be filled
completely. Using the prepared materials, tools, equipment and the
proportion indicated above mix by machine using the following procedures

1st position the mixer safely, i.e. level the mixer and check the wheels to
prevent movement once you have started the motor

2nd check its drum capacity to avoid over loading the mixer

Example if the total volume of ingredients is 0.35 m 3 it produces 0.24 m3,


and then we need a 400per300litter model. It has a capacity of 0.4 m 3 and
amount of 0.3m3

3rd start the mixer machine

4th add some amount of water in the mixer

5th using the gauge box and all the sand

6th add all the cement

7th add a little water to mix

8th using the gauge box add all the course aggregate to the drum

9th pour enough water for mixing

10th continue mixing until the materials are thoroughly mixed (approximately
5-6 minutes mixing time after all the materials are in the drum)

11th discharge the mix from the drum in the wheel barrow or container by
tilting the drum

12th finally clean and maintained the mixer

6. Formwork
Concrete is cast into molds referred to as forms or shuttering. Usually, the
forms used for walls, columns, beams and slabs are built by joining wooden
boards edge on edge. The advantage of using wood is that it can easily be
used to create any required shape. Plywood, laminated boards and metal are
also commonly used for formwork.

These materials have the advantage that they are more durable and can be
reused many times. Formwork is also available in panels with hinges making
it easy to assemble and to facilitate re- use. Joints and hinges on formwork
need to be thoroughly cleaned when it is removed.

Formwork should be built solid enough to contain the concrete when poured
as well as the weight of the reinforcement steel. The wet concrete has some
considerable weight and requires extensive support arrangements.

6.1. Removing Formwork


Forms should be left in place until the concrete has hardened sufficiently to
hold its own weight. The surface should be hard enough to withstand any
damage caused by the stripping of forms. Care should be taken not to
damage edges and corners.

Keeping the formwork in place for the first week contributes to the curing
process as the forms stop water in the concrete from evaporating.

Side forms for beams, slabs and columns can be safely removed after a
couple of days. When the concrete needs to bear its own weight, it is
necessary to leave it to cure before removing the formwork

7. Transport of Concrete
Concrete can either be produced on site or at commercial mixing plants.
When large quantities of concrete are required, it is common practice to

Organize the supply from a local mixing plant (if available), from which the
fresh concrete is transported by truck to the work site. On site, concrete is
transported using wheelbarrows and buckets to reach the final locations
where it is placed. The transport time of any concrete should be as short as
possible. Ideally, the concrete should be poured within 15 minutes after the
mixing has been completed. When rotating drum trucks are used, a
maximum of two hours is normally permitted for transport.

Whether mixing is done on site or at a plant, it is important to organize the


site in a manner that provides ready access to the forms where the concrete
will be poured.
Transport the mixed concrete by buckets, conveyers, pumps etc… to the
place where concrete is to be casted. During this operation care should be
taken to avoid segregation.

N.B The system of Trans porting concretes on the type of job being done,
the nature of the site, the equipment available, the distance to be covered
below or above ground and the cost of labor at the time

The following action should be taken before starting placement of concrete

 Make the form to be braced rigidly


 Keep the form in its true position
 Lubricate the sides and bottom of the form
 Fill the space formed during form working to avoid bleeding
 Pour the concrete in the form by keeping the position of reinforcement
bars

N.B Do not drop the concrete above one meter height, since this would
cause segregation of its ingredient

9. Pouring Concrete

Having secured the necessary supply, the concrete needs to be placed


and compacted. These two activities are carried out simultaneously. Placing
and compaction of concrete should be done without causing any segregation
of its ingredients. When placing the concrete, care need to be taken not to
damage the formwork or dislodge the reinforcement.

Placing the concrete starts from the corners of the formwork with
compaction of the concrete starting immediately after it has been placed. In
the case of a sloping site, pouring should start at the lowest level. The
concrete should be placed in layers not higher than 30 cm when compacted
by hand and in layers not higher than 60 cm when compacted by vibration.

Slabs and floors should be poured in one continuous operation to avoid any
vertical or horizontal joints, which would create planes of weaknesses within
the structure.

10. Curing
When the ingredients in concrete are brought together, the cement and
water react with each other starting a chemical process, causing the
concrete to form a hard mass, which adheres to and binds together the
aggregate. Concrete starts setting roughly two hours after is has been
mixed. This implies that the pouring and compaction need to be complete
within this period of time. Any shaping or reworking of the concrete once the
concrete starts setting will cause serious damage to the concrete.

Adequate curing of the concrete during its initial days after placing is
essential in order to achieve its strength and other qualities such as surface
durability, volume stability, water-tightness and abrasion resistance. Proper
curing also prevents the surface from cracking, caused by insufficient
binding due to the non-availability of water.

Curing the concrete basically consists of preventing the concrete from drying
out during the setting and hardening stage. Water is a necessary ingredient
in the curing process, since hydration is a chemical process, taking place
between the water and the cement. Freshly mixed concrete contains
sufficient water to secure that proper curing can take place, however, any
loss of water caused by evaporation will compromise the curing process. The
curing process is most critical during the initial days after pouring. The
exposed surface of the concrete is therefore kept moist during a period of
four to six days..

Curing is the final step in concrete

As concrete dries it shrinks, if quick drying takes place when there is very
little strength, cracking will result, so it will reduce the problem.

Cracking can be done with different methods depending on the type of


structure, the weather condition and the quantity of the work.

To perform curing activities

o Select appropriate method of curing


o Start curing after 24 hrs of casting depending on the weather condition
and place of casting
o Continue curing until the concrete structure acquires adequate
strength

N.B Water used for curing should be potable

11. Compacting (consolidating) concrete


Compact manually by shovel or spade, piece of iron bar or timber etc…

Example consolidating concrete using a shovel, proceed as follow

Handle the shovel backwards and move the blade dawn wards repeatedly

Compact mechanically using vibrator/ poker

 Insert the vibrating head of the poker


 Vibrate the concrete for 5-15 seconds
 Vibrate the concrete uniformly throughout the structure
 With draw the poker slowly
 Finally switch of the poker

N.B Pouring of concrete and compaction should have to be done


simultaneously

When using a poker with timber form work does not let it to touch the inside
of the forms and the reinforcement bars

12. Consistency

Concrete shall have a consistency such that it will be workable in the


required position. It shall be of such a consistency that it will flow around
reinforcing steel but individual particles of the coarse aggregate when
isolated shall show a coating of mortar containing its proportionate amount
of sand. The consistency of concrete shall be gauged by the ability of the
equipment to properly place it and not by the difficulty in mixing and
transporting. The quantity of mixing water shall be determined by the
Engineer and shall not be varied without his consent. Concrete as dry as it is
practical to place with the equipment specified shall be used.

13. Batching

Measuring and Batching of materials shall be done at a batching plant

1. Portland Cement
Either sacked or bulk cement may be used. No fraction of a sack of cement
shall be used in a batch of concrete unless the cement is weighed. All bulk
cement shall be weighed on an approved weighing device. The bulk cement
weighing hopper shall be properly sealed and vented to preclude dusting
operation. The discharge chute shall not be suspended from the weighing
hopper and shall be so arranged that cement will neither be lodged in it nor
leak from it.Accuracy of batching shall be within plus (+) or minus (-) 1
mass percent.

2. Water
Water may be measured either by volume or by weight. The accuracy of
measuring the water shall be within a range of error of not more than 1
percent.

3. Aggregates
Stockpiling of aggregates shall be in accordance with Subsection 311.2.10.
All aggregates whether produced or handled by hydraulic methods or
washed, shall be stockpiled or binned for draining for at least 12 hours prior
to batching. Rail shipment requiring more than 12 hours will be accepted as
adequate binning only if the car bodies permit free drainage. If the
aggregates contain high or non – uniform moisture content, storage or
stockpile period in excess of 12 hours may be required by the Engineer.

Batching shall be conducted as to result in a 2 mass percent maximum


tolerance for the required materials.

4. Batching
When batches are hauled to the mixer, bulk cement shall be transported
either in waterproof compartments or between the fine and coarse
aggregate. When cement is placed in contact with moist aggregates, batches
will be rejected unless mixed within 1 – ½ hours of such contact. Sacked
cement may be transported on top of the aggregates.

Batches shall be delivered to the mixer separate and intact. Each batch shall
be dumped cleanly into the mixer without loss, and when more than one
batch is carried on the truck, without spilling of material from one batch
compartment into another

14. WORKING METHOD

As the technical specification is the guideline for all construction contacts,


the work is to be performed in line with this document and any provision
there on the B.O.Q.

Cement mortars are to be mixed using mixers


Whenever level differences are encountered in an axis, the leveling work is
to be performed using chips of stones at bottom of the foundation till the
level that enable to construct the upper courses with 30*40cm dimensioned
stones is reached.
If mixer problem is faced and hand mix is un-avoidable, the work will be
executed using hand mix by increasing cement by 10%, but by informing
the site supervisor to do so.
General Remarks: - After executing the work with this methodology, we
assure the work satisfies the technical requirements and any failure
thereafter will be judged according to the Ethiopian Standard Conditions Of
Contracts. And, as the time goes & technology advances, the working
methodology of the time might change, and hence, the new methodology
will be provided before any further application.

For any damage or injury that might occur--- first aid is ready at site level,
and if the injury is beyond the aider’s level, transportation service is
available for external treatment.
We hope you will accept & approve our work methodology and grant us to
continue the stated activity.

ACTIVITY – Concrete casting in …………………..


Objective – To cast C-25 concrete in to …………………………… shown in
structural drawings.
Raw Material Description – Cement ------ 3.6 qt’l/ m 3
Gravel----- 0.75 m 3/ m3
Sand ------- 0.53 m 3/ m3

Total demand of each material for particular work is to be found by


multiplying the above listed consumption output by the takeoff quantity
ready for inspection.
EQUIPMENT & MANPOWER DESCRIPTION, BREACKDOWN ANALYSIS
AND WORKING TIME

Responsible assigned professionals are the Site engineers in their respective


zonal assignment.

Equipment involved

1 Mixer

2 Vibrators

Manpower involved

1 Foreman

1 Mixer operator

2 Carpenter

2 Mason

15 Dl

2 Vibrator operators

Break down Analysis & Working time

Starting time to at the time submission & signing of checklist and take off
sheet is done.

Working rate per day 16 m3

Volume of work to be take- off quantity attached with the checklist for
inspection.

To complete the work --- (take-off qt’y/16) Days

ACTIVITY – Concrete casting in Footing.

Objective – To cast C-25 concrete in to Footing shown in structural drawings.

Raw Material Description – Cement ------ 3.6 qt’l/ m 3

Gravel----- 0.72 m 3/ m3

Sand ------- 0.5 m 3/ m3


Total demand of each material for particular work is to be found by
multiplying the above listed consumption output by the takeoff quantity
ready for inspection.

EQUIPMENT & MANPOWER DESCRIPTION, BREACKDOWN ANALYSIS


AND WORKING TIME

Responsible assigned professionals are the Site engineers in their respective


zonal assignment.

Equipment involved

1 Mixer

1 Vibrator

Manpower involved

1 Foreman

1 Mixer operator

1 Carpenter

1 Mason

20 Dl

Break down Analysis & Working time

Starting time to at the time submission & signing of checklist and take off
sheet is done.

Working rate per day 16 m3

Volume of work to be take- off quantity attached with the checklist for
inspection.

To complete the work --- (take-off qt’y/16) Day

ACTIVITY – Concrete casting in Grade Beam


Objective – To cast C-25 concrete in to Grade Beam shown in structural
drawings.

Raw Material Description – Cement ------ 3.6 qt’l/ m3


Gravel----- 0.72 m 3/ m3

Sand ------- 0.5 m 3/ m3

Total demand of each material for particular work is to be found by


multiplying the above listed consumption output by the takeoff quantity
ready for inspection.

EQUIPMENT & MANPOWER DESCRIPTION, BREACKDOWN ANALYSIS


AND WORKING TIME

Responsible assigned professionals are the Site engineers in their


respective zonal assignment.

Equipment involved

1 Mixer

1 Vibrator

Manpower involved

1 Foreman

1 Mixer operator

1 Carpenter

1 Mason

20 Dl

Break down Analysis & Working time

Starting time to at the time submission & signing of checklist and take off
sheet is done.

Working rate per day 16 m3

Volume of work to be take- off quantity attached with the checklist for
inspection.

To complete the work --- (take-off qt’y/16) Day

You might also like