Professional Documents
Culture Documents
TPL-100000-CHS-EM-TS-0001 Dust Extraction System
TPL-100000-CHS-EM-TS-0001 Dust Extraction System
TPL-100000-CHS-EM-TS-0001 Dust Extraction System
OWNER:
ADANI MAHAN ENERGEN LIMITED
EPC CONTRACTOR:
TATA PROJECTS LIMITED
ISSUE REV DATE INITIALS SIGN INITIALS SIGN INITIALS SIGN Remarks
TABLE OF CONTENTS
1.00.00 INTRODUCTION......................................................................................................................................3
2.00.00 SCOPE OF SUPPLY...............................................................................................................................3
3.00.00 TERMINAL POINTS................................................................................................................................6
4.00.00 EXCLUSIONS...........................................................................................................................................7
5.00.00 PERFORMANCE GUARANTEES.........................................................................................................7
6.00.00 BIDDER OFFER.......................................................................................................................................7
7.00.00 TECHNICAL DATASHEETS..................................................................................................................9
8.00.00 ANNEXURES...........................................................................................................................................9
TITLE: TECHNICAL SPECIFICATION FOR DUST Doc:No.
EXTRACTION SYSTEM TPL-100000-CHS-EM-TS-0001
1.00.00 INTRODUCTION
1.01.01 This enquiry specification covers the design, engineering, manufacturing, supply, testing &
inspection at shop, transportation and delivery to site, supervision of erection, trial
operation, training, performance testing and commissioning of Dust Extraction system as
indicated under scope supply for 2x800 MW (PH-II) MAHAN ULTRA THERMAL POWER
PROJECT.
2.01.00 MECHANICAL
2.01.01 Scope includes design, engineering, manufacturing, supply, testing & inspection at shop,
transportation and delivery to site, supervision of erection, trial operation, training,
performance testing and commissioning of complete Dust extraction system.
2.02.00 Each Dust extraction system shall be Comprise with the following:
i. Complete dust extraction system including fans, Ducting, Bag filter assembly with
collecting hoppers and Rotary air lock feeder, Chimney with supports, acoustic
insulations and all the drives with drive base frames and accessories.
All the flexible connections and gaskets required at inlet and outlet of fans and
ducting.
Compressor and air receivers with necessary valves and fittings as required.
All interconnecting ducting with counter flange and all interconnecting piping
Dampers as required.
Screw conveyor with slide gate.
Dust disposal chute from bag filter hopper to conveyor skirt board.
Inspection door as required.
Interconnection with plant DDCMIS
ii. Structures and Access Platform, walkway & hand railing.
iii. Lubrication system
iv. Guards for all the rotating parts.
v. All equipment foundation bolts, base frame, base plates, anchors bolts, all required
fasteners to install the equipment’s.
vi. All the first fill and one year’s topping requirements of consumables till successful
commissioning/initial operation.
vii. Start up and commissioning spares.
viii. Mandatory spares and recommended spares as per annexure-IV
ix. Special Maintenance tools and tackles if any required
2.02.02 Bidder to consider and size the compressor required complete Dust extraction system as
per the flow diagram enclosed. Bidder to note that compressor provided by bidder to cater
an additional requirement of instrument air for other systems whose supply is in TPL scope
TITLE: TECHNICAL SPECIFICATION FOR DUST Doc:No.
EXTRACTION SYSTEM TPL-100000-CHS-EM-TS-0001
2.03.00 ELECTRICAL
2.03.01 All HT and LT motors for the drives, MOV’s Actuators (if any), VFD Panels, Local control
panels, Local Starter panels (LSP), LPBS shall be in bidder’s scope of supply.
2.03.02 Power and Control Cables between the bidder’s LCP /LSP to the equipment supplied by
bidder. Wherever, both end equipments are in bidder’s scope, the interconnecting cable,
cable carrier system between the bidder supplied equipments, are in bidder’s scope.
2.03.03 LT cabling accessories such as Cable glands, lugs, ferrules, tags and conduits for bidder
supplied cables.
2.03.04 LV system shall be designed for 415V, 3 phase 4 wire. TPL will provide the 41V, 3phase, 3
wire Power supply to the equipments in bidder’s scope or as per the scope specified
elsewhere in the tender specification. Bidder shall derive the control supply, for satisfactory
operation of bidder supplied equipment.
2.03.05 Bidder shall provide the load list as per attached load list template.
2.03.06 PAINTING FOR ELECTRICAL EQUIPMENT
i. The painting of all electrical equipment shall be epoxy based with suitable additives.
The thickness of finish coat shall be minimum 50 microns (minimum total DFT shall
be 100 microns).
ii. However, in case electrostatic process of painting is offered for any electrical
equipment, minimum paint thickness of 50 microns shall be acceptable for finish
coat.
iii. The Contractor shall furnish the complete painting details during detailed engineering
stage.
2.04.00 INSTRUMENTATION
2.04.01 Bidder shall supply complete Control & Instrumentation (C & I) items / devices/ safety
switches for each dust extraction system etc. required for safe and efficient operation of
Dust extraction system.
TITLE: TECHNICAL SPECIFICATION FOR DUST Doc:No.
EXTRACTION SYSTEM TPL-100000-CHS-EM-TS-0001
2.04.02 All instruments shall be as per finally approved P&IDs/GA during detailed engineering by
NTPC/TPL. All instruments supplied by bidder shall be integrated as a part of this package.
As a minimum following Instruments shall be provided by Bidder for each dust extraction
system
i. Pressure Gauge and Pressure Switch at air manifold
ii. Differential Pressure Switch on Bag Filter
iii. Level Switch for each Hopper below bag filter
iv. Zero speed switch for Air lock valves below hoppers
v. Instruments Air Compressor Instrumentation shall be provided to meet control and
operation philosophy of technical specification Annexure -III
2.04.03 Bidder shall provide all field instrumentation / sensors / final control elements with actuators/
solenoid valves/ valve positioners / pressure/ DP/ Level transmitters, pressure/ DP/ Draft
gauges, Thermocouples/ RTDs with temperature transmitter, temperature gauges along
with associated thermowell / protecting tubes, pressure/ DP/ temperature/ flow/ level
switches, Level gauges, flow gauges with accessories, local gauge boards, etc. which are
required for Local/ Remote monitoring and control of dust extraction system. All instruments
shall be supplied in line with Annexure-V.
2.04.04 All required mounting & erection hardware like impulse tubes, Manifold, Root / Drain valves
and instrument fittings, Snubbers, Counter flanges, Cable glands, Cable trays, Conduits,
Racks/ Stanchion/LIE/LIR to mount remote Instruments and Structural steel for installing
Bidder’s supplied instruments is under the Bidder’s scope of supply on as required basis.
2.04.05 All instrumentation and control cables up to Junction Box shall be provided by Bidder. All
Cables shall be supplied in line with Annexure-V.
2.04.06 Dust extraction system shall be controlled from DDCMIS. Interface between the various
drives and control system shall be in line with Annexure-V.
2.04.07 Instrument Air Compressor/Dryer shall be operated and controlled from the Microprocessor
Control Panel supplied by Bidder. Complete Start/ Stop, Loading / Unloading shall be done
from the control Panel supplied by Bidder. Auto Changeover of Compressor/Dryers shall be
done using master controller or same shall be implemented in both Local Control Panels with
each compressor set as per OEM standard practices, however same shall be specified in the
bid offer.
2.04.08 Microprocessor based control Panel shall have provision for Remote Start/Stop Command
from purchaser control system. Also, necessary feedbacks like
Running/Off/Trip/Loading/Unloading status shall be provided for monitoring in purchaser
control system (DDCMIS).
2.04.09 Compressor Local Control Panel shall have provision for RS-485 Modbus or TCP/IP
communication with DDCMIS. Necessary fibre optic connectors/ converters/ patch panels etc.
for communications on both ends shall be provided by Bidder.
2.04.10 Bidder shall provide the vibration measurements and temperature measurements monitoring
system for protection of the compressors as per OEM practices. Complete VMS system along
TITLE: TECHNICAL SPECIFICATION FOR DUST Doc:No.
EXTRACTION SYSTEM TPL-100000-CHS-EM-TS-0001
with sensors, cables, mounting accessories shall be in Bidder scope only. Make and Model
number of Vibration sensors and VMS shall be in line with Purchaser make /model no. of
Main VMS system.
2.04.11 Local control panel shall be considered for operation of SOV for purging.
2.04.12 In case of HT motors, following shall be considered by Bidder
i. At least two (02) nos. of duplex thermocouples or duplex platinum RTDs (100 ohms
at 0 Def C) and one no. of temperature indicators shall be provided for bearing metal
temperature measurement, control and monitoring.
ii. Six numbers of Duplex type or 12 nos. Simplex type Resistance Element
Temperature Detectors (RTDs) shall be suitably distributed at locations where
highest temperatures may be expected in stator windings and one (1) element in
each bearing. The RTD’s shall comply with the latest edition of IS:2828.
iii. In addition to the above, all necessary instruments required for hydraulic system and
for protection shall also be provided by Bidder. Same shall be as per approved P&ID
during detailed engineering.
2.04.13 Bidder to please note that all RTDs/Thermocouple (Including Bearing and Winding RTDs)
shall be provided with temperature Transmitter.
2.04.14 Bidder to please note that PT/DPT/TT shall be Foundation Fieldbus/ Profibus (FF/PF)
compatible, which shall be decided during detailed engineering based on finalization of
DDCMIS vendor.
2.04.15 Bidder to note that all electrical actuator shall be Foundation Fieldbus/ Profibus (FF/PF)
compatible, which shall be decided during detailed engineering based on finalization of
DDCMIS vendor.
2.04.16 Bidder to please note that cable from FF/ PF instruments and actuator along with necessary
junction box shall be in purchaser scope, however necessary cable tray / conduit/ cable tray
support and space for mounting junction box shall be considered by bidder.
2.04.17 For Binary and analog inputs required in major equipment of FGD system protection, triple-
sensing devices shall be provided.
2.04.18 Binary and analog inputs, which are, required for protection of more than one equipment as
well as protection signals for HT Drives etc., triple sensing devices shall be provided.
2.04.19 For other critical binary and analog inputs required for protection and interlock purpose of
other equipment (e.g. those interlocks which may result in loss of production, non-availability
of a major equipment etc.), triple sensors shall be provided.
2.04.20 Bidder to please note that scope of supply and services shall be in line with the Scope
Matrix for C&I.
2.04.21 All systems, Instruments and accessories shall be from the latest proven product range of a
qualified manufacturer whose successful performance has been established.
2.04.22 All Instruments / Panels/JB etc. shall be tagged as per KKS tagging philosophy. Tag plate
shall be provided of corrosion resistant material.
2.04.23 All special tools/ Tackles required for Control and Instrumentation shall be provided by
TITLE: TECHNICAL SPECIFICATION FOR DUST Doc:No.
EXTRACTION SYSTEM TPL-100000-CHS-EM-TS-0001
Bidder.
2.04.24 Bidder to please refer Annexure-V for all technical requirements of Control and
Instrumentation.
4.00.00 EXCLUSIONS
4.01.01 Civil foundation excluded.
4.01.02 Erection and commissioning (however supervision is included)
4.01.03 Handling facilities
4.01.04 HT switchgear, 11/0.433kV Service Transformer, 415 V LT Non Segregated Bus Duct
between Service Transformers and PMCC, PMCC/MCC/DB, 220V DC Battery and Battery
charger.
4.01.05 Illumination
4.01.06 Above ground earthing and Below ground earthing
4.01.07 Lightning Protection.
4.01.08 DDCMIS
4.01.09 UPS system
4.01.10 I&C Cables from Junction Box to DDCMIS
4.01.11 FF/PF cable and Junction Box for FF/PF compatible instruments/actuators supplied by
Bidder.
6.04.00 Bidder to submit special tools and tackles, recommended spares, as required for the
proposed package.
6.05.00 Bidder to submit equipment cooling water requirement (DM water), service water,
instrument air, service air etc (if any).
6.06.00 Bidder shall submit the following documents during detailed Engineering
i. Instrument List (in purchaser format provided during detailed engineering).
ii. I/O list (in purchaser format provided during detailed engineering).
iii. Instrument Datasheet
iv. Cable Interconnection Diagram and Cable Schedule (in purchaser format provided
during detailed engineering).
v. Operation and Control Philosophy defining the interlock and protection required for
each drive.
vi. Logic Diagram (including compressor) for Bidder supplied systems in NTPC format
vii. GA and Datasheet of VMS (as Applicable)
viii. UPS/ Non UPS / 24 VDC load Requirements
ix. Mandatory / Recommended / Start up and Commissioning spares list.
x. Calibration Test certificates / Type test reports
xi. As built drawings
8.00.00 ANNEXURES
Annexure-VII Spares