Study On Action of SOTF Protection and Generation Shutdown Caused by Power Swing

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 5

1

Study on Action of SOTF Protection and Generation


Shutdown Caused by Power Swing due to Faults at
Transmission Lines
Lei Zhang 1,*, Xilai Yuan 1, Arnold Medina Sanchez 1, Wilbert Alvarez 1, Jianhua Ren1

1 Affiliation 1: Empresa de generación Huallaga. S. A,, Lima, Perú


* Correspondence: lei_zhang@ctg.p

Abstract— Large generator units, as the critical equipment of distance protection of the line to malfunction. Normally, when a
modern power systems, will experience a transient process of short circuit fault occurs on a line, the differential protection of
power-angle stability when experiencing load changes, line the line will operate to cut off the faulty phase, while generating
faults, or changes in line operation mode. In the process, power power swing in the healthy phase conductors of other lines. At
swings are generated within the system. Power swing is usually this time, in order to ensure power transmission, especially for
detected by a mechanism based on continuous impedance large units, and ensure system frequency stability, the distance
calculation, and through the function of power swing blocking protection of the healthy phase line is blocked by the Power
[1], the related functions of distance protection are blocked to Swing Block (PSB) mechanism. However, this locking function
should be reactivated in the event of another short circuit fault
prevent the distance protection from malfunctioning [2], and
in the line, which requires the Power Swing Deblocking (PSD)
the large unit shutdown or island operation, resulting in damage
function to unlock.
to system stability by avalanche effect. This article described a
two-generation unit shutdown event with pre-fault operation at There are many methods for monitoring power swings,
200MW each. Due to the lighting strikes on the 220kV among which the most common is to detect the rate of change in
transmission line, the power swing was detected by distance line impedance under fault conditions as a condition for the
protection. Before the faulty phase reclosure, the power swing activation of PSB and PSD [1] [2]. The PSD function under fast
triggered the action of the backup protection of the distance power swing and high fault resistance is detailed in [3]. The
protection SWITCH ON TO FAULT (SOTF) and tripped three method for detecting the Swing Center Voltage (SCV) of
phases of the double circuit transmission line on the same tower. symmetrical faults in power oscillations is proposed by this
In order to ensure the stability of the power swing during faults reference [4]. Recently, with the continuous innovation of
algorithms, the adaptive fuzzy neural inference system (ANFIS)
and the safety of the blocking function, this study uses Power
has also been used in this field.
Factory Digisilent to conduct a transient analysis of the power
system based on the published detailed electrical system model. This article is based on the analysis of a lightning strike
When it is greater than 320MW, the power swing caused by the tripping fault on the transmission line of a certain power plant as
failure of the two circuits will cause the generator to lose shown in Fig. 3 . The power plant has two 225MW units
synchronization and cause system stability problems. operating at its rated power of 0.68 operating point and its 125-
Therefore, under this extreme fault condition, an automatic kilometre double circuit 220kV power transmission line on the
control mechanism for the unit to automatically reduce output same tower. After a lightning strike occurred on the S and T
is proposed to ensure that the unit loses synchronization. phases of circuit 1, a phase-to-ground fault occurred. After 53
Keywords—synchronous generator, short-circuit fault, power ms, the phase to ground fault was removed by the line
swing, single-phase reclosing scheme, SOTF, distance protection. differential protection. At the same time, a single phase to
ground fault occurred on the S phase of circuit 2. After 54 ms,
I. INTRODUCTION the phase was removed by the line differential protection, and
Large generators, as the core equipment of modern power the reclosing function was activated at 520 ms, At a distance of
systems, generate power angle (rotor angle of synchronous 560ms, the backup protection SOFT of the protection was
motors) swings and power transmission line swing when their activated, and the other two healthy phases were cut off. The S
load experiences major disturbances such as line faults or phase reclosed at 610ms and immediately tripped. The reclosing
switching of line operation modes. Power swings may cause the failed, and all the power plant's power transmission lines were
2

shut down, resulting in a serious accident of the power plant's crossing the PSB range on a concentric mho circle is used. In the
large unit being cut off. The accident caused a loss of 306MW case of a stable power swing, the detector observes the apparent
power supply to the power system where the power plant is impedance vector initially enters the power swing range shown
located, resulting in a decrease of 0.59Hz in the power grid, in Fig.4 as PPOL and only later enters the fault detection range
which is insufficient to trigger a stable power grid accident. as APOL in the figure. It is also possible that a power swing
Therefore, the automatic load-shedding extreme value of the vector will enter the power swing range and leave it again
power grid was not triggered. without coming into contact with the fault range. If the vector
enters the power swing polygon and passes through it leaving on
the opposite side, then the section of the network seen from the
This article first provides a detailed analysis of the distance
relay location has lost synchronism, which means the power
protection and backup protection of the factory's transmission
transfer is unstable.
line, especially the detection and blocking functions of power
oscillations during line faults. In order to ensure the stability of
power oscillation during faults and the safety of locking
functions, this study conducted a transient analysis of the power
system using Power Factory Digitilent based on a published
detailed electrical system model. The results will provide a
theoretical basis for the transformation of line distance
protection and backup protection.

Figure 1 L2150 Fault recording and relay action


Figure 3 Single-line diagram of the studied electrical system

Figure 2 L2151 Fault recording and relay action

II. TRANSMISSION LINE POWER SWING DETECTION AND


BLOCKING FUNCTION Figure 4 Pickup characteristic of the power swing detection for a
A common problem of the line being protected by distance polygon
relay is to be de-energized incorrectly by a power swing.
Therefore Power Swing Blocking (PSB) and Deblocking (PSD) The PSD function normally is used in the case of unstable
function is applied to differentiate a power swing and a real fault. power swings and real faults during power swings to maintain
In the event of a short-circuit, the impedance vector, which is the reliability of power system protection. Various parameters
calculated by tracking voltage and current samples continually , are used for this purpose. However, due to the complexity of
would tumble dramatically and when it is lower than a pre-set differentiating the symmetrical fault, more studies are
line characteristic value, an open command control the relevant undertaken and tested. In our case study, we do not consider any
breaker opens, however, when there is a power swing of a power deblocking function at the power plant.
system, such as shown in Fig. 1 and Fig. 2 case, calculated III. SYSTEM MODELLING FOR POWER SWING STUDIES
impedance value by the more slowly increasing voltage than the
current periodically may lead to a wrong breaker action. In order It is shown in the previous section that there is no PSD
to solve the problem, some other parameters are tracked. In the function installed in the power protection system of the power
power plant, the time passed for the impedance value for plant system, therefore several cases and symmetrical and
unsymmetrical faults combined with the various operation
3

modes of the two generation units are simulated in order to test


the performance of the PSB and guarantee under the case of an
unstable power swing, an automatic generation decrease can be
applied. In this section, the time-domain EMT model of the two-
generation-units system and its transmission lines as shown in
Fig. 3 is built up.
A. Generator and transmission line model
The generator model is inspired by the database of the
published grid connection on the official website of the national
power system. Meanwhile, the updated 2022 and 2023 test
results were applied. Two generation units G1 and G2 are
connected to double-circuit overhead transmission lines L2150
and L2151 of 127.5km on the same transmission tower via two
transformers TR1 and TR2 with a capacity of 255MVA each.
The transmission lines are modelled with frequency-dependent
modes to reveal their transient behaviour. The saturation
characteristics of all the transformers in the system are Figure 6 Mathematical model of turbine
implemented. The main equipment details are listed in Table 1.
Table 1RATINGS OF THE EQUIPMENT IMPLEMENTED IN THE IV. SIMULATION RESULTS AND ANALYSIS
SYSTEM The fault event procedures of the system shown in Figure 1
and Figure 2 can be presented in Table 2.
Equipment Ratings Number of units
Table 2 EVENTS RECONSTRUCTION SIMULATED
Hydro Power 225MW 2
Generation t=0 Single phase to ground fault
Units on line L2151 (S phase)
Main 13.8/220kV,255MVA 2 t=0 Double phase to ground fault
Transformer (S phase and T phase) on line
Overhead 220kV, 127.5km 2 (L2150/L2151) L2150,
tranmission line t=53 ms P substation line L2150
three-phase disconnection

B. The Mathematical Model of Government and Turbines t=53 ms Line L2150 fault clearing
The concept of the governor and turbine control are vital for t=54 ms P substation line L2151
transient simulation under load and fault condition. In this phase S disconnected
section, the governor block diagram shown in Figure 5 and the
t=61 ms C Substation L2150 line
turbine model shown in Figure 6can be obtained. Table 5-1
three-phase disconnection
shows the parameterization of the model used for validation
records, and Table 5-4 shows the valve characteristics of the t=63 ms C line L2151, line S phase
model. disconnected
t=645 ms Line L2151 S Phase
Reclosing
t=662ms Line L2151 S Phase
disconnected

A. Event Reconstruction Simulation Results


The reconstruction simulation of the event shows that the
frequency due to the event drops to 59.41 Hz at 14.01s after the
fault occurred, which meets the reality situation. Based on the
record of the national grid, the load rejection scheme for
minimum frequency was not activated.

Figure 5 Governor mathematical model


4

Figure 8 Simulation result of rotor angle, rotor frequency and output


power of the main generators at 450MW Generation

C. Successful Reclosing Simulation Result with 450MW


Generation
In the case of the total output power of the two-generation
units reaching 450 MW before the fault occurred on the lines,
in Fig. 9 the curves of the rotor angle, frequency, and output
power are calculated. It can be seen that the output power
significantly decreases to 200MW, and the rotor angle increases
from 0 degrees to 150 degrees within 0.5 seconds. It is believed
that when the rotor angle increases by more than 90 degrees
Figure 7 Simulated frequency during the event. (accurate values should be calculated based on structural
parameters), the synchronous generator loses stable operating
B. Successful Reclosing Simulation Result with 306MW conditions. From the above power curve, the synchronous
Generation generators lose stability at 0.3 seconds and each generator
The pre-fault generator operation point is 306MW. After the output power begins to plummet to zero. The frequency curve
fault occurred, the total output power of each generation unit shows that the rotor frequency continues to rise from 60Hz
suddenly decreased from 150 MW to 70 MW simultaneously. during this process, proving that when the total output power is
The sudden drop in load leads to an increase in rotor angular 450MW, the synchronous motor loses stability. This situation
velocity. All the parameters including the rotor angle, rotor should be avoided by properly configuring the protection and
frequency and output power are seen in Fig. 8 . The above rotor control of the system. One quick solution is to implement an
angle curve shows that it rapidly increases from -10 degrees to automatic generation unit cut-off scheme in the control system.
50.18 degrees, and the rotor frequency increases from 60 Hz to
the highest 60.5Hz. Then, due to the action of the governor, the
output power of the rotor gradually increases. After 645
milliseconds when the reclosing is realized, the output power
instantly increases to 319.1 MW per unit, meaning that the total
output reaches the transient peak of 640MW. The following 10
seconds undergo periodic attenuation, and after 10 seconds, the
rotor angle and frequency gradually return to the rated
frequency. From the analysis of the above process, the
maximum transient rotor angle of the synchronous generator is
50.18 degrees, which is still within the limit of system stability.
Therefore, the system ultimately periodically attenuates the
transient overshot to achieve stability.

Figure 9 Simulation result of rotor angle, rotor frequency and output


power of the main generators at 450MW Generation

D. Successful Reclosing Simulation Result with various


Generation
The following Fig.10 shows the rotor frequency curve under
various output conditions. If both the automatic load shedding
of the national power grid at 59.2Hz and the unit output power
limit are considered, the pre-fault output power of 320MW is
the highest pre-fault output requirement.
5

Figure 10 Simulation result of Rotor frequency and power of the Figure 11 Simulation result of rotor angle, rotor frequency and
generators at 360MW,340MWaand 320MW output output power of the main generators in Chaglla Electrical System for
Type 1 fault and 456MW output with one unit disconneted after fault
E. Successful Reclosing Simulation Result with 450MW within 200ms
Generation(Not exceeding 200ms, disconnect one 225MW
V. CONCLUSIONS
unit)
The application of EMT studies has allowed the large signal
To implement the automatic generation unit cut-off scheme,
non-linear dynamic analysis of the fault event under various
the fault reconstruction and successful reclosing was simulated.
generation output, fault and operation mode conditions, where it
All the parameters including the rotor angle, rotor frequency has been possible to assess if the reclosing was successful, the
and output power are seen in Fig. 11. When the two generation power swing is stable or unstable. The result shows that when
units operate at their nominal operation power of 450MW in the two-generation unit operates at its nominal output, the fault
total before the fault, it is required to disconnect one of the event may lead to an unstable power swing, where the PSD
generation unit of 200MW within 200ms after the fault. The should be installed and activated. The other solution is to cut off
transient simulation result shows in this situation the power one of the generation units after the fault occurred within 200ms,
system returns to stable within 8 seconds. Although the so that the power system stability will be maintained. Further
frequency is lower than the 59.2Hz threshold specified by the work can explore the two solutions' viability.
power grid between the 0.697- and 0.780-second interval.
However, due to this short interval of only 0.031 seconds, and REFERENCES
if it is less than 0.150 seconds of national grid criteria to trigger
the automatic load-shedding program, it still can be considered [1] G. Eason, B. Noble, and I. N. Sneddon, “On certain integrals of Lipschitz-
a stable case. Hankel type involving products of Bessel functions,” Phil. Trans. Roy.
Soc. London, vol. A247, pp. 529–551, April 1955. (references)
[2] J. Clerk Maxwell, A Treatise on Electricity and Magnetism, 3rd ed., vol.
2. Oxford: Clarendon, 1892, pp.68–73.
[3] I. S. Jacobs and C. P. Bean, “Fine particles, thin films and exchange
anisotropy,” in Magnetism, vol. III, G. T. Rado and H. Suhl, Eds. New
York: Academic, 1963, pp. 271–350.
[4] K. Elissa, “Title of paper if known,” unpublished.
[5] R. Nicole, “Title of paper with only first word capitalized,” J. Name
Stand. Abbrev., in press.
[6] Y. Yorozu, M. Hirano, K. Oka, and Y. Tagawa, “Electron spectroscopy
studies on magneto-optical media and plastic substrate interface,” IEEE
Trans. J. Magn. Japan, vol. 2, pp. 740–741, August 1987 [Digests 9th
Annual Conf. Magnetics Japan, p. 301, 1982].
[7] M. Young, The Technical Writer’s Handbook. Mill Valley, CA:
University Science, 1989.

You might also like