Professional Documents
Culture Documents
MRPL Refinery RA
MRPL Refinery RA
MRPL Refinery RA
Declaration: By submitting this assessment (Parts 1 – 4) for marking I declare that it is entirely my own work. I understand that falsely claiming that
the work is my own is malpractice and can lead to NEBOSH imposing severe penalties (see the NEBOSH Malpractice Policy for further information).
Important note: You must refer to the document ‘Unit IG2: risk assessment – Guidance and information for learners and Learning Partners’ while
completing all parts of this assessment. Your Learning Partner should provide you with a copy, but it can also be downloaded from the relevant
resources section for this qualification on the NEBOSH website.
Part 1: Background
The working hours for the office posting there is a general shift of eight hours per day (09:30 AM
to 05:30 PM), 05 days working including tea breaks and lunch. At an onshore location the
employee gets a general shift or shift of eight days of two days morning (06-02 PM), evening shift
(02-10 PM), night shift (10-06 AM). At offshore seven days shift of 12 hours and seven night shift
of 12 hours and then 14 days off.
Description of the area to be included in the The risk assessment will include the entire plant of MRPL
risk assessment
The HSE manager who reports directly to the General manager, has the responsibility for Health
Any other relevant information and Safety of the Organisation. There is a safety officer to assist the HSE Manager to solve the
accurate issue.
* If you’re worried about confidentiality, you can invent a false name and location for your organisation but, all other information provided must be
factual.
By analysing the risk assessment and the inspection which i did earlier, I understood the various
hazards and the existing control measures at the workplace. After i have referred to
● ISO 9001
● ISO 14001
● ISO 45001
● ILO C167
● ILO R175
Studying these Acts’ rules and regulations, I understood existing control measures and these acts
helped me to decide on the additional control measures required in the workplace.
Hazard category Who might be harmed and What are you already doing? What further controls/actions are Timescale
and hazard how? required? s for
further Responsible
actions to person’s job title
be
completed
(within …)
1. FIRE Plant operators, Plant ● Only closed containers are 1. Construct a separate lightweight 4 months Plant Manager
engineer, Fire marshals, used for the storage of roof storage area to store large
Storage of Plant workers, NDT flammable liquids. volume flammable liquids for
flammable liquids technicians and other explosion relief.
inside the plant ● Fire marshals provide
people inside the plant
supervision.
such as petrol, and outside the plant. 2. Install automatic smoke, heat and 1 month Plant Manager
diesel and LPG fire detection alarms.
● Ensure that LPG cylinders
leaks can cause Storage tanks contain are chained upright.
fire and explosion. flammable liquids, a small 3. Construct a storage area for LPG, 3 months Plant Manager
mistake can cause ● Ensure that empty and full separated from other buildings
massive damage to life, LPG cylinders are kept with secured fences and lockable
property damage, injuries separated. gates.
in body, environmental
● Provided proper ventilation.
pollution and the entire 4. Install fire sprinklers and hose 2 months Plant Manager
system is challenging to reels in the plant.
● Implemented a roll call
manage. system.
5. Purchase drip trays for under 1 month Purchase Manager
leaking oil sump and bunds.
3. RADIATION NDT technician, rig ● Sign boards indicate that 1. Install positive pressure air fans, 3 months Plant Manager
workers, drilling workers, caution of radiation has Radon sump and extraction
Radiation that plant supervisors and been placed. system to prevent Radon gas
emitted from other plant workers. seeping from ground up into a
drilling and ● Ensure that exposure does workplace.
fracking of oil and Oil and gas exploration not exceed the relevant
gas extraction and its production radiation dose limit. 2. Construct floor, walls, ceiling and 5 months Plant Manager
activities. activities can expose doors to be built with materials
significant quantities of ● Record keeping and that provide shielding for the
the radioactive materials reporting programme has desired radiation protection.
to the environment. been done.
Underground oil and gas 3. Purchase an industrial 1 week Purchase Officer
reservoirs contain ● Ensure the risk assessed radiography camera to inspect
elevated levels of by a competent person. pipe welding.
radioactive materials,
mostly Radium-226 and ● Shields and personal 4. Provide personal exposure 1 week Safety Manager
Radium-228, this can protective equipment are monitoring equipment.
increase the risk of provided.
cancer. Radium also
5. CONFINED NDT technicians, ● Permit to work system has 1. Proper communication methods 1 week Purchase Manager
SPACE supervisors, Plant been executed. to be arranged (purchase
insectors, Draughtsman, walky-talky) between the worker
Engineer and Tank and pipeline ● Hole watcher personal in the confined space and the
maintenance workers,
maintenance work protective equipment is Hole watcher.
cleaners and helpers.
in pipeline, always available.
process column The workers have to 2. Provide proper ventilation and 1 month Plant Engineer
and storage tanks enter the confined space ● Good housekeeping lighting arrangements.
having lack of to maintain and inspect provided.
oxygen and pipeline and storage 3. Implement a policy for 2 days Safety Officer
poisonous gas. tanks. An enclosed nature ● Proper isolation is provided atmospheric testing before and
of the place is having a for the workers. after entry.
lack of oxygen and poor ● Proper supervision is
ventilation and lights.
provided. 4. Construct safe and quick access 3 months Plant Manager
Limited entry and exit for
and egress methods.
the air, poisonous gas
can easily affect a person
working in confined 5. Implementing a system of five 3 days Safety Officer
space. It can result in people is essential for any
breathing problems, loss confined space work.
of consciousness,
asphyxiation and death. 6. Develop emergency and rescue 3 days Safety Manager
arrangements to cope with
foreseeable emergencies.
6. WORK Plant engineer, Plant ● Eye catching emergency 1. Implement a policy to eliminate 3 months Plant Manager
EQUIPMENT supervisor, NDT control button provided. pinch point entanglement areas
technicians, Plant and install automating tasks like
operators and people ● Provided environmental material handling.
Use of
around the machineries suitable lighting conditions
mechanical
working area. for the safety of the 2. Install fixed guard machines to 1 month Plant Manager
equipment such
as generator, operators. prevent direct contact with
pump, Using a machine without dangerous moving parts of
compressor, proper safeguard can ● Operators have adequate machines.
drilling machine, lead to injuries that range space provided to move
welding machine from minor life altering, around work equipment 3. Provide fences (perimeter guard)
and heat the consequence could safely. to prevent sparks produced by 2 months Plant Manager
exchangers. even be fatal hazards the drilling and welding machines.
presented by machineries ● Personal protective
includes moving part such equipment such as safety 4. Install two hand control machines 2 months Plant Manager
as belts, gear, roller, goggles, hand gloves, for the crushing machine.
chain, electrically charged shields, helmets and whole
7. WORKING AT Pipeline workers, Plant ● Good and high quality 1. Replace old scaffold materials to 1 month Plant Manager
HEIGHT operators, Mechanical materials are used for new scaffold materials.
department workers, scaffolding.
Fall of people and
Electrical and ● Sign boards that indicate 2. Precise communication methods 1 week Plant Manager
materials from the
instrumentation the people working at to be arranged between the
scaffold
department workers. height have been placed.
8. NOISE It mainly affects the ● Provided an absorption mat 1. Construct an acoustic haven for 4 months Plant Manager
workers surrounded by and rubber mat were workers.
Excessive noise excessive noise placed under the pumps.
from the machine producing areas including 2. Build an acoustic enclosure for 4 months Plant Manager
such as safety officers, ● Maintenance of machinery the generator with sound
compressor, supervisors and the and routine inspection for insulating walls.
pump, motors, employees nearby the the machines.
generators, area. 3. Replace lost and damaged 1 month Plant Manager
drilling and cutting ● Warning signs boards that machineries.
machines. Exposure to excessively indicate the excessive
loud noise from the heavy noise producing area have 4. Machine that produces exhaust 2 weeks Plant Manager
equipment and machinery been placed. gases to be filled with a silencer
while working can lead to on the exhaust.
temporary reduction in ● Shifts and breaks provided
hearing sensitivity as a for the workers to move 5. Modify machines and equipment 2 weeks Plant Engineer
result of short exposure to away from the noise that makes relatively lesser noise
excessively loud noise. producing areas. than before.
Repeated exposure to
loud noise leads to ● Earplugs are provided to 6. Build an isolated workplace for 1 month Plant Manager
Noise-induced hearing the workers. cutting and drilling purposes.
loss (NIHL). Excessive
exposure to loud noise 7. Provided a sound metre to check 5 days Safety Officer
can result in tinnitus, the noise level.
mental stress and risk of
accident. 8. Implement a policy of health
surveillance (audiometry) before 2 days Safety Officer
and after every work.
9. VIBRATION The employees who work ● Ensure that equipment is 1. Implement a policy of eliminating 1 month Plant Manager
near the vibration inspected before and after the high vibration producing
Exposure to producing machines, usage. machines.
excessive plant supervisors, safety
vibration into the officers and helpers. ● Providing proper 2. Purchase high quality and 2 month Purchase Manager
hand-arm maintenance to the produce low vibration equipment.
vibration from Continuous exposure to machineries.
machines due to the vibration can result in 3. Purchase anti-vibrant gloves. 3 days Purchase Officer
usage of carpal tunnel syndrome, ● Providing toolbox talk
machines. Heavy nerve damage, muscle based on vibrations and its 4. Make a sign board at the 5 days Safety Officer
equipment and weakening, joint damage harm. workplace that indicates about
working near and hand-arm vibration the vibration hazards.
generators, syndrome ( HAVS). ● Personal protective
pumps, equipment provided such 5. Provide proper maintenance for 3 days Plant Engineer
compressors and as hand gloves, safety the machineries.
motors. boots and helmet to prevent
direct exposure to the 6. Provide competent workers for 1 week Plant Manager
vibration. the work.
10. MANUAL Plant Engineer, ● Provided a trolley for 1. Purchase advanced hydraulic 2 weeks Purchase Manager
HANDLING mechanical maintenance transferring the materials. trolleys, chain blocks, lever hoist,
workers, NDT shackles, web slings, pulley for
Using the body to technicians, riggers and ● Allowed maximum load lifting purpose.
lift, carry, push helpers. carrying capacity 25Kg.
and pull heavy 2. Provide a proper inspection of the 3 days Plant Engineer
pipes, equipment For the maintenance of ● Ensure load passage lifting machine before and after
and materials. works in pipes and system from one worker to use.
replacing work in pipe another for reducing the
accessories the workers lifting time. 3. Break down a heavy load into 1 week Project Manager
are using the body force, smaller loads.
improper manual handling ● Ensure good housekeeping
can cause back injury, in the workplace. 4. Implementing a policy for lifting 3 months Safety Manager
tendon and ligament equipment needs load test
injuries. Heavy material ● Provided personal certifications and inspection
lifting with improper protective equipment. certificates.
manual handling leads to
WRULDs is a condition 5. Hire well experienced and 1 month HR Manager
11. SLIP AND All workers walking ● Maintaining good 1. Provide sufficient lighting 3 weeks Plant Engineer
TRIP around the area had oil housekeeping. conditions in the workplace.
spilled.
Exposed to the ● Sign boards indicate there 2. Purchase drip trays for under
risk of slip and trip People move around in is a slippery area. leaking oil sump and bunds 1 month Purchase Manager
while moving the workplace in slippery around the storage tank.
around the areas. There might be a
workplace chance to slip and trip. It
12. MOVEMENT All drivers in the plant, ● Ensure that the load is 1. Implement a policy to examine 2 days Plant Engineer
OF PEOPLE Plant engineer, supervisor stable and secured. tires, oil levels and water, oil or
AND and workers walking radiator leaks.
EQUIPMENT around the area. ● Ensure forklift is not
overloaded.
13. LONE NDT technicians, rig 1. Implement a policy of no lone 2 weeks Plant Manager
WORKING workers and confined working for certain high risk
space workers. activities.
Workers who
separated from 2. Provide proper ventilation and 3 weeks Plant Engineer
their colleagues NDT technicians have to lighting conditions.
● Toolbox talk before and
for work inside the work in pipelines for the
after work.
rigs and the maintenance purpose in 3. Purchase a walky-talky for 1 month Purchase Officer
pipeline sectors. confined space. There is communication purposes to the
● Sign boards and barriers
a chance that one person confined space worker and the
have been placed.
would have difficulty in supervisor.
handling equipment that
● Machinery maintenance
can result in broken 4. Construct a safe and quick 4 months Plant Manager
has been provided.
bones and WRULDs. An access and egress to the
enclosed nature, the workplace.
● Supervision provided.
place has poor ventilation
and lighting. In rigs 5. Install emergency alarms in one 2 weeks Safety Officer
● Personal protective
poisonous gas can easily working area and personal
equipment such as
affect the person working alarms in worker’s personal
respirator, gloves has been
in the rig. protective equipment.
provided.
14. MENTAL Plant operator, all 1. Implement a policy for selecting 5 days Plant Manager
ILL-HEALTH managers, all employees of the month and
supervisors, production encourage them.
Over workload, co-ordinators and all plant
work related engineers. 2. Arrange weekly interaction 1 week Plant Manager
● Had a positive atmosphere.
stress, anxiety sessions for management and
and depression Excessive workload from the workers.
● Provided sick pay.
starts from high the higher department
level mental would resul;t in mental-ill 3. Arrangement to allow workers 2 days HSE Manager
● Workers can take rest
ill-health. health, anxiety, recover from high stress
anytime at the workplace if
depression, headache, situations without fear of
needed.
irritability, inability to punishment.
concentrate, chest pain,
● All workers have a monthly
high blood pressure and 4. Flexible working hours have to be 4 days Plant Manager
leave rotation.
hypertension. allowed where possible.
15. SUBSTANCE All the workers who are 1. Strict action must be taken to 1 week Plant Supervisor
ABUSE AT addicted to consumption those who violated the drugs and
WORK of alcohol, tobacco and ● The organisation has a alcohol policy of the organisation.
other drugs in the strict policy against the
Substances such workplace. Colleagues consumption of drugs and 2. Install CCTV cameras in all the 2 months Project Manager
as alcohol, and people who deal with alcohol in the workplace. areas of the organisation.
tobacco and other those who are addicted to
drugs are drugs and alcohol are ● Warning signs against the 3. Purchase breath analyser to 1 month Project Manager
consumed in the also affected. consumption of alcohol and detect the alcohol or drug
workplace by the drugs have been placed. consumers in the workplace.
workers.
● Organisation has CCTV 4. Implement a policy to conduct 2 weeks Plant Supervisor
Alcohol and drug cameras in some areas. regular drug and alcohol testing
consumption in the
in the workplace.
workplace can result in an
MRPL has many financial reasons to provide health and safety in the workplace. Major accidents in
the industry can make a huge impact on the financial state of the company. There are two types of
cost, one is direct cost and another one is indirect cost. Indirect cost mainly happens due to the
consequences of the accident such as loss of goodwill, reduction in morale of the workers,
industry’s credibility, business reputation, time and expenses to recruiting new workers. Direct cost
is the after effect of the accident such as first aid, compensation given to the workers, legal
recruitment penalties, repairing cost of damaged machinery and the plant buildings. Both costs are
capable of knocking down a company.
Justification for action 1
Action
Construct a separate lightweight roof storage area to store large volume flammable liquids for
explosion relief. (Hazard category - ‘FIRE’)
Specific legal arguments
● C167 Safety and Health in Construction Convention 1988 (No.167) Article-27, states
that sufficient and suitable storage should be provided for flammable liquids, solids and gas.
● C152 Occupational Safety and Health (Dock work) Convention 1979 (No.152)
Article-32, states that adequate measures shall be taken to prevent exposure of workers to
toxic substances or oxygen deficient of flammable atmosphere.
Action
Install Ultra-fast earthing switch (UFES) in case of an internal arc fault, an arc detection relay trips
the UFES, which earths all three phases to extinguish the arc. (Hazard category - ‘Electricity’)
Specific legal arguments
● C167- Safety and Health in Construction Convention,1988 ( No.167) of Article-26 states
that all electrical equipment and installation shall be constructed, installed and maintained
by a competent person, so used as to guard against danger.
Action
Install positive pressure air fans, Radon sump and extraction system to prevent Radon gas seeping
from ground up into a workplace. ( Hazard category - ‘Radiation’)
Specific legal arguments
● C115 Radiation Protection Convention 1960 ( No.115) of Article-3, states that in the light
of knowledge available at the time, all appropriate steps shall be taken to ensure effective
protection of workers, as regards their health and safety against ionising radiation.
● C115 Radiation Protection Convention 1960 (No.115) of Article-5, states that every effort
should be made to restrict the exposure of workers to ionising radiation to the lowest
practicable level and any unnecessary exposure shall be avoided by all parties concerned.
● C167 Safety and Health in Construction Convention 1988 (No.167) of Article-19, states
that to avoid risk to workers arising from possible underground dangers such as the
circulation of fluids or the presence of pockets of gas, by undertaking appropriate
investigation to locate them.
● R114 Radiation Protection Recommendation 1960 (R114), suggest that plan should be
made in advance for measures to take prompt remedial action to prevent further spread of
radioactive contamination and to apply other appropriate safety precaution, including
decontamination procedures with as necessary, the immediate collaboration of all authorities
concerned.
Planned review date/period with reasoning According to our organisation’s Health and Safety policy, the review of risk assessment is
conducted every 12 months. I actually have done my review of risk assessment on the date of 04
March 2022 and I'm scheduled for the next review date on 02 March 2023.
Before the date comes, i can assure you that the following changes will be considered while
reviewing risk assessment in the organisation, they are:
How the risk assessment findings will be The risk assessment finding will be communicated through the meeting including Chief safety
communicated AND who you need to tell officers, Plant manager, HSE manager, Supervisors and one of the workers representatives. I will
present a documentary of risk assessment in the meeting and explain to them about the hazards
and the control measures. An awareness class will be conducted for all the workers by HSE officers
and Safety officers to give proper instruction and training at the workplace. The findings of risk
assessment will be included in the next available toolbox talks and summary of risk assessment
and actions to be taken will be posted on all the health and safety notice boards of the plant, so all
the workers can have access to it. And I will upload a copy to the company website. I will make sure
How you will follow up on the risk For the checking process, I will set daily reminders 2 weeks prior to the actions that are due to be
assessment to check that the actions have completed by the pant in charge. I will speak to the responsible person for each of the actions. If the
been carried out
actions are not implemented or delayed. I will explain the consequences we could face. If there are
any financial issues, I will talk with the financial department to convince them to allocate additional
resources. If there is any genuine reason, I will give some more time to allocate resources. Again if
it is delayed, i will consult the management department and explain the consequences to them and
make sure it will be implemented.