QUALITY CONTROL PROCESS by BERNABAD
YES
2
• Project quality specifications (Consultant attach the list of material
that considers necessary at this stage, to be provide the Technical
Data Sheet (TDS), all necessary certificates and/or Sample for
approval before implementation of any works.
• Contractor needs to submit any list of material, equipment and
Method of Statement (MS) one month and half before start the
works, when applicable;
• Contractor to submit the TDS, Approval Form Sheet (AFS) and MS
in English and complete with the date of submission (form sheet is
in attach above).
3
• Inspections and tests. Contractor needs to submit inspection
request at least 24h before.
4
• Control of nonconformances: Is there are any nonconformity works
appears during construction, Contractor will propose the solution
and discuss with the consultant before take any action.
5
• Approval Form Sheet it’s has three (3) conditions: A. Not Approve
(Contractor’s can’t do the purchase and need to complete the
comments and information for Consultant); B. Approve
(Contractor’s can proceed with procurement/logistic); C. Approve
with Condition (Contractor’s can proceed with
procurement/logistic but still have comments to revise).
6
• Approval Form Sheet submit by contractor must include:
Description of material for approval, if possible, with pictures,
Technical data sheet, Certificate of company, Certificate of
products and tests of approval and/or Catalog and If any deviation
of the product submit that is not according project to submit.
7
Example for List of Materials and Equipment necessary to providing the Technical Data Sheet, Sample and Request
Inspection
Project: NEW BUILDING ARCHIEVE CENTRE FOR CENTRO NACIONAL CHEGA
AC.001.2024
APO.2023.02 TEMPORARY FENCE 2 m HIGH CORRUGATED SHEET 2 m HIGH CORRUGATED SHEET Temporary fence, 2 m high, including acces doors.
ELECTRICITY SUPPLY BY
APO.2023.08
8
CONTRACTOR’S
LOGO HERE
Material/Equipment Description:
"Description of the material/equipment, can be support with image"
According
VERIFICATION:
Yes No
Observations
Project
Specifications Book
Bill of Quantities
Others
CONSULTANT REVIEW:
9
• Method of statement: Attached MS sheet, Contractor will
submit MS based on Construction methods and TDS submitted.
10
• Method of Statement form sheet must include: Storage of
product, Description of method of installation, Schedule of works
for the task, Manpower list (description of tasks and installation
time match with the schedule of works), Material list and Safety
measurement from product.
11
EXAMPLE FOR LIST OF WORK METHOD STATEMENT
Project Name :
Contractor’s name :
Consultant : Bernabad Arquitectura and Inginieria
Location : Mascarenhas, Rua Balide, Dili, Timor-Leste
12
Project: NEW BUILDING ARCHIEVE CENTRE FOR CENTRO NACIONAL CHEGA
Deadline Date :
Urgent
Starting Working Date: Finish Working Date:
1 - Identification
Reference Document
Team Leader/Representative
Signature: Christophe Nortier
Received By : Date:
Comments:
Received By : Date:
13
Project: NEW BUILDING ARCHIEVE CENTRE FOR CENTRO NACIONAL CHEGA
Document No: Revision :
Document Title: Comment Date :
Response Date:
14
• Minutes of Meetings (MoM) will be notes taken during
the weekly meeting, new points, updated decisions and
progress of work on site, results of a meeting. The
Consultant will subsequently submit an editable draft for
approval by all participants, if there is no comment within
24 hours, the MoM will automatically be assumed to be
correct.
• Minutes of Meetings are prepared weekly according to
the established schedule, Monday morning at 9am.
15
CONTRACTOR’S
LOGO HERE
MINUTES OF MEETING
Date:
PROJECT: IMPORT SCANNER REPORT NUMBER: 001/AC/2024
EMPLOYER: Centro Nacional Chega (CNC) Place:
CONSULTANT: Bernabad Arquitectura SLP (BA) Meeting type: Technical ☒ Planning ☐ Extraordinary ☐ Other ☐
GOVERNMENT: Ministry of Public Work (MOP)
CONTRACTOR: NZ & 4A Next Meeting: Date: 28/8/2023 Place: Tibar Port
This confirms and records our interpretation of the discussions which occurred and our understanding reached during this meeting. Unless notified in writing within
seven days of the date below, we will assume that the following interpretation as description is complete and accurate. The instruction noted in this minute shall be
applied the site
PARTICIPANTS:
BA MOP CNC - Engº [Name]
- Engº [Name] - Engº [Name] - Engº [Name] - Engº [Name]
- Engº [Name] - Engº [Name] - Engº [Name]
ITEMS:
No Description Action by Status Date
OWNER
OPEN
001 PROGRESS REPORT CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
002 METHOD STATEMENT CONSULTANT
CONTRACTOR CLOSED
OWNER
003 OPEN
BUILDING STAKE OUT CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
004 REVISE WEEKLY PLAN CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
005 CONCRETE READY MIX CONSULTANT
CONTRACTOR CLOSED
OWNER
006 OPEN
RECORDING PROPERTY CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
007 TIMELINE SCHEDULE CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
008 DOCUMENTATION FOR QUALITY MANAGEMENT CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
009 NOTIFICATION CONSULTANT
CONTRACTOR CLOSED
OWNER
OPEN
010 TASK BY WEEKLY PLAN: CONSULTANT
CONTRACTOR CLOSED
ADITTIONAL INFO:
ATTACHMENTS:
SCHEDULE OF WORKS ANALYSIS for :
Copies: Participants:
☒ BA
☒ MOP
☒ CNC
☒ NZR & 4A
16
ANNEX №1
PROGRESS REPORT FOR AFS & MS
17
CONTRACTOR'S LOGO
ARCHIEVE CENTRE
PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE CENTRO NACIONAL CHEGA DATE -
ES.MS.STR.017.
4/18/2023 ES.MS.STR.017 EARTHING NETWORK
Earthing Network
ES.MS.STR.018.
3/1/2024 ES.MS.STR.018 MECHANICAL WORKS
Mechanical Works
ES.MS.ARC.009.
4/17/2024 ES.MS.ARC.009 FLOOR FINISHES
Floor Finishes
ES.MS.STR.014
GENERAL ELECTRICAL POWER
3/14/2024 General Electrical ES.MS.STR.014
SUPPLY
Power Supply
ES.MS.LIGH.016
3/22/2024 ES.MS.LIGH.016 LIGHTING
Lighting
18
CONTRACTOR'S
LOGO HERE ARCHIEVE CENTRE
PROJECT: NEW CONSTRUCTION NATIONAL CENTRE ARCHIEVE CENTRO NATIONAL CHEGA DATE: -
230919 AFS.002.2023-
Approval Form Sheet- ES.AFS.001-006&008- PRELIMINARIES AND
9/19/2023
Preliminaries and 015&017.2023 PREVIOUS WORKS
Previous works
231003
ES.AFS.016.2023-
10/3/2023 ES.AFS.016.2023 FIELD DENSITY TEST
Field Density Test
Result
231003
ES.AFS.19.2023-Mud MUD SLAB - FINE
10/3/2023 ES.AFS.019.2023 - B
Slab-Raw Material AGGREGATE
Test
231003
ES.AFS.019.2023- MUD SLAB - TRIAL MIX 7 &
10/3/2023
Mud Slab Trial Mix 14 DAYS
7&14days
ES.AFS.019.2023 - E
231003
ES.AFS.019.2023- MUD SLAB - TRIAL MIX 28
10/12/2023
Mud Slab Trial Mix DAYS
28days
231005 P23_2022
ROOF & WALL STEEL
1/18/2024 ES.TDS.2023.53 - ES.AFS.053.2023
SHEET
Roof & Wall
231005 P22_202
ES.TDS.2023.63 -
SCHNEIDER
10/5/2023 ES.AFS.063.2023 SCHNEIDER COMPACT
COMPACT NSX100F
36kA AC 4P3R 63A
TMD_2
231005 P22_202
ES.TDS.2023.66&67 - ES.AFS.066&067.202
10/5/2023 CABLE 3x1,5mm & 3x2.5mm
cable 3x1,5mm & 3
3x2.5mm
ES.TDS.2023.65 -
LVMP Distribution
LVMP Distribution
12/27/2023 ES.AFS.065.2023 Panel+Digital meter and
Panel+Digital meter
analyzer
and analyzer
231005 P23_202
10/5/2023 ES.TDS.2023.71 - ES.AFS.071.2023 LIGTHNING INTERCEPTOR
Lighting Interceptor
231005 P22_202
ES.TDS.2023.72 -
10/5/2023 ES.AFS.072.2023 Isolated Cable BCC 70mm2
Issolated Cable BCC
70mm2
231006
ES.AFS.019.2023 -
Mud Slab-
10/6/2023 ES.AFS.019.2023 MUD SLAB - CEMENT
MANUFACTURE'S
CERTIFICATE
TONASA CEMENT
231008
10/8/2023 ES.AFS.020.2023-AFS
Formwork Sample
ES.AFS.020.2023 FORMWORK