Professional Documents
Culture Documents
Short Circuit Calculation Report
Short Circuit Calculation Report
Short Circuit Calculation Report
The short circuit calculation report is generated with Software Calculation with ETAP 19.0.1.
Short circuit calculation is worked out considering the following conditions:
SC calculations are done in accordance with IEC 60909 -------- (1) Reference of the
Equation (1), (2) , (3)
1. The short circuit calculation report is generated with ETAP 19.1 version.
2. THE Solar Plant BRANCH CIRCUIT MAIN CB SHALL BE CONNECTED TO A
TRANSFORMER WITH THE FOLLOWING DATA 16 MVA, 110kV/33kV Z-8%
3. We have considered Transformer MVA= Base MVA , So MVAbase = 16 MVA , kVbase =
33kV
4. Inverters and PV array station considered as a generating load while deriving short circuit
level to check fault contribution for each bus at 0.660kV bus.
5. SC calculations are done in accordance with IEC 60909.
2
One-Line Diagram - OLV1 (Edit Mode)
3 km 3R OH DOG CONDUCTOR
33 kV
OD Metering Switchyard
IDT TRANSFORMER-2 33 kV
6.25/3.125/3.125 MVA IDT TRANSFORMER-3 33kV ICOG Panel
3.125 MVA
0.66 kV
0.66 kV
2 m 3500 A 1-3/C 35
35 m 1.9/3.3kV 3C 35 Sq mm Al.
LV PANEL-1 BUS DUCT
3500 A 2 m
0.66 kV LV PANEL-1 BUS DUCT2
Change Over Switch
page 1 08:24:46 Feb 15, 2024 Project File: 33kV Solar Plant
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 1
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Project Developer: RADIANCE RENEWABLES PVT LTD SN:
Owners Engineer: SGURR ENERGY PVT LTD Revision: Base
Study Case: SC
EPC Contractor: SOLON INDIA PVT LTD Config.: Normal
Short-Circuit Analysis
Number of Buses: 1 0 28 29
Line/Cable/
XFMR2 XFMR3 Reactor Busway Impedance Tie PD Total
Number of Branches: 3 2 0 11 0 10 26
Number of Machines: 0 1 0 0 0 1
Adjustments
Apply Individual
Tolerance Adjustments /Global Percent
Transformer Impedance: Yes Individual
Apply Individual
Temperature Correction Adjustments /Global Degree C
Transmission Line Resistance: Yes Global 20
29 Buses Total
3.499
3.178
kA 2.911 33 kV
OD Metering Switchyard
0.273
0.109
3.145
IDT TRANSFORMER-2 33 kV kA
IDT TRANSFORMER-3 3.039 33kV ICOG Panel
6.25/3.125/3.125 MVA
3.125 MVA 0.109
37.05
4 kA IDT TR-2 LV-2
33.866 0.66 kV 36.71 33kV Cable IDT TR-1
3 kA IDT TR-3 LV-1
37.05 4.1 0 33.52 0.66 kV
IDT TR-2 LV-1 4 kA
0.66 kV 33.866 4.1
0.109
4.1
IDT TR-3 LV BUS DUCT
IDT TRANSFORMER-1
IDT TR-2 LV-1 BUS DUCT IDT TR-2 LV-2 BUS DUCT
6.25/3.125/3.125 MVA
36.71 LT PANEL -5 37.01
3 kA 33.52 0.66 kV 6 kA
37.05 LT PANEL -4 33.825
37.05
LT PANEL -3 4 kA 33.866 0.66 kV 4.1 IDT TR-1 LV-2 37.01
4 kA 0.66 kV 33.866 IDT TR-1 LV-1 4.1 6 kA
33.825 0.66 kV
4.1 4.1 0.66 kV
4.1
LV PANEL-5 BUS DUCT
IDT TR-3 LV -1 BUS DUCT
LV PANEL-4 BUS DUCT
LV PANEL-3 BUS DUCT
36.71
3 kA 33.52
INVERTER-5 AC BUS
0.66 kV IDT TR-3 LV -2 BUS DUCT
INVERTER-4 AC BUS 4.1
INVERTER-3 AC BUS 37.05
4 kA 0.66 kV
37.0 0.66 kV
5 4 kA 33.866 33.866
4.1 4.1
1.9/3.3kV 3C 35 Sq mm Al
37.01 37.01
3125kW INVERTER-5 LT PANEL -1 6 kA 6 kA LT PANEL-2
0.66 kV 33.825 33.825 0.66 kV
3125kW INVERTER-3
3125kW INVERTER-4 4.1 4.1 0
3125kW INVERTER-2
1.1kV 3C 35 Sq mm Al2
3125kW INVERTER-1
1.1kV 3C 35 Sq mm Al
page 1 11:06:12 Mar 04, 2024 Project File: 33kV Solar Plant
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 6
Contract: SN:
Branch Connections
25kVA Auxiliary Trafo 2W XFMR 25kVA TRAFO HT SIDE 25kVA TRAFO LV 1554.12 15510.09 15587.76
50kVA Auxiliary Trafo 2W XFMR 50 kVA TRAFO HT 50 kVA AUX TRAFO LV 777.06 7755.05 7793.88
IDT TRANSFORMER-3 2W XFMR IDT TRANSFORMER-3 HT IDT TR-3 LV-1 21.38 213.41 214.48
IDT TRANSFORMER-1 3W Xfmr IDT TRANSFORMER-1 HT IDT TR-1 LV-1 24.95 248.99 250.24
3W Xfmr IDT TR-1 LV-1 IDT TR-1 LV-2 124.69 1244.36 1250.59
IDT TRANSFORMER-2 3W Xfmr IDT TRANSFORMER-2 HT IDT TR-2 LV-1 24.95 248.99 250.24
3W Xfmr IDT TR-2 LV-1 IDT TR-2 LV-2 124.69 1244.36 1250.59
IDT TR-2 LV-1 BUS DUCT Bus Duct IDT TR-2 LV-1 LT PANEL -3
IDT TR-2 LV-2 BUS DUCT Bus Duct IDT TR-2 LV-2 LT PANEL -4
IDT TR-3 LV -1 BUS DUCT Bus Duct IDT TR-1 LV-1 LT PANEL -1
IDT TR-3 LV -2 BUS DUCT Bus Duct IDT TR-1 LV-2 LT PANEL-2
IDT TR-3 LV BUS DUCT Bus Duct IDT TR-3 LV-1 LT PANEL -5
1.1kV 3C 35 Sq mm Al Cable 50 kVA AUX TRAFO LV Auxiliary MDB 50kVA 2527.38 227.42 2537.59
1.1kV 3C 35 Sq mm Al2 Cable 25kVA TRAFO LV Auxiliary MDB 25kVA 2527.38 227.42 2537.59
1.9/3.3kV 3C 35 Sq mm Al Cable IDT TR-2 LV-2 Change Over Switch 799.41 71.93 802.64
1.9/3.3kV 3C 35 Sq mm Al. Cable LT PANEL-2 25kVA TRAFO HT SIDE 699.48 62.94 702.31
33kV Cable ICOG Panel Cable 33kV Outdoor HT Panel 33kV ICOG Panel 0.33 0.33 0.47
33kV Cable IDT TR-1 Cable 33kV ICOG Panel IDT TRANSFORMER-1 HT 0.05 0.04 0.06
33kV Cable IDT TR-2 Cable 33kV Outdoor HT Panel IDT TRANSFORMER-2 HT 0.06 0.06 0.08
33kV Cable IDT TR-3 Cable 33kV Outdoor HT Panel IDT TRANSFORMER-3 HT 0.06 0.06 0.08
33kV Cable XLPE Cable Cable OD Metering Switchyard 33kV Outdoor HT Panel 0.28 0.28 0.39
50kVA TRAFO Cable Cable Change Over Switch 50 kVA TRAFO HT 838.15 71.93 841.23
3R OH DOG CONDUCTOR Line 110kV/33kV Substation End OD Metering Switchyard 9.23 9.72 13.41
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 7
Contract: SN:
% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV R X" R/X
110kV / 33kV Substation 110kV/33kV Substation End 200.000 33.000 4.97519 49.75186 0.10
Contract: SN:
SHORT-CIRCUIT REPORT
25kVA TRAFO LV 25kVA TRAFO HT SIDE 0.00 0.000 0.000 999.9 0.000
Contract: SN:
Nominal kV = 0.415
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 2.135 kA Method C
Steady State = 0.912 kA rms
Auxiliary MDB 25kVA 25kVA TRAFO LV 0.00 0.000 0.000 999.9 0.000
25kVA TRAFO HT SIDE 25kVA TRAFO LV 102.19 0.130 -0.903 6.9 0.912
Contract: SN:
Nominal kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.481 kA Method C
Steady State = 3.145 kA rms
33kV Outdoor HT Panel 33kV ICOG Panel 0.81 0.660 -2.966 4.5 3.039
IDT TRANSFORMER-1 HT 33kV ICOG Panel 0.00 0.000 -0.109 999.9 0.109
Contract: SN:
33kV ICOG Panel 33kV Outdoor HT Panel 0.03 0.000 -0.109 999.9 0.109
IDT TRANSFORMER-2 HT 33kV Outdoor HT Panel 0.00 0.000 -0.109 999.9 0.109
IDT TRANSFORMER-3 HT 33kV Outdoor HT Panel 0.00 0.000 -0.055 999.9 0.055
OD Metering Switchyard 33kV Outdoor HT Panel 0.64 0.653 -2.822 4.3 2.897
Contract: SN:
Auxiliary MDB 50kVA 50 kVA AUX TRAFO LV 0.00 0.000 0.000 999.9 0.000
50 kVA TRAFO HT 50 kVA AUX TRAFO LV 95.87 0.491 -1.639 3.3 1.711
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 7.675 kA Method C
Steady State = 5.321 kA rms
Change Over Switch 50 kVA TRAFO HT 51.17 5.159 -1.301 0.3 5.321
50 kVA AUX TRAFO LV 50 kVA TRAFO HT 0.00 0.000 0.000 999.9 0.000
Contract: SN:
OD Metering Switchyard 110kV/33kV Substation End 2.09 0.000 -0.273 999.9 0.273
110kV / 33kV Substation 110kV/33kV Substation End 110.00 0.348 -3.482 10.0 3.499
Contract: SN:
25kVA TRAFO LV Auxiliary MDB 25kVA 15.87 0.250 -0.834 3.3 0.870
Contract: SN:
50 kVA AUX TRAFO LV Auxiliary MDB 50kVA 27.28 0.762 -1.287 1.7 1.495
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 14.632 kA Method C
Steady State = 10.136 kA rms
IDT TR-2 LV-2 Change Over Switch 93.00 9.349 -3.916 0.4 10.136
50 kVA TRAFO HT Change Over Switch 0.00 0.000 0.000 999.9 0.000
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000
IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms
IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520
Contract: SN:
33kV ICOG Panel IDT TRANSFORMER-1 HT 0.11 0.661 -2.963 4.5 3.036
IDT TR-1 LV-1 IDT TRANSFORMER-1 HT 7.82 0.000 -0.055 999.9 0.055
IDT TR-1 LV-2 IDT TRANSFORMER-1 HT 7.82 0.000 -0.055 999.9 0.055
Contract: SN:
33kV Outdoor HT Panel IDT TRANSFORMER-2 HT 0.14 0.654 -2.983 4.6 3.054
IDT TR-2 LV-1 IDT TRANSFORMER-2 HT 7.82 0.000 -0.055 999.9 0.055
IDT TR-2 LV-2 IDT TRANSFORMER-2 HT 7.82 0.000 -0.055 999.9 0.055
Contract: SN:
33kV Outdoor HT Panel IDT TRANSFORMER-3 HT 0.14 0.654 -3.037 4.6 3.107
IDT TR-3 LV-1 IDT TRANSFORMER-3 HT 6.70 0.000 -0.055 999.9 0.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000
IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms
IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms
IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775
IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms
Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000
IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811
IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055
Contract: SN:
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms
IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520
Contract: SN:
33kV Outdoor HT Panel OD Metering Switchyard 0.06 0.000 -0.273 999.9 0.273
110kV/33kV Substation End OD Metering Switchyard 22.31 0.647 -2.838 4.4 2.911
Contract: SN:
33kV ICOG Panel 33.000 33kV ICOG Panel Bus 3.145 6.481 3.145
33kV Outdoor HT Panel 33.000 33kV Outdoor HT Panel Bus 3.164 6.542 3.164
50 kVA AUX TRAFO LV 0.415 50 kVA AUX TRAFO LV Bus 1.711 3.433 1.711
110kV/33kV Substation 33.000 110kV/33kV Substation Open Air 3.771 8.996 3.771
End End
Auxiliary MDB 25kVA 0.415 Auxiliary MDB 25kVA Bus 0.870 1.746 0.870
Auxiliary MDB 50kVA 0.415 Auxiliary MDB 50kVA Bus 1.495 2.508 1.495
Change Over Switch 0.660 Change Over Switch Bus 10.136 14.632 10.136
IDT TR-1 LV-1 0.660 IDT TR-1 LV-1 Bus 37.016 83.682 33.825
0.660 IDT TR-3 LV -1 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
IDT TR-1 LV-2 0.660 IDT TR-1 LV-2 Bus 37.016 83.682 33.825
0.660 IDT TR-3 LV -2 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
IDT TR-2 LV-1 0.660 IDT TR-2 LV-1 Bus 37.054 83.868 33.866
0.660 IDT TR-2 LV-1 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
IDT TR-2 LV-2 0.660 IDT TR-2 LV-2 Bus 37.054 83.868 33.866
0.660 IDT TR-2 LV-2 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
IDT TR-3 LV-1 0.660 IDT TR-3 LV-1 Bus 36.713 83.400 33.520
0.660 IDT TR-3 LV BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
2
INVERTER-3 AC BUS 0.660 INVERTER-3 AC BUS Bus 37.054 83.868 33.866
0.660 LV PANEL-3 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
0.660 LV PANEL-4 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 38
Contract: SN:
0.660 LV PANEL-5 BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243
0.660 IDT TR-3 LV -1 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
0.660 IDT TR-3 LV -2 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
2
LT PANEL -3 0.660 LT PANEL -3 Bus 37.054 83.868 33.866
0.660 LV PANEL-3 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
0.660 IDT TR-2 LV-1 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
LT PANEL -4 0.660 LT PANEL -4 Bus 37.054 83.868 33.866
0.660 IDT TR-2 LV-2 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
0.660 LV PANEL-4 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
0.660 IDT TR-3 LV BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243
0.660 LV PANEL-5 BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243
Contract: SN: