Short Circuit Calculation Report

The short circuit calculation report is generated with Software Calculation with ETAP 19.0.1.
Short circuit calculation is worked out considering the following conditions:

Source Fault Level:-

 Rating of Source Transformer bay extension rating 16 MVA, 110kV/33kV Z-8%


 Base MVA = Source Transformer Rating =16MVA -----(1)

1. Calculating the transformer reactance on the 33kV side in per unit:

Formula: Reactance33kV= Percentage Reactance of Source transformer/100


=8 %/100 = 0.08 Percentage Reactance 33kV ---- (2)

2. Calculating the short circuit MVAsc at the 33kV side:

Formula: Short Circuit MVAsc 33kV=Base MVA33kV /Reactance 33kV

Short Circuit MVA33kV=16MVA /0.08 = 200 MVASc ---- (3)

SC calculations are done in accordance with IEC 60909 -------- (1) Reference of the
Equation (1), (2) , (3)

Short circuit calculation is worked out considering the following conditions:-

1. The short circuit calculation report is generated with ETAP 19.1 version.
2. THE Solar Plant BRANCH CIRCUIT MAIN CB SHALL BE CONNECTED TO A
TRANSFORMER WITH THE FOLLOWING DATA 16 MVA, 110kV/33kV Z-8%
3. We have considered Transformer MVA= Base MVA , So MVAbase = 16 MVA , kVbase =
33kV
4. Inverters and PV array station considered as a generating load while deriving short circuit
level to check fault contribution for each bus at 0.660kV bus.
5. SC calculations are done in accordance with IEC 60909.

2
One-Line Diagram - OLV1 (Edit Mode)

110kV / 33kV Substation


200 MVAsc

110kV/33kV Substation End

3 km 3R OH DOG CONDUCTOR

33 kV
OD Metering Switchyard

300 m 1-3/C 300


33kV Cable Incoming
33 kV
33kV Outdoor HT Panel

1-3/C 300 60 m 1-3/C 300


60 m 33kV Cable IDT TR-3 1-3/C 300
33kV Cable IDT TR-2 260 m
33kV Cable ICOG Panel

IDT TRANSFORMER-2 HT IDT TRANSFORMER-3 HT

IDT TRANSFORMER-2 33 kV
6.25/3.125/3.125 MVA IDT TRANSFORMER-3 33kV ICOG Panel
3.125 MVA

IDT TR-2 LV-2 1-3/C 300


0.66 kV 50 m
IDT TR-3 LV-1 33kV Cable IDT TR-1
0.66 kV
IDT TR-2 LV-1
0.66 kV
IDT TRANSFORMER-1 HT
8 m 3500 A
IDT TR-3 LV BUS DUCT
10 m 3500 A 10 m 3500 A IDT TRANSFORMER-1
IDT TR-2 LV-1 BUS DUCT IDT TR-2 LV-2 BUS DUCT
6.25/3.125/3.125 MVA
LT PANEL -5
LT PANEL -4 0.66 kV
LT PANEL -3 0.66 kV
0.66 kV IDT TR-1 LV-2
IDT TR-1 LV-1
0.66 kV
0.66 kV
2 m 3500 A 10 m
LV PANEL-5 BUS DUCT 3500 A
2 m 3500 A
2m LV PANEL-4 BUS DUCT IDT TR-3 LV -1 BUS DUCT
LV PANEL-3 BUS DUCT
3500 A 10 m
INVERTER-5 AC BUS 3500 A
0.66 kV IDT TR-3 LV -2 BUS DUCT
INVERTER-4 AC BUS
INVERTER-3 AC BUS
1.9/3.3kV 3C 35 Sq mm Al

0.66 kV
0.66 kV

1-3/C 35 3125kW INVERTER-5 LT PANEL -1 LT PANEL-2


40 m 0.66 kV 0.66 kV
3125kW INVERTER-3
3125kW INVERTER-4

2 m 3500 A 1-3/C 35
35 m 1.9/3.3kV 3C 35 Sq mm Al.
LV PANEL-1 BUS DUCT
3500 A 2 m
0.66 kV LV PANEL-1 BUS DUCT2
Change Over Switch

INVERTER-1 AC BUS 25kVA TRAFO HT SIDE


INVERTER-2 AC BUS
40 m 0.66 kV 0.66 kV
50kVA TRAFO Cable

50 kVA TRAFO HT 25kVA Auxiliary Trafo


25 kVA

50kVA Auxiliary Trafo


50 kVA

50 kVA AUX TRAFO LV 3125kW INVERTER-2 25kVA TRAFO LV

1-4/C 35 50 m 3125kW INVERTER-1


1-4/C 35 50 m
1.1kV 3C 35 Sq mm Al
1.1kV 3C 35 Sq mm Al2

Auxiliary MDB 50kVA Auxiliary MDB 25kVA


0.415 kV 0.415 kV

page 1 08:24:46 Feb 15, 2024 Project File: 33kV Solar Plant
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 1
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Project Developer: RADIANCE RENEWABLES PVT LTD SN:
Owners Engineer: SGURR ENERGY PVT LTD Revision: Base
Study Case: SC
EPC Contractor: SOLON INDIA PVT LTD Config.: Normal

Electrical Transient Analyzer Program

Short-Circuit Analysis

IEC 60909 Standard

3-Phase Fault Currents

Swing V-Control Load Total

Number of Buses: 1 0 28 29

Line/Cable/
XFMR2 XFMR3 Reactor Busway Impedance Tie PD Total

Number of Branches: 3 2 0 11 0 10 26

Synchronous Power Synchronous Induction Lumped


Generator Grid Motor Machines Load Total

Number of Machines: 0 1 0 0 0 1

System Frequency: 50.00

Unit System: Metric

Project Filename: 33kV Solar Plant

Output Filename: C:\ETAP 1901\33kV Solar Plant\SC.SI1S


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 2
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Contract: SN:
Engineer: DARSHIT VYAS Revision: Base
Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Adjustments

Apply Individual
Tolerance Adjustments /Global Percent
Transformer Impedance: Yes Individual

Reactor Impedance: Yes Individual

Overload Heater Resistance: No

Transmission Line Length: Yes

Cable / Busway Length: Yes

Apply Individual
Temperature Correction Adjustments /Global Degree C
Transmission Line Resistance: Yes Global 20

Cable / Busway Resistance: Yes Global 20


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 3
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Contract: SN:
Engineer: DARSHIT VYAS Revision: Base
Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Bus Input Data

Bus Initial Voltage


ID Type Nom. kV Base kV Sub-sys %Mag. Ang.

25kVA TRAFO HT SIDE Load 0.660 0.660 1 100.00 0.00


25kVA TRAFO LV Load 0.415 0.415 1 100.00 0.00
33kV ICOG Panel Load 33.000 33.000 1 100.00 0.00
33kV Outdoor HT Panel Load 33.000 33.000 1 100.00 0.00
50 kVA AUX TRAFO LV Load 0.415 0.415 1 100.00 0.00
50 kVA TRAFO HT Load 0.660 0.660 1 100.00 0.00
110kV/33kV Substation End SWNG 33.000 33.000 1 100.00 0.00
Auxiliary MDB 25kVA Load 0.415 0.415 1 100.00 0.00
Auxiliary MDB 50kVA Load 0.415 0.415 1 100.00 0.00
Change Over Switch Load 0.660 0.660 1 100.00 0.00
IDT TR-1 LV-1 Load 0.660 0.660 1 100.00 0.00
IDT TR-1 LV-2 Load 0.660 0.660 1 100.00 0.00
IDT TR-2 LV-1 Load 0.660 0.660 1 100.00 0.00
IDT TR-2 LV-2 Load 0.660 0.660 1 100.00 0.00
IDT TR-3 LV-1 Load 0.660 0.660 1 100.00 0.00
IDT TRANSFORMER-1 HT Load 33.000 33.000 1 100.00 0.00
IDT TRANSFORMER-2 HT Load 33.000 33.000 1 100.00 0.00
IDT TRANSFORMER-3 HT Load 33.000 33.000 1 100.00 0.00
INVERTER-1 AC BUS Load 0.660 0.660 1 100.00 0.00
INVERTER-2 AC BUS Load 0.660 0.660 1 100.00 0.00
INVERTER-3 AC BUS Load 0.660 0.660 1 100.00 0.00
INVERTER-4 AC BUS Load 0.660 0.660 1 100.00 0.00
INVERTER-5 AC BUS Load 0.660 0.660 1 100.00 0.00
LT PANEL -1 Load 0.660 0.660 1 100.00 0.00
LT PANEL-2 Load 0.660 0.660 1 100.00 0.00
LT PANEL -3 Load 0.660 0.660 1 100.00 0.00
LT PANEL -4 Load 0.660 0.660 1 100.00 0.00
LT PANEL -5 Load 0.660 0.660 1 100.00 0.00
OD Metering Switchyard Load 33.000 33.000 1 100.00 0.00

29 Buses Total

All voltages reported by ETAP are in % of bus Nominal kV.


Base kV values of buses are calculated and used internally by ETAP.
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 4
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Contract: SN:
Engineer: DARSHIT VYAS Revision: Base
Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Line/Cable/Busway Input Data

ohms or siemens/1000 m per Conductor (Cable) or per Phase (Line/Busway)


Line/Cable/Busway Length

ID Library Size Adj. (m) % Tol. #/Phase T (C) R X Y

1.1kV 3C 35 Sq mm Al Changeover 1.0MCUN4 35 50.0 0 1 90 1.11000 0.09400 0.0001015


1.1kV 3C 35 Sq mm Al LT PNL 1.0MCUN4 35 50.0 0 1 90 1.11000 0.09400 0.0001015
1.9/3.3kV 3C 35 Sq mm Al 50kVA 1.0NCUN3 35 40.0 0 1 90 1.11000 0.09400 0.0001015
1.9/3.3kV 3C 35 Sq mm Al. 25kvA 1.0NCUN3 35 35.0 0 1 90 1.11000 0.09400 0.0001015
33kV Cable ICOG Panel 33NALN3 300 260.0 0 1 90 0.12800 0.10000 0.0144000
33kV Cable IDT TR-1 33NALN3 300 50.0 0 1 90 0.12800 0.10000 0.0144000
33kV Cable IDT TR-2 33NALN3 300 60.0 0 1 90 0.12800 0.10000 0.0144000
33kV Cable IDT TR-3 33NALN3 300 60.0 0 1 90 0.12800 0.10000 0.0144000
33kV Cable Incoming 33NALN3 300 300.0 0 1 90 0.12800 0.10000 0.0144000
3R OH DOG CONDUCTOR 100 3000.0 0 3 70 0.33500 0.35300 0.0010000

Line / Cable / Busway resistances are listed at the specified temperatures.


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 5
Location: TAMIL NADU 19.0.1C Date: 02-24-2024
Contract: SN:
Engineer: DARSHIT VYAS Revision: Base
Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

2-Winding Transformer Input Data

Transformer Rating Z Variation % Tap Setting Adjusted


ID MVA Prim. kV Sec. kV %Z X/R + 5% - 5% % Tol. Prim. Sec. %Z

25kVA Auxiliary Trafo 0.025 0.660 0.415 4.50 9.98 0 0 0 0 0 4.0000

50kVA Auxiliary Trafo 0.050 0.660 0.415 4.50 9.98 0 0 0 0 0 4.0000

IDT TRANSFORMER-3 3.125 33.000 0.660 7.00 9.98 0 0 0 0 0 7.0000

3-Winding Transformer Input Data

Transformer Rating Tap * Impedance Z Variation


ID Winding MVA kV % %Z X/R MVAb % Tol. + 5% - 5%

IDT TRANSFORMER-1 Primary: 6.250 33.000 Zps = 14.00 9.98 6.250 0 0 0

Secondary: 3.125 0.660 Zpt = 7.00 9.98 6.250 0

Tertiary: 3.125 0.660 Zst = 7.00 9.98 6.250 0

IDT TRANSFORMER-2 Primary: 6.250 33.000 Zps = 14.00 9.98 6.250 0 0 0

Secondary: 3.125 0.660 Zpt = 7.00 9.98 6.250 0

Tertiary: 3.125 0.660 Zst = 7.00 9.98 6.250 0

* Nominal tap settings are used for the calculation.


One-Line Diagram - OLV1 (Short-Circuit Analysis)

110kV / 33kV Substation


200 MVAsc

3.499

3.178
kA 2.911 33 kV
OD Metering Switchyard
0.273

33kV Cable XLPE Cable 3.164


33 kV kA
2.897 33kV Outdoor HT Panel
0.109 0.055 0.109

33kV Cable IDT TR-2 33kV Cable IDT TR-3

33kV Cable ICOG Panel

0.109
3.145
IDT TRANSFORMER-2 33 kV kA
IDT TRANSFORMER-3 3.039 33kV ICOG Panel
6.25/3.125/3.125 MVA
3.125 MVA 0.109

37.05
4 kA IDT TR-2 LV-2
33.866 0.66 kV 36.71 33kV Cable IDT TR-1
3 kA IDT TR-3 LV-1
37.05 4.1 0 33.52 0.66 kV
IDT TR-2 LV-1 4 kA
0.66 kV 33.866 4.1
0.109
4.1
IDT TR-3 LV BUS DUCT
IDT TRANSFORMER-1
IDT TR-2 LV-1 BUS DUCT IDT TR-2 LV-2 BUS DUCT
6.25/3.125/3.125 MVA
36.71 LT PANEL -5 37.01
3 kA 33.52 0.66 kV 6 kA
37.05 LT PANEL -4 33.825
37.05
LT PANEL -3 4 kA 33.866 0.66 kV 4.1 IDT TR-1 LV-2 37.01
4 kA 0.66 kV 33.866 IDT TR-1 LV-1 4.1 6 kA
33.825 0.66 kV
4.1 4.1 0.66 kV
4.1
LV PANEL-5 BUS DUCT
IDT TR-3 LV -1 BUS DUCT
LV PANEL-4 BUS DUCT
LV PANEL-3 BUS DUCT
36.71
3 kA 33.52
INVERTER-5 AC BUS
0.66 kV IDT TR-3 LV -2 BUS DUCT
INVERTER-4 AC BUS 4.1
INVERTER-3 AC BUS 37.05
4 kA 0.66 kV
37.0 0.66 kV
5 4 kA 33.866 33.866
4.1 4.1
1.9/3.3kV 3C 35 Sq mm Al

37.01 37.01
3125kW INVERTER-5 LT PANEL -1 6 kA 6 kA LT PANEL-2
0.66 kV 33.825 33.825 0.66 kV
3125kW INVERTER-3
3125kW INVERTER-4 4.1 4.1 0

LV PANEL-1 BUS DUCT 1.9/3.3kV 3C 35 Sq mm Al.

0.66 kV LV PANEL-1 BUS DUCT2


10.13
6 kA Change Over Switch
10.136
INVERTER-1 AC BUS 37.01
0 6 kA 37.01 INVERTER-2 AC BUS
0.66 kV 33.825
6 kA 0.66 kV
33.825
50kVA TRAFO Cable
4.1 4.1 25kVA Auxiliary Trafo
25 kVA

50kVA Auxiliary Trafo


50 kVA

3125kW INVERTER-2
1.1kV 3C 35 Sq mm Al2
3125kW INVERTER-1
1.1kV 3C 35 Sq mm Al

Auxiliary MDB 50kVA Auxiliary MDB 25kVA


1.373
0.415 kV 0.783 0.783
kA 0.415 kV
1.373
kA

page 1 11:06:12 Mar 04, 2024 Project File: 33kV Solar Plant
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 6

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Branch Connections

CKT/Branch Connected Bus ID % Impedance, Pos. Seq., 100 MVAb

ID Type From Bus To Bus R X Z Y

25kVA Auxiliary Trafo 2W XFMR 25kVA TRAFO HT SIDE 25kVA TRAFO LV 1554.12 15510.09 15587.76

50kVA Auxiliary Trafo 2W XFMR 50 kVA TRAFO HT 50 kVA AUX TRAFO LV 777.06 7755.05 7793.88

IDT TRANSFORMER-3 2W XFMR IDT TRANSFORMER-3 HT IDT TR-3 LV-1 21.38 213.41 214.48

IDT TRANSFORMER-1 3W Xfmr IDT TRANSFORMER-1 HT IDT TR-1 LV-1 24.95 248.99 250.24

3W Xfmr IDT TRANSFORMER-1 HT IDT TR-1 LV-2 24.95 248.99 250.24

3W Xfmr IDT TR-1 LV-1 IDT TR-1 LV-2 124.69 1244.36 1250.59

IDT TRANSFORMER-2 3W Xfmr IDT TRANSFORMER-2 HT IDT TR-2 LV-1 24.95 248.99 250.24

3W Xfmr IDT TRANSFORMER-2 HT IDT TR-2 LV-2 24.95 248.99 250.24

3W Xfmr IDT TR-2 LV-1 IDT TR-2 LV-2 124.69 1244.36 1250.59

IDT TR-2 LV-1 BUS DUCT Bus Duct IDT TR-2 LV-1 LT PANEL -3

IDT TR-2 LV-2 BUS DUCT Bus Duct IDT TR-2 LV-2 LT PANEL -4

IDT TR-3 LV -1 BUS DUCT Bus Duct IDT TR-1 LV-1 LT PANEL -1

IDT TR-3 LV -2 BUS DUCT Bus Duct IDT TR-1 LV-2 LT PANEL-2

IDT TR-3 LV BUS DUCT Bus Duct IDT TR-3 LV-1 LT PANEL -5

LV PANEL-1 BUS DUCT Bus Duct LT PANEL -1 INVERTER-1 AC BUS

LV PANEL-1 BUS DUCT2 Bus Duct LT PANEL-2 INVERTER-2 AC BUS

LV PANEL-3 BUS DUCT Bus Duct LT PANEL -3 INVERTER-3 AC BUS

LV PANEL-4 BUS DUCT Bus Duct LT PANEL -4 INVERTER-4 AC BUS

LV PANEL-5 BUS DUCT Bus Duct LT PANEL -5 INVERTER-5 AC BUS

1.1kV 3C 35 Sq mm Al Cable 50 kVA AUX TRAFO LV Auxiliary MDB 50kVA 2527.38 227.42 2537.59

1.1kV 3C 35 Sq mm Al2 Cable 25kVA TRAFO LV Auxiliary MDB 25kVA 2527.38 227.42 2537.59

1.9/3.3kV 3C 35 Sq mm Al Cable IDT TR-2 LV-2 Change Over Switch 799.41 71.93 802.64

1.9/3.3kV 3C 35 Sq mm Al. Cable LT PANEL-2 25kVA TRAFO HT SIDE 699.48 62.94 702.31

33kV Cable ICOG Panel Cable 33kV Outdoor HT Panel 33kV ICOG Panel 0.33 0.33 0.47

33kV Cable IDT TR-1 Cable 33kV ICOG Panel IDT TRANSFORMER-1 HT 0.05 0.04 0.06

33kV Cable IDT TR-2 Cable 33kV Outdoor HT Panel IDT TRANSFORMER-2 HT 0.06 0.06 0.08

33kV Cable IDT TR-3 Cable 33kV Outdoor HT Panel IDT TRANSFORMER-3 HT 0.06 0.06 0.08

33kV Cable XLPE Cable Cable OD Metering Switchyard 33kV Outdoor HT Panel 0.28 0.28 0.39

50kVA TRAFO Cable Cable Change Over Switch 50 kVA TRAFO HT 838.15 71.93 841.23

3R OH DOG CONDUCTOR Line 110kV/33kV Substation End OD Metering Switchyard 9.23 9.72 13.41
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 7

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Power Grid Input Data

% Impedance
Power Grid Connected Bus Rating 100 MVA Base
ID ID MVASC kV R X" R/X

110kV / 33kV Substation 110kV/33kV Substation End 200.000 33.000 4.97519 49.75186 0.10

Total Connected Power Grids ( = 1 ): 200.000 MVA


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 8

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

SHORT-CIRCUIT REPORT

3-Phase fault at bus: 25kVA TRAFO HT


SIDE
Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 16.351 kA Method C
Steady State = 11.318 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

25kVA TRAFO HT SIDE Total 0.00 10.268 -4.762 0.5 11.318

LT PANEL-2 25kVA TRAFO HT SIDE 90.87 10.268 -4.762 0.5 11.318

25kVA TRAFO LV 25kVA TRAFO HT SIDE 0.00 0.000 0.000 999.9 0.000

3125kW INVERTER-2 INVERTER-2 AC BUS 90.87 0.000 0.000 0.0 0.000

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 11.318 11.318 0.018

0.02 11.318 11.318 0.000

0.03 11.318 11.318 0.000

0.04 11.318 11.318 0.000

0.05 11.318 11.318 0.000

0.06 11.318 11.318 0.000

0.07 11.318 11.318 0.000

0.08 11.318 11.318 0.000

0.09 11.318 11.318 0.000

0.10 11.318 11.318 0.000

0.15 11.318 11.318 0.000

0.20 11.318 11.318 0.000

0.25 11.318 11.318 0.000

0.30 11.318 11.318 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 9

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 25kVA TRAFO LV

Nominal kV = 0.415
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 2.135 kA Method C
Steady State = 0.912 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

25kVA TRAFO LV Total 0.00 0.130 -0.903 6.9 0.912

Auxiliary MDB 25kVA 25kVA TRAFO LV 0.00 0.000 0.000 999.9 0.000

25kVA TRAFO HT SIDE 25kVA TRAFO LV 102.19 0.130 -0.903 6.9 0.912

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 0.912 1.226 0.819

0.02 0.912 1.050 0.520

0.03 0.912 0.970 0.330

0.04 0.912 0.936 0.210

0.05 0.912 0.922 0.133

0.06 0.912 0.916 0.085

0.07 0.912 0.914 0.054

0.08 0.912 0.913 0.034

0.09 0.912 0.912 0.022

0.10 0.912 0.912 0.014

0.15 0.912 0.912 0.001

0.20 0.912 0.912 0.000

0.25 0.912 0.912 0.000

0.30 0.912 0.912 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 10

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 33kV ICOG Panel

Nominal kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.481 kA Method C
Steady State = 3.145 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

33kV ICOG Panel Total 0.00 0.660 -3.075 4.7 3.145

33kV Outdoor HT Panel 33kV ICOG Panel 0.81 0.660 -2.966 4.5 3.039

IDT TRANSFORMER-1 HT 33kV ICOG Panel 0.00 0.000 -0.109 999.9 0.109

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.145 3.688 1.927

0.02 3.145 3.277 0.920

0.03 3.145 3.176 0.439

0.04 3.145 3.152 0.210

0.05 3.145 3.147 0.100

0.06 3.145 3.146 0.048

0.07 3.145 3.145 0.023

0.08 3.145 3.145 0.011

0.09 3.145 3.145 0.005

0.10 3.145 3.145 0.002

0.15 3.145 3.145 0.000

0.20 3.145 3.145 0.000

0.25 3.145 3.145 0.000

0.30 3.145 3.145 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 11

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 33kV Outdoor HT


Panel
Nominal kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.542 kA Method C
Steady State = 3.164 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

33kV Outdoor HT Panel Total 0.00 0.653 -3.096 4.7 3.164

33kV ICOG Panel 33kV Outdoor HT Panel 0.03 0.000 -0.109 999.9 0.109

IDT TRANSFORMER-2 HT 33kV Outdoor HT Panel 0.00 0.000 -0.109 999.9 0.109

IDT TRANSFORMER-3 HT 33kV Outdoor HT Panel 0.00 0.000 -0.055 999.9 0.055

OD Metering Switchyard 33kV Outdoor HT Panel 0.64 0.653 -2.822 4.3 2.897

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.164 3.723 1.962

0.02 3.164 3.303 0.948

0.03 3.164 3.197 0.459

0.04 3.164 3.171 0.222

0.05 3.164 3.165 0.107

0.06 3.164 3.164 0.052

0.07 3.164 3.164 0.025

0.08 3.164 3.164 0.012

0.09 3.164 3.164 0.006

0.10 3.164 3.164 0.003

0.15 3.164 3.164 0.000

0.20 3.164 3.164 0.000

0.25 3.164 3.164 0.000

0.30 3.164 3.164 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 12

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 50 kVA AUX TRAFO


LV
Nominal kV = 0.415
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 3.433 kA Method C
Steady State = 1.711 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

50 kVA AUX TRAFO LV Total 0.00 0.491 -1.639 3.3 1.711

Auxiliary MDB 50kVA 50 kVA AUX TRAFO LV 0.00 0.000 0.000 999.9 0.000

50 kVA TRAFO HT 50 kVA AUX TRAFO LV 95.87 0.491 -1.639 3.3 1.711

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 1.711 1.954 0.944

0.02 1.711 1.750 0.368

0.03 1.711 1.717 0.144

0.04 1.711 1.712 0.056

0.05 1.711 1.711 0.022

0.06 1.711 1.711 0.009

0.07 1.711 1.711 0.003

0.08 1.711 1.711 0.001

0.09 1.711 1.711 0.001

0.10 1.711 1.711 0.000

0.15 1.711 1.711 0.000

0.20 1.711 1.711 0.000

0.25 1.711 1.711 0.000

0.30 1.711 1.711 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 13

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 50 kVA TRAFO HT

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 7.675 kA Method C
Steady State = 5.321 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

50 kVA TRAFO HT Total 0.00 5.159 -1.301 0.3 5.321

Change Over Switch 50 kVA TRAFO HT 51.17 5.159 -1.301 0.3 5.321

50 kVA AUX TRAFO LV 50 kVA TRAFO HT 0.00 0.000 0.000 999.9 0.000

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 5.321 5.321 0.000

0.02 5.321 5.321 0.000

0.03 5.321 5.321 0.000

0.04 5.321 5.321 0.000

0.05 5.321 5.321 0.000

0.06 5.321 5.321 0.000

0.07 5.321 5.321 0.000

0.08 5.321 5.321 0.000

0.09 5.321 5.321 0.000

0.10 5.321 5.321 0.000

0.15 5.321 5.321 0.000

0.20 5.321 5.321 0.000

0.25 5.321 5.321 0.000

0.30 5.321 5.321 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 14

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: 110kV/33kV


Substation End
Nominal kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 8.996 kA Method C
Steady State = 3.771 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

110kV/33kV Substation End Total 0.00 0.348 -3.755 10.8 3.771

OD Metering Switchyard 110kV/33kV Substation End 2.09 0.000 -0.273 999.9 0.273

110kV / 33kV Substation 110kV/33kV Substation End 110.00 0.348 -3.482 10.0 3.499

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.771 5.204 3.586

0.02 3.771 4.592 2.619

0.03 3.771 4.229 1.913

0.04 3.771 4.022 1.397

0.05 3.771 3.907 1.021

0.06 3.771 3.844 0.746

0.07 3.771 3.810 0.545

0.08 3.771 3.792 0.398

0.09 3.771 3.782 0.290

0.10 3.771 3.777 0.212

0.15 3.771 3.771 0.044

0.20 3.771 3.771 0.009

0.25 3.771 3.771 0.002

0.30 3.771 3.771 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 15

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus:


Auxiliary MDB 25kV
Nominal
A kV = 0.415
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 1.746 kA Method C
Steady State = 0.870 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

Auxiliary MDB 25kVA Total 0.00 0.250 -0.834 3.3 0.870

25kVA TRAFO LV Auxiliary MDB 25kVA 15.87 0.250 -0.834 3.3 0.870

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 0.870 0.994 0.480

0.02 0.870 0.890 0.187

0.03 0.870 0.873 0.073

0.04 0.870 0.871 0.029

0.05 0.870 0.870 0.011

0.06 0.870 0.870 0.004

0.07 0.870 0.870 0.002

0.08 0.870 0.870 0.001

0.09 0.870 0.870 0.000

0.10 0.870 0.870 0.000

0.15 0.870 0.870 0.000

0.20 0.870 0.870 0.000

0.25 0.870 0.870 0.000

0.30 0.870 0.870 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 16

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus:


Auxiliary MDB 50kV
Nominal
A kV = 0.415
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 2.508 kA Method C
Steady State = 1.495 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

Auxiliary MDB 50kVA Total 0.00 0.762 -1.287 1.7 1.495

50 kVA AUX TRAFO LV Auxiliary MDB 50kVA 27.28 0.762 -1.287 1.7 1.495

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 1.495 1.531 0.329

0.02 1.495 1.496 0.051

0.03 1.495 1.495 0.008

0.04 1.495 1.495 0.001

0.05 1.495 1.495 0.000

0.06 1.495 1.495 0.000

0.07 1.495 1.495 0.000

0.08 1.495 1.495 0.000

0.09 1.495 1.495 0.000

0.10 1.495 1.495 0.000

0.15 1.495 1.495 0.000

0.20 1.495 1.495 0.000

0.25 1.495 1.495 0.000

0.30 1.495 1.495 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 17

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: Change Over Switch

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 14.632 kA Method C
Steady State = 10.136 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

Change Over Switch Total 0.00 9.349 -3.916 0.4 10.136

IDT TR-2 LV-2 Change Over Switch 93.00 9.349 -3.916 0.4 10.136

50 kVA TRAFO HT Change Over Switch 0.00 0.000 0.000 999.9 0.000

3125kW INVERTER-4 INVERTER-4 AC BUS 93.00 0.000 0.000 0.0 0.000

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 10.136 10.136 0.008

0.02 10.136 10.136 0.000

0.03 10.136 10.136 0.000

0.04 10.136 10.136 0.000

0.05 10.136 10.136 0.000

0.06 10.136 10.136 0.000

0.07 10.136 10.136 0.000

0.08 10.136 10.136 0.000

0.09 10.136 10.136 0.000

0.10 10.136 10.136 0.000

0.15 10.136 10.136 0.000

0.20 10.136 10.136 0.000

0.25 10.136 10.136 0.000

0.30 10.136 10.136 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 18

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: IDT TR-1 LV-1

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TR-1 LV-1 Total 0.00 7.269 -36.296 5.0 37.016

IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050

3125kW INVERTER-1 INVERTER-1 AC BUS 0.00 3.056 -2.734 0.9 4.100

3125kW INVERTER-2 INVERTER-2 AC BUS 72.20 0.031 -1.521 48.6 1.521

LT PANEL -1 IDT TR-1 LV-1 0.00 3.056 -2.734 0.9 4.100

INVERTER-1 AC BUS LT PANEL -1 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 19

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: IDT TR-1 LV-2

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TR-1 LV-2 Total 0.00 7.269 -36.296 5.0 37.016

IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050

25kVA TRAFO HT SIDE LT PANEL-2 0.00 0.000 0.000 999.9 0.000

3125kW INVERTER-2 INVERTER-2 AC BUS 0.00 3.056 -2.734 0.9 4.100

3125kW INVERTER-1 INVERTER-1 AC BUS 72.20 0.031 -1.521 48.6 1.521

LT PANEL-2 IDT TR-1 LV-2 0.00 3.056 -2.734 0.9 4.100

INVERTER-2 AC BUS LT PANEL-2 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 20

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: IDT TR-2 LV-1

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TR-2 LV-1 Total 0.00 7.242 -36.340 5.0 37.054

IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-3 INVERTER-3 AC BUS 0.00 3.056 -2.734 0.9 4.100

3125kW INVERTER-4 INVERTER-4 AC BUS 72.27 0.030 -1.517 51.0 1.517

LT PANEL -3 IDT TR-2 LV-1 0.00 3.056 -2.734 0.9 4.100

INVERTER-3 AC BUS LT PANEL -3 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.079 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.920

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 21

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: IDT TR-2 LV-2

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TR-2 LV-2 Total 0.00 7.242 -36.340 5.0 37.054

Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000

IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-4 INVERTER-4 AC BUS 0.00 3.056 -2.734 0.9 4.100

3125kW INVERTER-3 INVERTER-3 AC BUS 72.27 0.030 -1.517 51.0 1.517

LT PANEL -4 IDT TR-2 LV-2 0.00 3.056 -2.734 0.9 4.100

INVERTER-4 AC BUS LT PANEL -4 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.078 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.919

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 22

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: IDT TR-3 LV-1

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TR-3 LV-1 Total 0.00 7.246 -35.991 5.0 36.713

IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520

3125kW INVERTER-5 INVERTER-5 AC BUS 0.00 3.056 -2.734 0.9 4.100

LT PANEL -5 IDT TR-3 LV-1 0.00 3.056 -2.734 0.9 4.100

INVERTER-5 AC BUS LT PANEL -5 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 36.713 47.827 30.651

0.02 36.713 41.960 20.317

0.03 36.713 39.105 13.467

0.04 36.713 37.783 8.926

0.05 36.713 37.187 5.916

0.06 36.713 36.922 3.922

0.07 36.713 36.805 2.599

0.08 36.713 36.754 1.723

0.09 36.713 36.731 1.142

0.10 36.713 36.721 0.757

0.15 36.713 36.713 0.097

0.20 36.713 36.713 0.012

0.25 36.713 36.713 0.002

0.30 36.713 36.713 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 23

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus:


IDT TRANSFORMER-
Nominal
1 HT kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.472 kA Method C
Steady State = 3.143 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TRANSFORMER-1 HT Total 0.00 0.661 -3.073 4.6 3.143

33kV ICOG Panel IDT TRANSFORMER-1 HT 0.11 0.661 -2.963 4.5 3.036

IDT TR-1 LV-1 IDT TRANSFORMER-1 HT 7.82 0.000 -0.055 999.9 0.055

IDT TR-1 LV-2 IDT TRANSFORMER-1 HT 7.82 0.000 -0.055 999.9 0.055

3125kW INVERTER-1 INVERTER-1 AC BUS 7.82 0.000 -2.734 37320540.0 2.734

3125kW INVERTER-2 INVERTER-2 AC BUS 7.82 0.000 -2.734 37320540.0 2.734

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.143 3.684 1.922

0.02 3.143 3.274 0.916

0.03 3.143 3.173 0.437

0.04 3.143 3.150 0.208

0.05 3.143 3.145 0.099

0.06 3.143 3.143 0.047

0.07 3.143 3.143 0.023

0.08 3.143 3.143 0.011

0.09 3.143 3.143 0.005

0.10 3.143 3.143 0.002

0.15 3.143 3.143 0.000

0.20 3.143 3.143 0.000

0.25 3.143 3.143 0.000

0.30 3.143 3.143 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 24

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus:


IDT TRANSFORMER-
Nominal
2 HT kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.532 kA Method C
Steady State = 3.161 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TRANSFORMER-2 HT Total 0.00 0.654 -3.092 4.7 3.161

33kV Outdoor HT Panel IDT TRANSFORMER-2 HT 0.14 0.654 -2.983 4.6 3.054

IDT TR-2 LV-1 IDT TRANSFORMER-2 HT 7.82 0.000 -0.055 999.9 0.055

IDT TR-2 LV-2 IDT TRANSFORMER-2 HT 7.82 0.000 -0.055 999.9 0.055

3125kW INVERTER-3 INVERTER-3 AC BUS 7.82 0.000 -2.734 37320540.0 2.734

3125kW INVERTER-4 INVERTER-4 AC BUS 7.82 0.000 -2.734 37320540.0 2.734

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.161 3.717 1.956

0.02 3.161 3.298 0.944

0.03 3.161 3.193 0.455

0.04 3.161 3.168 0.220

0.05 3.161 3.162 0.106

0.06 3.161 3.161 0.051

0.07 3.161 3.161 0.025

0.08 3.161 3.161 0.012

0.09 3.161 3.161 0.006

0.10 3.161 3.161 0.003

0.15 3.161 3.161 0.000

0.20 3.161 3.161 0.000

0.25 3.161 3.161 0.000

0.30 3.161 3.161 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 25

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus:


IDT TRANSFORMER-
Nominal
3 HT kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.532 kA Method C
Steady State = 3.161 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

IDT TRANSFORMER-3 HT Total 0.00 0.654 -3.092 4.7 3.161

33kV Outdoor HT Panel IDT TRANSFORMER-3 HT 0.14 0.654 -3.037 4.6 3.107

IDT TR-3 LV-1 IDT TRANSFORMER-3 HT 6.70 0.000 -0.055 999.9 0.055

3125kW INVERTER-5 INVERTER-5 AC BUS 6.70 0.000 -2.734 37320540.0 2.734

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.161 3.717 1.956

0.02 3.161 3.298 0.944

0.03 3.161 3.193 0.455

0.04 3.161 3.168 0.220

0.05 3.161 3.162 0.106

0.06 3.161 3.161 0.051

0.07 3.161 3.161 0.025

0.08 3.161 3.161 0.012

0.09 3.161 3.161 0.006

0.10 3.161 3.161 0.003

0.15 3.161 3.161 0.000

0.20 3.161 3.161 0.000

0.25 3.161 3.161 0.000

0.30 3.161 3.161 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 26

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: INVERTER-1 AC BUS

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-1 INVERTER-1 AC BUS 0.00 3.056 -2.734 0.9 4.100

INVERTER-1 AC BUS Total 0.00 7.269 -36.296 5.0 37.016

IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050

3125kW INVERTER-2 INVERTER-2 AC BUS 72.20 0.031 -1.521 48.6 1.521

IDT TR-1 LV-1 LT PANEL -1 0.00 4.213 -33.562 8.0 33.825

LT PANEL -1 INVERTER-1 AC BUS 0.00 4.213 -33.562 8.0 33.825

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 27

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: INVERTER-2 AC BUS

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-2 INVERTER-2 AC BUS 0.00 3.056 -2.734 0.9 4.100

INVERTER-2 AC BUS Total 0.00 7.269 -36.296 5.0 37.016

25kVA TRAFO HT SIDE LT PANEL-2 0.00 0.000 0.000 999.9 0.000

IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050

3125kW INVERTER-1 INVERTER-1 AC BUS 72.20 0.031 -1.521 48.6 1.521

IDT TR-1 LV-2 LT PANEL-2 0.00 4.213 -33.562 8.0 33.825

LT PANEL-2 INVERTER-2 AC BUS 0.00 4.213 -33.562 8.0 33.825

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 28

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: INVERTER-3 AC BUS

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-3 INVERTER-3 AC BUS 0.00 3.056 -2.734 0.9 4.100

INVERTER-3 AC BUS Total 0.00 7.242 -36.340 5.0 37.054

IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-4 INVERTER-4 AC BUS 72.27 0.030 -1.517 51.0 1.517

IDT TR-2 LV-1 LT PANEL -3 0.00 4.186 -33.606 8.0 33.866

LT PANEL -3 INVERTER-3 AC BUS 0.00 4.186 -33.606 8.0 33.866

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.079 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.920

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 29

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: INVERTER-4 AC BUS

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-4 INVERTER-4 AC BUS 0.00 3.056 -2.734 0.9 4.100

INVERTER-4 AC BUS Total 0.00 7.242 -36.340 5.0 37.054

Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000

IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-3 INVERTER-3 AC BUS 72.27 0.030 -1.517 51.0 1.517

IDT TR-2 LV-2 LT PANEL -4 0.00 4.186 -33.606 8.0 33.866

LT PANEL -4 INVERTER-4 AC BUS 0.00 4.186 -33.606 8.0 33.866

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.078 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.919

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 30

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: INVERTER-5 AC BUS

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-5 INVERTER-5 AC BUS 0.00 3.056 -2.734 0.9 4.100

INVERTER-5 AC BUS Total 0.00 7.246 -35.991 5.0 36.713

IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520

IDT TR-3 LV-1 LT PANEL -5 0.00 4.189 -33.258 7.9 33.520

LT PANEL -5 INVERTER-5 AC BUS 0.00 4.189 -33.258 7.9 33.520

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 36.713 47.827 30.651

0.02 36.713 41.960 20.317

0.03 36.713 39.105 13.467

0.04 36.713 37.783 8.926

0.05 36.713 37.187 5.916

0.06 36.713 36.922 3.922

0.07 36.713 36.805 2.599

0.08 36.713 36.754 1.723

0.09 36.713 36.731 1.142

0.10 36.713 36.721 0.757

0.15 36.713 36.713 0.097

0.20 36.713 36.713 0.012

0.25 36.713 36.713 0.002

0.30 36.713 36.713 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 31

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: LT PANEL -1

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-1 INVERTER-1 AC BUS 0.00 3.056 -2.734 0.9 4.100

LT PANEL -1 Total 0.00 7.269 -36.296 5.0 37.016

IDT TRANSFORMER-1 HT IDT TR-1 LV-1 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-2 IDT TR-1 LV-1 72.20 0.607 -5.014 8.3 5.050

3125kW INVERTER-2 INVERTER-2 AC BUS 72.20 0.031 -1.521 48.6 1.521

IDT TR-1 LV-1 LT PANEL -1 0.00 4.213 -33.562 8.0 33.825

INVERTER-1 AC BUS LT PANEL -1 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 32

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: LT PANEL-2

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.682 kA Method C
Steady State = 33.825 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

LT PANEL-2 Total 0.00 7.269 -36.296 5.0 37.016

25kVA TRAFO HT SIDE LT PANEL-2 0.00 0.000 0.000 999.9 0.000

3125kW INVERTER-2 INVERTER-2 AC BUS 0.00 3.056 -2.734 0.9 4.100

IDT TRANSFORMER-1 HT IDT TR-1 LV-2 82.31 3.606 -28.548 7.9 28.775

IDT TR-1 LV-1 IDT TR-1 LV-2 72.20 0.607 -5.014 8.3 5.050

3125kW INVERTER-1 INVERTER-1 AC BUS 72.20 0.031 -1.521 48.6 1.521

IDT TR-1 LV-2 LT PANEL-2 0.00 4.213 -33.562 8.0 33.825

INVERTER-2 AC BUS LT PANEL-2 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.016 47.963 30.499

0.02 37.016 42.146 20.152

0.03 37.016 39.338 13.315

0.04 37.016 38.047 8.797

0.05 37.016 37.470 5.813

0.06 37.016 37.215 3.841

0.07 37.016 37.103 2.538

0.08 37.016 37.054 1.677

0.09 37.016 37.033 1.108

0.10 37.016 37.024 0.732

0.15 37.016 37.016 0.092

0.20 37.016 37.016 0.012

0.25 37.016 37.016 0.001

0.30 37.016 37.016 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 33

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: LT PANEL -3

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-3 INVERTER-3 AC BUS 0.00 3.056 -2.734 0.9 4.100

LT PANEL -3 Total 0.00 7.242 -36.340 5.0 37.054

IDT TRANSFORMER-2 HT IDT TR-2 LV-1 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-2 IDT TR-2 LV-1 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-4 INVERTER-4 AC BUS 72.27 0.030 -1.517 51.0 1.517

IDT TR-2 LV-1 LT PANEL -3 0.00 4.186 -33.606 8.0 33.866

INVERTER-3 AC BUS LT PANEL -3 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.079 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.920

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 34

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: LT PANEL -4

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.868 kA Method C
Steady State = 33.866 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-4 INVERTER-4 AC BUS 0.00 3.056 -2.734 0.9 4.100

LT PANEL -4 Total 0.00 7.242 -36.340 5.0 37.054

Change Over Switch IDT TR-2 LV-2 0.00 0.000 0.000 999.9 0.000

IDT TRANSFORMER-2 HT IDT TR-2 LV-2 82.42 3.583 -28.587 8.0 28.811

IDT TR-2 LV-1 IDT TR-2 LV-2 72.27 0.602 -5.019 8.3 5.055

3125kW INVERTER-3 INVERTER-3 AC BUS 72.27 0.030 -1.517 51.0 1.517

IDT TR-2 LV-2 LT PANEL -4 0.00 4.186 -33.606 8.0 33.866

INVERTER-4 AC BUS LT PANEL -4 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 37.054 48.078 30.635

0.02 37.054 42.253 20.306

0.03 37.054 39.423 13.459

0.04 37.054 38.113 8.921

0.05 37.054 37.523 5.913

0.06 37.054 37.261 3.919

0.07 37.054 37.145 2.598

0.08 37.054 37.094 1.722

0.09 37.054 37.072 1.141

0.10 37.054 37.062 0.757

0.15 37.054 37.055 0.097

0.20 37.054 37.054 0.012

0.25 37.054 37.054 0.002

0.30 37.054 37.054 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 35

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: LT PANEL -5

Nominal kV = 0.660
Voltage c Factor = 1.05 (Maximum If)
Peak Value = 83.400 kA Method C
Steady State = 33.520 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

3125kW INVERTER-5 INVERTER-5 AC BUS 0.00 3.056 -2.734 0.9 4.100

LT PANEL -5 Total 0.00 7.246 -35.991 5.0 36.713

IDT TRANSFORMER-3 HT IDT TR-3 LV-1 82.19 4.189 -33.258 7.9 33.520

IDT TR-3 LV-1 LT PANEL -5 0.00 4.189 -33.258 7.9 33.520

INVERTER-5 AC BUS LT PANEL -5 0.00 3.056 -2.734 0.9 4.100

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 36.713 47.827 30.651

0.02 36.713 41.960 20.317

0.03 36.713 39.105 13.467

0.04 36.713 37.783 8.926

0.05 36.713 37.187 5.916

0.06 36.713 36.922 3.922

0.07 36.713 36.805 2.599

0.08 36.713 36.754 1.723

0.09 36.713 36.731 1.142

0.10 36.713 36.721 0.757

0.15 36.713 36.713 0.097

0.20 36.713 36.713 0.012

0.25 36.713 36.713 0.002

0.30 36.713 36.713 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 36

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase fault at bus: OD Metering


Switchyard
Nominal kV = 33.000
Voltage c Factor = 1.10 (Maximum If)
Peak Value = 6.593 kA Method C
Steady State = 3.178 kA rms

Contribution Voltage & Initial Symmetrical Current (rms)


From Bus To Bus %V kA kA X/R kA
ID ID From Bus Real Imaginary Ratio Magnitude

OD Metering Switchyard Total 0.00 0.647 -3.112 4.8 3.178

33kV Outdoor HT Panel OD Metering Switchyard 0.06 0.000 -0.273 999.9 0.273

110kV/33kV Substation End OD Metering Switchyard 22.31 0.647 -2.838 4.4 2.911

Breaking and DC Fault Current (kA)


Based on Total Bus Fault Current

TD (S) Ib sym Ib asym Idc

0.01 3.178 3.751 1.992

0.02 3.178 3.324 0.973

0.03 3.178 3.214 0.475

0.04 3.178 3.187 0.232

0.05 3.178 3.180 0.113

0.06 3.178 3.179 0.055

0.07 3.178 3.178 0.027

0.08 3.178 3.178 0.013

0.09 3.178 3.178 0.006

0.10 3.178 3.178 0.003

0.15 3.178 3.178 0.000

0.20 3.178 3.178 0.000

0.25 3.178 3.178 0.000

0.30 3.178 3.178 0.000


Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 37

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Short-Circuit Summary Report

3-Phase Fault Currents

Device Capacity (kA)


Bus Device Making Short-Circuit Current (kA)
ID kV ID Type Peak Ib sym Ib asym Idc I"k ip Ib sym Ib asym Idc Ik
25kVA TRAFO HT SIDE 0.660 25kVA TRAFO HT SIDE Bus 11.318 16.351 11.318

25kVA TRAFO LV 0.415 25kVA TRAFO LV Bus 0.912 2.135 0.912

33kV ICOG Panel 33.000 33kV ICOG Panel Bus 3.145 6.481 3.145

33kV Outdoor HT Panel 33.000 33kV Outdoor HT Panel Bus 3.164 6.542 3.164

50 kVA AUX TRAFO LV 0.415 50 kVA AUX TRAFO LV Bus 1.711 3.433 1.711

50 kVA TRAFO HT 0.660 50 kVA TRAFO HT Bus 5.321 7.675 5.321

110kV/33kV Substation 33.000 110kV/33kV Substation Open Air 3.771 8.996 3.771
End End
Auxiliary MDB 25kVA 0.415 Auxiliary MDB 25kVA Bus 0.870 1.746 0.870

Auxiliary MDB 50kVA 0.415 Auxiliary MDB 50kVA Bus 1.495 2.508 1.495

Change Over Switch 0.660 Change Over Switch Bus 10.136 14.632 10.136

IDT TR-1 LV-1 0.660 IDT TR-1 LV-1 Bus 37.016 83.682 33.825

0.660 IDT TR-3 LV -1 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
IDT TR-1 LV-2 0.660 IDT TR-1 LV-2 Bus 37.016 83.682 33.825

0.660 IDT TR-3 LV -2 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
IDT TR-2 LV-1 0.660 IDT TR-2 LV-1 Bus 37.054 83.868 33.866

0.660 IDT TR-2 LV-1 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
IDT TR-2 LV-2 0.660 IDT TR-2 LV-2 Bus 37.054 83.868 33.866

0.660 IDT TR-2 LV-2 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
IDT TR-3 LV-1 0.660 IDT TR-3 LV-1 Bus 36.713 83.400 33.520

0.660 IDT TR-3 LV BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243

IDT TRANSFORMER-1 33.000 IDT TRANSFORMER-1 Bus 3.143 6.472 3.143


HT HT
IDT TRANSFORMER-2 33.000 IDT TRANSFORMER-2 Cable Bus 3.161 6.532 3.161
HT HT
IDT TRANSFORMER-3 33.000 IDT TRANSFORMER-3 Bus 3.161 6.532 3.161
HT HT
INVERTER-1 AC BUS 0.660 INVERTER-1 AC BUS Bus 37.016 83.682 33.825

0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160

INVERTER-2 AC BUS 0.660 INVERTER-2 AC BUS Bus 37.016 83.682 33.825

0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
2
INVERTER-3 AC BUS 0.660 INVERTER-3 AC BUS Bus 37.054 83.868 33.866

0.660 LV PANEL-3 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219

INVERTER-4 AC BUS 0.660 INVERTER-4 AC BUS Bus 37.054 83.868 33.866

0.660 LV PANEL-4 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 38

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

3-Phase Fault Currents

Device Capacity (kA)


Bus Device Making Short-Circuit Current (kA)
ID kV ID Type Peak Ib sym Ib asym Idc I"k ip Ib sym Ib asym Idc Ik
INVERTER-5 AC BUS 0.660 INVERTER-5 AC BUS Bus 36.713 83.400 33.520

0.660 LV PANEL-5 BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243

LT PANEL -1 0.660 LT PANEL -1 Bus 37.016 83.682 33.825

0.660 IDT TR-3 LV -1 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160

LT PANEL-2 0.660 LT PANEL-2 Bus 37.016 83.682 33.825

0.660 IDT TR-3 LV -2 BUS Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
DUCT
0.660 LV PANEL-1 BUS DUCT Busduct 50.000 37.016 83.682 * 37.016 59.169 46.160
2
LT PANEL -3 0.660 LT PANEL -3 Bus 37.054 83.868 33.866

0.660 LV PANEL-3 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219

0.660 IDT TR-2 LV-1 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
LT PANEL -4 0.660 LT PANEL -4 Bus 37.054 83.868 33.866

0.660 IDT TR-2 LV-2 BUS Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219
DUCT
0.660 LV PANEL-4 BUS DUCT Busduct 50.000 37.054 83.868 * 37.054 59.238 46.219

LT PANEL -5 0.660 LT PANEL -5 Bus 36.713 83.400 33.520

0.660 IDT TR-3 LV BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243

0.660 LV PANEL-5 BUS DUCT Busduct 50.000 36.713 83.400 * 36.713 59.045 46.243

OD Metering Switchyard 33.000 OD Metering Switchyard Bus 3.178 6.593 3.178

ip is calculated using method C


Ib does not include decay of non-terminal faulted induction motors
Ik is the maximum steady state fault current
Idc is based on X/R from Method C and Ib as specified above

LV CB duty determined based on service rating.


Total through current is used for device duty.
* Indicates a device with calculated duty exceeding the device capability.
# Indicates a device with calculated duty exceeding the device marginal limit . ( 95 % times device capability)
Project: TN SUNRISE ONE (21.75MWp DC) ETAP Page: 39

Location: TAMIL NADU 19.0.1C Date: 03-04-2024

Contract: SN:

Engineer: DARSHIT VYAS Revision: Base


Study Case: SC
Filename: 33kV Solar Plant Config.: Normal

Short-Circuit Summary Report

Device Capacity 3-Phase Short-Circuit Duty Results


Rated Thermal Thermal
Bus ID Device ID Ithr (kA) Tkr (sec.) Energy (MJ) Ith (kA) Tkr (sec.) Energy (MJ)