To,
Dear Sir,
We, MYK Arment Private Limited an ISO 9001:2008 company established since
last 12 years in India and Asia Pacific. We are a member of Indian Green Building
Council (IGBC) and have been working with German Technology.
MYK Arment, is one of the fastest growing construction chemicals company and
to back this up we have 3 factories in India, with a state of art R&D centre and
branches and qualified/ trained team members across India. With a Vision to “Set
Standards of Excellence & Trust in the Global Construction Chemical Industry “,
Our commitment is to innovate, lead and deliver cutting edge construction
chemicals which has brought in razor-sharp focus to action our vision, achieve
our goals and become a dominant player in the Indian, Asian, Middle Eastern &
African markets.
Please feel free to contact us at the details mentioned below, visit our website,
email us or you can call on our numbers mentioned below, it will be our privilege
Page 2
to service your requirement.
Yours Sincerely,
PART I – GENERAL
1.01 SUMMARY
FloArm SL Conductive/Dissipative : 2mm thick Epoxy resin based ESD flooring. Systems have
been designed for use in areas where a static Conductive or a static Dissipative floor is required as
a measure to control static electricity.
Page 3
PART II – PRODUCT / SYSTEM INFORMATION
Page 4
ASTM F-2170 : Standard Test Method for
Determining Relative Humidity in Concrete
Floor Slabs Using In Situ Probes: This test
measures the relative humidity in the slab
below the surface. If taken over a period of
time, it will show the rate of drying in the slab.
The maximum relative humidity should be
below 75%.
5. It is recommended to remove dust, dirt and loose concrete, mortar to ensure perfect bonding of epoxy
flooring system. It is also recommended to carry out mechanical grinding on the floor for proper adhesion
of successive system.
6. The concrete surface should be abraded or impacted by mechanical means to remove the uppermost cement
matrix. This can be achieved using appropriate proprietary equipment for grinding or shot blasting
preferably with integral vacuum containment. Percussive scrabbling is unsuitable. Prior to applying the
flooring a close visual examination should be made to verify cleanliness, soundness of the surface.
Page 5
7. It is also recommended to open construction joints, cracks (if any) on floor in V-groove type and fill up the
same using epoxy putty to avoid cracks in epoxy flooring system.
Page 6
1. Application of FloArm Primer EP – FloArm Primer EP should be applied either with a brush or roller in the
form of continuous pore free coating to ensure full coverage of the substrate. The rate of consumption would be
– 0.3 to 0.4 kg/sqm. If the surface is quite porous, one can go for application of FloArm Primer 1290.
1. When primer is dry bond the copper tape \to the primed concrete and connect end of the tape to suitable earth
point. This will include existing earthing points or copper strips that are themselves connected to the earthing
points.
2. Overcoat to top of tape with FloArm Conductive/Dissipative undercoat during the undercoat installation
process.
Page 7
Step 4: Application of FloArm SL Conductive/Dissipative
1. Under Coat: The mixed undercoat shall be applied with a roller or brush on the primer at a material
consumption rate of 6m²/kg. The undercoat provides a Conductive system passage to earth so correct
application and strict adherence to coverage rates are critical to the final electrical properties of the completed
floor. Thorough covering of earthing connections is essential. The Resistivity of the undercoat needs to be
measured before applying the top coat (after overnight Air Dry). The surface resistance (FloArm SL Conductive
undercoat) should be approx. 3x103 9 x103 Ohm & that for dissipative should be: 10 X 103 to 500 X 103 Ohms.
2. Top coat: The material once mixed should be used within its specified pot life. FloArm SL
Conductive/Dissipative is designed to flow out readily to provide a smooth substantially leveled surface. It is
applied by spreading evenly over the surface, using a serrated trowel, pin rake or squeegee. This should be
followed by rolling with a spiked roller to release any entrapped air and assist in smoothing out.
Page 8
PART IV- QUALITY ASSURANCE