:: In the Field

TRAINOR GLASS INSTALLERS CLOSE-IN EFFICIENTLY AND SAFELY WITH UNITIZED SYSTEMS

1. Preglazed curtain wall panels are shipped to the 2. A glazier, properly tied off to the structure,
jobsite in crates and hoisted to the floors using carefully handles the panel to guide it into place.
the tower crane. The panels are removed from the
crates and hoisted outside of the building using
our monorail system and remote controlled hoist.

4. Glaziers slide the panel into position where


it engages the adjoining vertical mullion. The
panel is then lowered into position locking it onto
3. The panel is turned to the proper position. a pre-installed anchor. The glaziers make final
adjustments with a set screw and disengage the
spreader bar, completing the installation.

Finished Project
Hunt Corporate Headquarters
Dallas, TX

5. The complete elevation: 2,800 unitized panels.