Saudi Aramco Pre-Commissioning Form: Surge Arrestors
Saudi Aramco Pre-Commissioning Form: Surge Arrestors
Yes No
1. Inspect for physical damage, such as damaged insulation or mounting brackets.
2. Verify location and name plate rating with plans and specifications.
3. Inspect ground and discharge counter connections for integrity if supplied.
4. Clean porcelain or silicon rubber insulation with distilled water and dry before
performing electrical tests.
5. Inspect for proper mounting and adequate clearance.
ELECTRICAL TESTS
Yes No
1. Perform an insulation power-factor test.
2. Perform continuity test of ground connections from arrestor
to ground grid system.
Yes No
1. Power factor tests should show similar dielectric loss between similar arresters.
2. Ground grid connections should not exceed 0.5 ohms.