SAUDI ARAMCO PRE-COMMISSIONING FORM
METAL ENCLOSED BUS
Equipment Type: SWITCHGEAR User Reference:
Equipment Tag No: H01-SG--CAB-201 Equipment Description: MV SWITCHGEAR
BI/JO No: 10-09442 Plant No. / Location: HAWAIYAH WIP-1
Ref. Drawings & Documents:
Manufacturer:
Model No: Serial No:
Test Completion Date:

FIELD INSTALLATION CHECK LIST

VISUAL AND MECHANICAL

Yes No
1. Inspect the entire assembly, including auxiliary equipment, for any apparent damage or
missing parts.
2. Remove shipping blocks, braces and parts.

3. Inspect for proper bracing, suspension alignment and enclosure ground.

4. Torque the connections as per manufacturer recommendations or per values in P-000.


5. The bus shall be inspected for physical damage and proper connection in accordance
with the single line diagram.
6. Check the location and type of drain plug.

7. Check current rating (cross section) of flexible connectors used at transformer and or
switchgear terminations of metal-enclosed bus.

ELECTRICAL TESTS

Yes No
1. Measure insulation resistance of each bus run phase to phase and phase to ground for
one (1) minute. Test voltage and minimum acceptable values in accordance with P-000
2. Perform A. C. high potential tests on each bus run phase to phase and phase to ground.
Potential application shall be in accordance with manufacturer's instructions or as
specified in P-000.
3. Perform phase rotation and phase cross voltage tests on each bus tie section energized
by separate sources. Performed tests when bus sections are powered by permanent
source.
4. Measure bus joint resistance.

5. Connect space heaters and check operability (when applicable).

6. Verify operation of heater ammeter and control power switch.

Witness POD Inspection Operation/Maintenance Contractor


Signature & Date
Copyright©Saudi Aramco 2009. All rights reserved.
Form No. P- 063 Issue Date: March 2006 Sheet 2 of 2
SAUDI ARAMCO PRE-COMMISSIONING FORM
METAL ENCLOSED BUS
Equipment Type: SWITCHGEAR User Reference:
Equipment Tag No: H01-SG--CAB-201 Equipment Description: MV SWITCHGEAR
BI/JO No: 10-09442 Plant No. / Location: HAWAIYAH WIP-1
Ref. Drawings & Documents:
Manufacturer:
Model No: Serial No:
Test Completion Date:

Field Test Record

Bus phase Megger Test Results High Potential Test Results


Phase A to Ground (BUS 1)

Phase B to Ground (BUS 1)

Phase C to Ground (BUS 1)

Phase A to Phase B (BUS 2)

Phase B to Phase C (BUS 2)

Phase C to Phase A (BUS 2)

Number of bus joints____________________________________

Joint no. Resistance Joint no. Resistance Joint no. Resistance

Phase Rotation
Measured Voltage

Voltage Phase A BUS 1 to Phase A BUS 2 _________________


Voltage Phase B BUS 1 to Phase B BUS 2 _________________
Voltage Phase C BUS 1 to Phase C Bus 2 _________________