Professional Documents
Culture Documents
Saudi Aramco Pre-Commissioning Form: Metal Enclosed Bus
Saudi Aramco Pre-Commissioning Form: Metal Enclosed Bus
Yes No
1. Inspect the entire assembly, including auxiliary equipment, for any apparent damage or
missing parts.
2. Remove shipping blocks, braces and parts.
7. Check current rating (cross section) of flexible connectors used at transformer and or
switchgear terminations of metal-enclosed bus.
ELECTRICAL TESTS
Yes No
1. Measure insulation resistance of each bus run phase to phase and phase to ground for
one (1) minute. Test voltage and minimum acceptable values in accordance with P-000
2. Perform A. C. high potential tests on each bus run phase to phase and phase to ground.
Potential application shall be in accordance with manufacturer's instructions or as
specified in P-000.
3. Perform phase rotation and phase cross voltage tests on each bus tie section energized
by separate sources. Performed tests when bus sections are powered by permanent
source.
4. Measure bus joint resistance.
Phase Rotation
Measured Voltage