Solution LCC
Solution LCC
O&M cost is (17 W * 2000 hours/year) /1000 * $0.25/kWh = $8.5 per year
PV of the capital cost of CFL is $7.5/(1+0.06)0 = $7.5
PV of the O&M cost of CFL is $8.5/(1+0.06)1 = $8.02
PV of the O&M cost of CFL is $8.5/(1+0.06)2 = $7.56
PV of the O&M cost of CFL is $8.5/(1+0.06)3 = $7.14
PV of the O&M cost of CFL is $8.5/(1+0.06)4 = $6.73
PV of the O&M cost of CFL is $8.5/(1+0.06)5 = $6.35
Total PV = 43.31