DAILY PLAN

Shift 2 = 13 November 2023


Shift 1 = 14 November 2023

TARGET PRODUKSI
November 2023
OB : 1.400.000 BCM
COAL : 305.000 MT
PLAN TARGET OB/DAY : 46.667 BCM
Fleet OB dan Coal Getting
No. : HRS-FRM-ENG-012 No. : HRS-FRM-ENG-012

DAILY WORK ORDER Revisi


Tanggal Berlaku
:1
: 21/09/2019 DAILY WORK ORDER Revisi
Tanggal Berlaku
:2
:21/09/2019
Halaman : 1 dari 3 Halaman : 2 dari 3
DAY/DATE/SHIFT 13 November 2023 Shift 2 & 14 November 2023 Shift 1 LAPORAN MATERIAL IN-PIT HARAP DIKONTINYUKAN !!! DAY/DATE/SHIFT 13 November 2023 Shift 2 & 14 November 2023 Shift 1

Inv. Seam I Utara


= Inventory Blasting

= Plan Blasting (Selasa, 14 November 2023)


HEX 1201
Expose Seam E Utara Opsi 2 Peralihan HEX 1202 EX 454 RML
COAL GETTING Inv. Seam G Utara
HEX 213 General Cleaning
Expose Seam F Utara Expose Seam O Upper Utara 1 Fleet Coal Getting
Opsi 1 HEX 447 Coal Getting
= Material Free Digging Seam O Lower Utara
= Rencana Peralihan Akses OB/Coal
Opsi 1 Peralihan EX 507 RML
Loading Material General Inv. Seam C1 Utara
= Perbaikan Jalur Air (Paritan) Cleaning Batubara
HEX 448 General Cleaning
= Material Ripping

HEX 1215
Stripping Floor Seam P Utara

457
EX 507 RML
Expose Seam C1 Utara
1215
1 Fleet Coal Getting
Seam P Utara
1203 Opsi 1 Peralihan HEX 1215
Stripping Floor Seam P Utara 447
507 (Layer Kedua)

1201

Opsi 1 Peralihan HEX 1202


Stripping Seam E Utara
1 Fleet Coal Getting
1202 Seam L Utara
Opsi 1 Peralihan EX 454 RML
Stripping Floor Seam L Utara

Inv. Seam G Tengah

HEX 1202
Stripping Seam E Utara

HEX 1203
Stripping Floor Seam I Utara

1204
Opsi Darurat Peralihan
HEX 1203
Expose Seam I Tengah

Inv. Seam P Utara


HEX 1204
Expose Seam P Tengah

Opsi 2 Peralihan EX 501 RML


Expose Seam I Tengah

Opsi 1 Peralihan HEX 1203


Expose Seam G Tengah Opsi 1 Peralihan HEX 1204/442
(Layer Kedua) Opsi 1 Peralihan EX 501 RML EX 501 RML Expose Seam P Tengah
Stripping Floor Seam I Selatan Stripping Floor L Selatan (Loading Bekas Pad HEX 1204)
OB REMOVAL Inv. Seam O Upper Tengah

Tinggi Front Distance Inv. Blast Coal w.b.


NO FLEET HAULER LOKASI MATERIAL AL RL Dumping Point Activity Plan MF
Loading (m) (m) (BCM) Expose

Inv. Seam G Selatan


1 1201 5 Seam E Utara Blasting -1 -10 3,0 IPD Mahoni RL+40 1783 Expose Seam E Utara 12139 186 1,02 HEX 229 General Cleaning Inv. Seam I Tengah
Opsi 1 HEX 443 Coal Getting
Ramp -5
2 1202 4 Seam E Utara Blasting -5 3,0 IPD Mahoni RL+40 1706 Stripping Seam E Utara 18634 - 0,92
ke -10

Ramp -25
3 1203 5 Seam I Utara Blasting -21
ke-40
3,0 IPD Mahoni RL+40 2175 Stripping Floor Seam I Utara 13422 - 0,95 NO FLEET HAULER LOKASI AL RL Distance (m) ACTIVITY PLAN

4 1204 6 Seam P Tengah Blasting -52 -53 3,0 IPD Mahoni RL+40 2703 Expose Seam P Tengah 6345 609 0,97 Seam P Utara Ramp -15
1 HEX 457 10 -17.4 7238 Coal Getting Seam P Utara
Blok 26 ke -20
Ramp -25
5 1215 6 Seam P Utara Blasting -21 3,0 IPD Mahoni RL+40 2622 Expose Seam P Utara 9219 609 0,97
ke -40 Seam OL Utara Ramp -5
2 HEX 443 10 -4.1 7353 Coal Getting Seam O Lower Utara
454 7 Seam OU Utara Free Digging -1 -5 1,5 IPD Mahoni RL +45 2707 Expose Seam O Upper Utara - 805 0,94 Blok 27 ke -10
Seam L Utara
7 501 7 Seam L Selatan Free Digging -114 -114 1,5 IPD Mahoni RL +45 2642 Stripping Floor L Selatan - - 0,92 HEX 447 9 -39.4 -40 6946 Coal Getting Seam L Utara
Blok 24
Ramp 20
7 507 6 Seam C1 Utara Ripping 20
ke 10
1,5 IPD Mahoni RL +45 1970 Expose Seam C1 Utara - 1526 0,99 NOTES : Total Inv. Batubara 90.250 MT
3.734 Maksimalkan coal getting sampai ke floor (10 cm batubara tersisa di floor) dan perhatikan Target CG November 2023 305.000 MT Ach. MTD
-
NOTE : sisa batubara bekas dudukan PC diloading habis dan jangan sampai ketinggalan! Remain CG 153.705 MT
Target JSO Monthly BRE-HRS (November 2023)
- Dibuat Oleh : Mengetahui : Diterima Oleh : Perhatikan masalah muatan DT batubara, mohon agar tetap terjaga full dan peres dengan vessel MTD CG 151.295 MT 50%
= 1.400.000 BCM -
Target Coal Getting (November 2023) agar tidak banyak tumpahan di jalan hauling! Remain Target/Day CG 8.539 MT
-
= 305.000 MT Dibuat Oleh : Mengetahui : Diterima Oleh :
Total Unit Hauler (HD)
-
Running = 24 ; Standby = 0
Total Unit Hauler (TRX)
-
Running = 5 ; Standby = 0
Mohon diperhatikan pembentukan bench di High Wall Selatan
-
untuk batas LOM sesuai acuan di lapangan!
- Mohon untuk tetap dilaporkan ritase-ritase HD yang inpit! Mine Plan Sect. Head Mine Plan Sect. Head Produksi Mine Plan Sect. Head Mine Plan Sect. Head Produksi
13 November 2023
PIT CENDANA
450
1201 AL = -1
RL = -5
AL = -1 1215
RL = -10
AL = -15
RL = -20
507

AL = 20
RL = 20 ke 10
450
(P1) 1202 1203
AL = -21
1202 RL =-25 ke -40 1204
AL = -5 AL = -52
RL = -5 ke -10 RL =-55

(P1) (P1)
1203 1204

CREST -110

(P1)
1203

501

AL = -114
RL = -114
Persiapan
Akses Jalan
HEX 1203

Weekly Plan Opsi Peralihan


Daily Plan Plan Drillpad
Rencana Jalan

12 November 2023
PLAN COAL GETTING WEEK 46 NOVEMBER 2023
PIT CENDANA

Deskripsi Monday Tuesday Wednesday Thursday Friday Saturday Sunday


Total
Activity Unit 13-Nov-23 14-Nov-23 15-Nov-23 16-Nov-23 17-Nov-23 18-Nov-23 19-Nov-23
OB Removal bcm 54.823 52.993 54.823 51.969 47.678 54.823 54.114 371.222
Coal Getting ton 11.021 11.072 11.025 11.053 11.095 11.022 11.047 77.335
Seam C ton - 1.526 - - 1.500 - 1.500 4.526
Seam D ton -
Seam E ton - - - - - 875 - 875
Seam F ton - - - 784 - - - 784
Seam G ton 7.021 7.500 6.500 7.143 6.500 7.000 6.500 48.164
Seam H ton - - - - 3.095 - - 3.095
Seam I ton - - 3.021 - - 3.147 - 6.168
Seam K ton - - - 3.126 - - - 3.126
Seam OU ton - 2.046 - - - - - 2.046
Seam OL ton 1.500 - - - - - 3.047 4.547
Seam P ton 2.500 - 1.504 - - - - 4.004
SR bcm/ton 4,97 4,79 4,97 4,70 4,30 4,97 4,90 4,80
OB Distance m 2.350 2.364 2.379 2.365 2.384 2.382 2.382 2.372
Coal Distance m 8.295 8.295 8.295 8.295 8.295 8.295 8.295 8.295
DUMPING POINT IPD MAHONI

13 November 2023
GENERAL ACTIVITY LOWWALL

13 November 2023
GENERAL ACTIVITY PIT

13 November 2023
GENERAL ACTIVITY PIT

13 November 2023
GENERAL ACTIVITY PIT

13 November 2023