Shoring in construction refers to the process of supporting a structure, trench, or other excavation to prevent
collapse. The shoring system helps maintain stability and safety during construction.
● Screw Jacks
Screw Jack Shoring used as a starting base for used to support vertical ● Steel Plates or Waler Adjustability- The system
scaffolding. It has an loads and fix unstable soils Plates offers adjustable height,
adjustable height to allow for or slopes. ● Braces making it suitable for a
● Steel Beams or
compensation on uneven Vertical Supports wide range of construction
grades so that a level ● Hand Crank or excavation scenarios.
scaffold is always attainable.
Stability- It provides
robust support, ensuring
safety for workers and
preventing soil movement
or instability.
Wood Shoring
1. Assess the Situation: Determine where wood shoring is needed and the specific requirements based on the
weight it needs to support and the conditions of the structure.
2. Gather Materials: Gather the necessary materials including lumber, shoring jacks, nails, hammer, saw, safety
equipment (gloves, goggles, hard hat), and any other tools required.
3. Prepare the Area: Clear the area where the shoring will be erected. Ensure there are no obstacles that could
interfere with the construction process.
4. Cut Lumber: Measure and cut the lumber to the required lengths based on the height and dimensions needed for
shoring.
5. Position Vertical Supports: Place the vertical supports (posts) in position at the appropriate intervals based on
engineering specifications or standards.
6. Secure Vertical Supports: Use nails or other appropriate fasteners to secure the vertical supports in place. Make
sure they are plumb (perfectly vertical) and aligned correctly.
7. Install Horizontal Members: Install horizontal beams or planks between the vertical supports to provide additional
support and stability.
8. Check Stability: Once the basic framework is in place, double-check the stability and alignment of the shoring
system. Make any necessary adjustments to ensure it is secure and properly supporting the load.
9. Add Additional Support: Depending on the load and requirements, additional bracing or supports may be
necessary to strengthen the shoring system. Install these as needed.
10. Dismantle Safely: When the shoring is no longer needed, dismantle it carefully and safely, ensuring that no part of
the structure collapses unexpectedly. Remove all materials and clean up the area.
11. Dispose of Materials: Dispose of any unused materials properly and recycle if possible.
Hydraulic Shoring
1. Assess the Site: Evaluate the excavation or construction site to determine where hydraulic shoring is needed.
2. Select Equipment: Choose the appropriate hydraulic shoring equipment based on the dimensions of the trench or
excavation, soil type, and required load-bearing capacity.
3. Prepare the Trench: Clear the trench of any debris and ensure it is dug to the required dimensions and depth
4. Position Hydraulic Shoring Equipment: Place the hydraulic cylinders or shores vertically along the length of the
trench at regular intervals.
5. Install Cross Braces and Spreaders: Place cross braces horizontally between the hydraulic cylinders to provide
lateral support and prevent the walls of the trench from collapsing inward.
6. Connect Hydraulic System: Connect the hydraulic cylinders to a hydraulic pump or power source using hydraulic
hoses or lines.
7. Inspect Regularly: Periodically inspect the hydraulic shoring system for signs of damage, leaks, or instability.
8. Clean Up: Remove all hydraulic shoring equipment from the site and dispose of any debris or materials properly.
The requirements provided by COSH (Construction Occupational Safety and Health) are essential for ensuring a
safe work environment when it comes to shoring safety regulations and concerns. Here are some important safety
guidelines and things to keep in mind when shoring
1. Training and Certification: Proper training and certification in emergency protocols, equipment operation,
and shoring safety procedures should be given to all personnel participating in shoring activities.
2. Personal Protective Equipment (PPE): To reduce the danger of harm, workers must wear the proper PPE,
such as hard hats, high-visibility vests, gloves, steel-toed boots, and eye protection.
3. Safe Work Practices: To avoid falls or accidents, observe safe work practices such as keeping a safe
distance from excavation edges, exercising caution when near heavy equipment, and securing loose
objects.
4. Communication: To coordinate shoring actions and make sure that everyone is aware of potential hazards
and safety procedures, maintain clear communication between workers, supervisors, and equipment
operators.
5. Fall Protection: When working at heights, provide personnel with fall protection equipment, such as
guardrails, safety nets, or personal fall arrest systems, as needed.
1. Site Conditions - Unusual soil characteristics can provide serious difficulties for shoring operations, such as weak
or changeable soil types, groundwater levels, and underground utilities.
2. Access and Egress- Limited access to the excavation site or inadequate space for equipment and materials can
hinder shoring operations.
3. Tight Deadlines - Construction projects often operate on tight schedules, and delays in shoring operations can
have cascading effects on project timelines.
4. Cost Constraints - Balancing the need for effective shoring with budgetary constraints requires careful cost
analysis and resource management to optimize project outcomes.
5. Regulatory Compliance - Adhering to local building codes, regulations, and safety standards governing shoring
operations is essential but can be challenging, especially when regulations are complex or vary between
jurisdictions.
6. Safety Risks - implementing comprehensive safety measures, providing adequate training, and enforcing strict
safety protocols are essential for mitigating these risks.
7. Environmental Considerations - Implementing erosion control measures, minimizing site disturbance, and
adhering to environmental regulations are critical for minimizing environmental impacts.
8. Maintaining Stability - Ensuring the stability and integrity of the shoring system throughout the duration of the
project, especially in dynamic soil conditions or adverse weather conditions, requires continuous monitoring,
inspection, and maintenance.