Professional Documents
Culture Documents
Estimation and Costing Dushyant Sir
Estimation and Costing Dushyant Sir
Estimation and Costing Dushyant Sir
CH. 1 - ESTIMATION
ESTIMATION
Estimation is a technique of calculating the various quantities and
expenditure to be incurred on a work.
1. Drawings
1. Preliminary estimation
2. Detailed estimation
PRELIMINARY ESTIMATION
This is also known as Approximate estimation or Abstract estimation or
Rough estimation.
It’s the estimate that is prepared in initial stage to know the approximate cost
i. Plinth Area
v. Circulation Area
i. Plinth Area :-
• It is The built up covered area of a building measured at floor level of any
story.
In Plinth area following shall be included [As per IS 3861-
2002] :-
3. Area of vertical
sun breaker.
4. Open platform
5. Terrace
6. Open or service stairs case
7. machine room, towers above terrace
level.
9. Courtyard Area
8. Area of mumty
ii. Carpet Area :-
The covered area of the usable spaces of room at any floor is
termed as carpet area.
It is measured b/w walls to walls within the building.
It is the sum of actual area which can be carpet.
Followings are not included in carpet areas (lets termed as X) :-
Wall area, veranda, corridors, passages, entrance hall, porch,
stair case, stair cover, lift shaft, bathroom, machine room, kitchen,
and pantry, store canteen, Ac duct, shaft for sanitary work.
It is the plinth area excluding area of walls or the total area of
floor in between walls and consists of floor of all rooms verandah,
passages, corridor etc.
Set back is the minimum open space required around any building.
This distance is provided to keep the construction away from roads, waters
bodies, and other buildings.
Its used for natural vegetation and to provide service line and rain water
disposal.
This value is provided as per city law & and its different for different cities.
v. Circulation area :-
Area that is helpful in movement of people through the building,
around the building or b/w the building is termed as circulation area.
Example: Verandah, Lobbies, corridors, stairs, lift, landing etc.
(1) Vertical circulation area (stair case, lift) = [3% of plinth area]
• More accurate then plinth area method or can say that This
method is most accurate in approximate estimation method
3. Unit rate method :-
calculated.
2. Supplementary estimate
supplementary estimate.
4. Annual repair and maintenance estimate :-
repair etc.
Sequence of preparing an estimate :-
Approximate estimation
Detailed estimation
Supplementary estimate
Revised estimate
Administrative approval
For any project to be executed by department, approval from
competent authority in required with respect to the cost of work on
the basis of approximate estimate and it is termed as administrative
approval.
works, rate and cost of the work by the competent authority of the
Work Cost
Petty work Less then 50,000
Minor work 50,000 – 2,00,000
Major work More then 2,00,000
LUMPSUM COST :-
• While preparing an estimate it is not possible to find the details of Petty
items hence their lumpsum value in considered.
• Petty items = These are minor or insignificant works in civil engineering.
• It includes –
1) Contingency
2) Work charge establishment
3) Tools and plants
4) Departmental cost
5) Sanitary and waters supply
6) Electrification
1). Contingency :-
Also known as emergency expenses
During the execution of the project certain services are required, expense,
It is the cost of engineer for certain work like designing, planning,
supervision etc.
6). Electrification :-
Its value is taken as 8 % of the project cost.
CH. 2 - SPECIFICATIONS
SPECIFICATIONS
➢It is used to provide the description of the work required to
prepare the estimates.
➢Specifications are of following two types-
1. General specifications
2. Detailed specifications
General specifications Detailed specifications
1 Earthwork
Per
1. Earthwork in excavation CUM
CUM
2. Earthwork in filling in foundation Per
CUM
trenches CUM
Per
3. Earth work in filling in plinth CUM
CUM
S No Particulars of item Units of Units of
measurement payment
2 Concrete
1. Lime concrete in foundation CUM Per CUM
4 Brick work
1. Brickwork in foundation CUM Per CUM
5 Stone work
Per
1. Stone masonry CUM
CUM
S Particulars of item Units of Units of
No measurement payment
6 Wood work
1. Doors and windows frames or chaukhats, Per
CUM
rafters, beams CUM
7 Steel work
1. Steel reinforcement bars etc. in RCC and
Quintal Per Quintal
reinforced brick work
8 Roofing
Per
1. RCC and RB slab roof (excluding steel) CUM
CUM
2. Lime concrete roof over and inclusive of
Per
tiles or brick or stone slab etc. (thickness SQM
SQM
specified)
Per
3. Centering and shuttering formwork SQM
SQM
Per
4. AC sheet roofing SQM
SQM
S No Particulars of item Units of Units of
measurement payment
10 Flooring
1. 25mm cement concrete over 75mm lime Per
SQM
concrete floor (including lime concrete) SQM
Per
2. 25mm or 40mm cement concrete floor SQM
SQM
Per
12 Steel wooden truss Number
Number
Per
13 Glass panels (supply) SQM
SQM
Per
14 Fixing of glass panels or cleaning Number
Number
Chujja, sunshade Thin partition wall
Arches
Reinforced brickwork
Doors and windows frames or chaukhats Rafters
Plastering Pointing
Steel wooden truss Glass panels
Major item of work
1. EARTHWORK :-
➢Measurement is done in - m3
➢Example - excavation, cutting, filling, banking etc.
But –
➢if trench width >1.5m and depth < 30cm measurement in (m²)
Lift :-
It is the Average height from source
of soil to point of deposition.
What is a metalled road?
➢It not provided for strength as it does not give any strength to brick
masonry.
➢But for -
i. Half brick work,
ii. partition wall,
iii. brick soiling,
iv. honey comb work, etc
whose thickness is ≤ 10cm the measurement should be done
in SQM (m²).
6. Wood work :-
➢Its Measurement is done in CUM (m³) For member Thickness > 10cm
Like- window frame, door frame, Rafter beam etc.
Also –
➢Door and window fittings are done in NUMBER
Like – Bolt, Hinges, Handles etc.
7. Stone work :-
➢But if the thickness of the floor is less then or equal to 7.5 cm then it
should be measured in SQM.
measured in SQM.
➢If the Area of opening less then 0.5 m² then no deduction should be made.
For members like - Jamb, soffit and sill.
➢If area of opening is more then 3m² then Deduction should be made on
both sides.
2. Masonry work :-
➢No deduction in made for opening up to 0.1m²
➢No deduction for end of beam, soffit, rafter and purlin up to – 0.05 m²
➢No deduction for bed plate, wall plate, bearing of chajja up to 10 cm.
3. White-washing, colouring, distemper :-
➢During white washing, colouring, distemper on AC and GI sheet area of
washing, colouring and distemper is increased.
Member Area increased Area coefficient (for
one side only)
Corrugated GI sheet 14 % 1.14
Corrugated AC sheet 20 % 1.20
Semi-Corrugated AC 10 % 1.10
sheet
NOTE if these works are carried out on both the side the area
coefficient in doubled.
4. Steel work :-
Bar Bending schedule (BBS) :-
➢It’s a comprehensive list that describe the certain properties of each
reinforcement bar, which are –
1. Location
2. length
3. Mark
4. Numbers
5. bending details.
6. Type
7. Size
These all quantities can be calculated by design drawings except length of
the bar. Hence length is calculating as CRANK LENGTH.
CRANK LENGTH :-
1. Bent up of bars
2. Hook length
1. Bent up of bars :-
Breadth – Height.
• Contract should be -
(i) contract should be in written.
(ii) subject should be simple and understandable.
(iii) It should be enforceable by court of law.
(iv) There must be free consent by both parties.
(v) Both the parties must be competent to sign the contract.
Contract document Should contain -
(i) Title page :- It has name of work mentioned overs it.
(ii) Index page:- It has page reference with content.
(iii) Tender notice :- It consist of brief description of work, cost of project and
completion time and amount of Earnest money.
(iv) Tender form :- It consist of bill of quantities, contract Rate, and total cost.
(v) Schedule of Rate
(vi) General specification
(vii) Detailed specification
(viii) Drawing at work
(ix) conditions of contract
(ix) conditions of contract.
➢In this the contractors undertakes the execution of work on the item
rate basis.
ii. The payment to the contractors is done on the basis of actual work.
Disadvantage
i. The total cost of work in not known at the start of work.
➢In this contract the payment to the contractor are made in percentage of the
work done value.
Advantage
▪ It is profitable to contractors.
Disadvantage
➢In this type of contract the contractors is paid by the owner the actual
cost of construction plus an amount of fees inversely variable according
to increase on decrease of the estimated cost.
Advantage :- In this case the contractors shall not try to increase the cost of
project unreasonably.
➢In this type of contract the contractors is paid the actual cost by the owner
➢In this type of contract, proper control has to be exercised by the owner in
➢In this contract, contractor agrees to perform specific job for fixed sum.
➢In this contract both parties try to fix the condition of work as precisely as
possible.
➢In this contractor undertakes the construction of a work with all contingencies
Disadvantage :-
➢ In this owner (dept) pay to the contractor for only the use of
labour in project and all the materials for construction are
arranged by Department.
8. Negotiated contract :-
➢When work is allotted to the contractor by mutual
execution, maintenance.
11. Package contract :-
contract.
15. Departmental contract :-
➢If the contract is done with a minor person [below 18 years age]
or without free consent then that contract is not valid and
declared as a void contract.
➢A void agreement is one which cannot be enforced by law.
Tenders
➢It’s the process of inviting bids or proposals in response to an invitation.
➢It is also defined as an offers in writing to execute the work as specified
by the owner.
Notice inviting tender (NIT) :-
➢It is prepared by administrative department after getting all the
necessary approvals.
(iii) Submission and opening of tenders and their scrutiny takes place
c) Bill of quantities
d) Condition of contract
e) Form of tender
f) Form of agreement
g) Form of Bond
Important terms used in tendering :-
Earnest money :-
➢It is the deposit made by the contractor after acceptance of his tender
➢Its purpose is to get the work done by the contractors as per specification
in stipulated time.
items.
Arbitration :-
➢It in the process of settlement of dispute between contractor
➢In this period contractors is required to maintain the entire work, in case
any defect in observed in it.
deposit.
Act of God :-
➢All the natural disasters comes under the act of god.
➢In such case, contractor is not liable for delay in the project
and owner is not liable for any damages.
Mobilization advance :-
advance.
Rejection of particular tender :-
• A particular tender is rejected in following conditions -
(i) Attendance
(ii) Payment.
i) Engineer in-chief
v) Assistant engineer
2) Taxation
3) Rent fixation
various reasons.
VALUE
is termed as value.
Price = C + Profit
Gross income :-
various sources.
(a) Taxes
• These are annual taxes paid by the owner such as - wealth tax, property
tax and municipal tax etc.
• (It varies b/w 10-25% of net income).
(b) Management
• Up to 10% of gross income is used for management purpose which
includes security guard, sweeper etc.
(c) Repairs
• 1.5% of total construction cost is set aside for annual repairs of
building. –
• These repair are must to maintain the building. –
• It is also calculated as 10% of gross income.
(d) sinking fund
• A certain amount of the gross rent is set aside annually as sinking fund
to accumulate the cost of construction at the end of design life.
(e) loss of rent:
• This is also an outgoing in case a building not fully occupied by the
tenants.
(f) insurance
• Premium given against fire and theft is also a type of outgoing.
(g) miscellaneous
• lighting of common area, expenditure of liftman etc. –
• It is applicable for big buildings only.
Perpetual income :-
• Income received for indefinite period is termed as perpetual income.
E.g. - Pension, royalty
➢When the property is sold or purchased at higher rate than it's market
➢It is defined as the value which a property can fetch when sold
(SHARE MARKET)
Potential value :-
value.
RENT/OFFICIAL
Monopoly value :-
accommodation value.
Rateable value
➢It is the net annual letting out value of a property obtained after
deducting the amount of yearly repairs and maintenance cost from
gross income.
➢At the end of design life book value is equal to scrap value or salvage
value as the case may be.
Depreciation :-
➢This decrease in value takes place due to wear and tear, impact
Corrosion, change in fashion or design of the structure or assets.
➢This method in
recommended for all the
assets which have constant
demand and does not face
obsolescence.
(B) Constant percentage method :-
➢Also known as Declining balance method
➢In this method the property is assumed to loose its value by a fixed
percentage of its book value known as fixed decl9ining book value
(FDB).
𝒐𝒓𝒅𝒆𝒓 𝒏𝒖𝒎𝒃𝒆𝒓
DF =
𝑺𝒖𝒎 𝒐𝒇 𝒕𝒉𝒆 𝒚𝒆𝒂𝒓𝒔
• ASF =
by the free holder, then the property is termed as lease hold property.
Capital cost.
Year purchase :-
𝟏
Year purchase =
𝒊