Professional Documents
Culture Documents
4 Th. Stage Methods of Construction and Estimation (Yousif Salam Shwani)
4 Th. Stage Methods of Construction and Estimation (Yousif Salam Shwani)
4 Th. Stage Methods of Construction and Estimation (Yousif Salam Shwani)
Syllabus
o. Subject
1- Construction Industry: Introduction to the construction Industry
2- The parties to the construction and operation stages .
1
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
List of references
1. Civil Engineering and Costing, S.P. Mahajan, 624. 1042, M214.
2. Estimating Building and Construction, 692.5, H816, 73-119.
3. Civil Engineering Estimating and Costing, V.N. VANZIRANI, S.P. CHANDOLA, first
edition, 1982.
Construction Industry
Creation is considered one of the largest construction industries because they include the
following:
1. Creation of construction materials and materials of electrical and mechanical services
industry from raw materials .
2. Convert these materials into projects and facilities under certain schemes and designs
.
3. Works operation and maintenance of the project.
4. Depend on a very large sector of human labor and administrative specialized cadres .
Therefore construction industry could be define as a services which change schemes and
designs made by engineers to integrated project
It includes the implementation of any project and the completion of the work of many
paragraphs as well as a large group of complex relationships
The project with multiple owners, civil engineers, architects , contractors and factories
owners, materials and machinery supplier, as well as some complex relationships with
government institutions , workers and others.
In The reality, construction industry varies from country to other and change in the same
country as well as from time to time and for the following reasons:
1. The reality of industries producing construction material and accessories, for example,
in Iraq, there is cement and brick industry while the iron industry there is weak and there
is no wood industry.
2
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2. Provide employment. If available labor required sizes and qualities, it leads to price
stability and the availability of worker.
3. Technical level. with the higher the requirements of development has increased the
need for technology in the construction industry will increased, which shorten the time and
cost.
4. Funding. It means the cash potential.
5. The quality of the required projects. Depending on the different ways of development
projects, in some countries, industrial being the appropriate projects however, in other
tourism is being the most appropriate project, and so on.
6. The availability of planning and designing cadres.
Hence, any civil construction activity should contain three stages namely:
A- Planning stage.
B- Designing stage.
C- Construction stage.
The relation between these stages could be clarify with this simple scheme.
n
additional work
Project Implementation stages
3
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
1. the good performance of constructed structures which fit with the target, for example, if
the project is commercially must achieve the intended profit .
2. Constructions progress have to follow the advanced prepared time schedule program
to avoid any fines due to delay.
3. The implementation , operation and maintenance costs have to be within the limits of
the prior estimated cost amount, designated materials and identified it to the study which
has prepared in advance .
4. The project has not lead to any environmental damage .
Employer
Supplier of the
The project
materials Engineer
Secondary
contractor Main
contractor
There are three main issues in each project : the time - cost and funding - quality. Since
the optimal time is the time that the project can be implemented in the least by the cost
without affecting the level of engineering specifications required for the project.
If we want to reduce the time the cost must be increased for the following reasons :
a. Increase the number of workers.
b. Increase the number of equipment or capacity.
c. Increase working hours or shift.
4
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The above mentioned increases must be studied well to ensure that this increase would
not lead to inverse results (an increase in the cost of poor quality or lack of
improvement).
The funding is to provide cash and material resources with necessary values according to
the original programming for the project. The Contractor would be funded in the form of
payments. However, the contractor funding periods shall be proportional to the executed
work.
To obtain a balanced relationship between the cost and time requires resorting to different
methods of implementation depending on the requirements of the situation.
Cost
ذ
Time
5
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Construction Equipments
3- Types of equipment
6
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The opted mechanism must achive the work requirement at the lowest cost (Lowest price
mechanism ) and resort to the use of private vehicles in the following cases :
1. When the job can not be achived by using standard equipment.
2. When the time is the most important factor ( the dominant factor ) in the completion regardless
of the cost .
3. When the unit cost or production for the especial mechanism less than they are if you use a
standard mechanism , but provided unit quantity have to be suficiant to recover the cost of
purchased machine (subtructing the value of the mechanism after use).
7
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
8
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
(1) by using the built in the 1st method the total cost include the following:
the conveyor belt cost at the end of the project = (625,000,000-125,000,000) = 500,000,000
9
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
(2) by using by using standard equipment trucks to transport stone in the 2st method the total
Example-2
It is intended to set up a water supply network for a residential village, the excavation section as
shown in the figure and the total pipes length is 2 km two following methods were selected,
Determine which method is more economic in term of the cost and duration of the completion of
the project.
1- First method use 8 group of worker, each worker wage is 20,000 ID/day average worker
production is 3 m3/day, and each eight workers require one supervisor with a wage of 40,000 ID
/ day.
2- Second method using a rented hydrolic excavator with productivity of 400 m3 / day which cost
300,000 dinars / day.
11
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
Toatal quantity=2,000x1.0x1.2=2,400 m3
1st. method
Eight group cost= 8x(40,000+8x20,000)=1,600,000 ID
Eight group production = 8x8x3 (m3/day)=192 m3 /day
So, the demanded duration= 2,400/192=12.5 day
therefore, 1st method cost=12.5 x 1,600,000 =20,000,000 iD
and requires a period of 12.5 days.
2nd. method
Total required period =2,400/400= 6 days
the total cost =6x 300,000 =1,800,000 ID
Thus, 2nd. method is recommended due to less time and cost consuming.
Solution:
Total quantity = 3 x2 x (2 x 60 +2 x 34)= 1128 m3
1st. method
11
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2nd. method
lets say 5 group used in each day
one group production=10 x 3 = 30 m3 /day
5 group production = 5 x 30 =150 m3 /day
one group cost = 50,000+10 x 25,000 = 300,000 ID/day
5 group cost = 5 x 300,000 = 1,500,000 ID / Day
Total working days = 1128 / 150 = 7.52 days
Tota cost = 7.52 x 1,500,000 = 11,280,000 ID
Thus : 1st. method is more suitable.
Below we will discuss the first case to assess the other cases .
The most important factors affecting the cost of owning and operating a particular machine are:
1-the annual value of a cash investment
2-The economic life of the equipment
3-The retrieval value of the equipment
4- The original cost of the machine ( the cost of purchase).
5- Work conditions of running the machine.
6- Number of operating hours per year(1800-2000) hour.
7- Number of years of operation .
8- maintenance and replacement of spare parts Care .
9- demand for used similar machines that affect the retrieval value ( the value of which is sold
after use ).
12
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Annual money value = value of money x(1+ The number of years × annual interest rate )
B- The compound interest =(6%):
V(annual)= invested amount(1+interest rate)t
where:
V(annual) = Annual value of an invested cash.
t = years number
Example-4
A vibrating roller was purchased at a price of 75 million ID has 5 years useful economical age,
Calculate the cost of owning the vibrating roller Basis on simple and compound interest account.
Solution:
A- Simple interest=5%
Annual money value = value of money x (1+The number of years × annual interest rate )
= 75,000,000 X (1+ 5 x 0.05)
=93,750,000 ID
B- Compound interest=6%
V(annual)= invested amount X (1+interest rate)t
= 75,000,000 X (1+ 0.06 )5
= 100,366,918.3 ID
13
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
4.1 Depreciation
Could be defined as a decrease in the value of the machine due to the use of the machine and/
or the period of time .
And it is calculated as follows :
D=(P-S)/n
14
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example-5
If the total cost (purchase + transport + installation) the machine is equal to (50 million dinars) and
the amount sold after use for five years (15 million dinars). Calculate the value of depreciation per
hour assuming the machine works (2000 hours) per year.
The solution/
D=
Book Value
Is the machine value at the beginning of each year resulting from subtract the amount the
Depreciation of the previous years from the amount of the machine purchase.
Depending on the number of years of use this percentage is estimated For example, if the
expected years of use is five the ratio of the Depreciation is (1 / 5) X 100% = 20 % , according
to the type of machine and working conditions the rate of Depreciation can change for example,
the double Declined Balance assumes the rate of Depreciation of
(2 / 5) X 100% = 40 %, which means double percentage.
Retrieval Value
Is the sale price of a machine after using it for a certain period, which represents the Book value
of the machine at the end of the work period or after its use .
Example
For the same previous example(Example-5), Calculate the value of retrieval assuming that the
depreciation value rate is doubled.
The solution/
Doubled Depreciation rate = X100% = 40 %
15
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Retrieval value=70,000,000-64,556,800=5,443,200
or
book value at the end of fifth year = 9,072,000-3,628,800=5,443,200
Note that the book value at the end of the duration of use ( the end of the fifth year ) is equal to
the retrieval value .
B-Declined Balance Method (D.B.M)
Annual Depreciation Value (D)=2(1/Economic age) x100%
D=2x( )x100%
Example-6
A machine was purchased at a price of 720,000,000 ID has 5 years useful economical age,
Calculate the machine Book value at the end of each year Basis on Declined Balance Method.
Solution:
Annual Depreciation Value (D)=2(1/Economic age) x100%
D=2(1/E)X100%=2(1/5)X100%=40%
16
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example-7
A Scraper was purchased at a price of 120,000,000 ID has 5 years useful economical age,
Calculate the machine Book value at the end of each year Basis on Sum of year Digits if the
machine retrieval value is 12,000 ID
Solution:
Total year number=1+2+3+4+5=15
D=5/15
Total Depreciation Value= Book Value- Retrieval value
=120,000,000-12,000,000=108,000,000 ID
17
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
18
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example-8:
Year Machine book value ID
1 50,000,000
2 35,000,000
3 25,000,000
4 15,000,000
5 5,000,000
P-= = =32,000,000 ID
19
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
coefficient with a useful life of 5 years and 2000 working hours per a year, annual cost for
maintenance and spare parts 80% of the annual depreciation, tire useful life is 4,000 hours, tire
maintenance cost 15% of the annual depreciation cost, the machine total cost $46,000, tire cost $
8,000,the cost of a one liter of fuel is $ 0.3 per liter and oil cost $2.5 per liter and operators
wages is $4 per hour. By taking the advantage of one of the following proposals
1- hiring the machine with fixed rate cost $ 30 per hour throughout entire machine economic age.
2- It is possible to apply for a contract to perform a project to remove 350,000 m3 soil each
1m3cost $ 0.5 to be completed during the period of 4 years with a fine of $200 as a penalty for
each late day, the machine might transport 50 m3/day.
The solution/
The machine cost without the tires= 46,000-8,000= $ 38,000
Machine average value (P-)= = = $22,800
Fuel quantity=0.15x200x0.6= 18 Liter/hour
Oil quantity=0.003 x 0.6 x 200 + = 0.6475 Liter/hour
Annual cost
1- Depreciation= = $7,600
2-Maintenance and repair = 0.8 x 7,600 =$ 6,080
3-Investment= = 0.12 x 22,800 = $ 2,736
Total annual cost=7,600+6,080+2,736=$16,416
Operational costs per hour:
1- Fixed costs = = 8.208 $/hour
2- Tire depreciation= =2 $ \ hour
Maintenance and repair of tires = 2 x 0.15 =0.3 $/hour
3- Fuel cost =(0.15 x 200 x 60%)x 0.3=5.4$/hour
4- Oil cost =(g)x2.5= (0.003 x 200 x 60%+ )x 2.5=1.61875 $/hour
5- Operator wages =4 $/ hour
Total hourly operational cost = (8.208+2+0.3+5.4+1.61875+4)=21.52675 $/hour
Total cost of entire machine life=21.52675x2000 x 5 =$ 215,267
Case I, the profit would be gained from hiring the machine of 30 $/hour is
total amount =30x2000x5=300,000 $
the net profit gained from hiring the machine=300,000-215,267=$84,733
Case II
The amount gained from the contract of removing all the soil quantity =350,000x0.5=$175,000
=7000 work hour per contract
21
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Contract required period= 3.5 year (Within the prescribed period 4 years)
Thus, no penalty would be considered. and it is possible to let the machine for the rest of the
time.
remained economic age=5x2,000-7,000=3,000 hour.
Therefore, Extra profit from hiring=3000 x 30 =$90,000
Total amount gained from the contract and hiring=175,000+90,000=$265,000
Thus, expected profit=265,000-215,267=$49,733 It is clear Case I is more profitable one.
H.W./Two options are available for a contractor as below:
1- Investing amount of $100,000 in a bank under a special offer of (8%) annual interest rate.
2- Purchasing a bulldozer and rented it to one of the construction project for 5 years with a hiring
cost of 100 $/hour.
If the following information were available:
1- Purchasing price =$100,000
2- Selling price after 5 year = $50,000
3- Engine HP=350 horse with 30 liter basin capacity oil changing period is 120 hour and
operating factor is 85%
4- Annual work hour is 2000 with annually repair and maintenance cost is 90% of annually
depreciation.
5- Diesel price is 0.3 $/ liter and oil price is 2.015$/liter
6- Operator wage 2 $/hour.
Select the most profitable method.
1- Rolling resistance:
Is the resistance faced by any vehicle while
starting a movement which vary according to the nature and quality of the surface.
Surface types
A-Soft surface (clay): (high resistance)
21
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2- Grade resistance:
When a machine moves on sloping surface, the vehicle traction effort
Increases with the increasing tendency surface. The rise of a machine on the road slope
inclination (1%) lead to increased effort to resist the inclination effort by the engine about (10 kg /
ton) of the machine weight .
22
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The exact value of the grade resistance may be found by multiplying the vehicle's weight by the
sine of the angle that the road surface makes with the horizontal.
∴ the net engine power= [real engine power x operating coefficient]-[required power to overcome
a rolling resistance+ required power to overcome a grade resistance ]
3-Effect of traction
The power available to move a vehicle and its load is expressed as rim-pull for wheel vehicle and
drawbar-pull for crawler tractors.
Rim-pull is the pull available at the rim of the driving wheels under rated condition.
Since, it is assumed that no slippage on the tires on the rims will occur, this is also the power
available at the surface of the tires.
drawbar-pull is the power available at the hitch of a crawler tractor operating under standard
condition.
Coefficient of Traction: could be defined as a coefficient that produce maximum usable pull if
multiplied by weight on drivers
Maximum usable pull= Coefficient of traction X weight on driver
This represent the maximum pull that a vehicle can develop, regardless of vehicle horsepower.
23
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Note, for crawler tractors and all-wheel-drive rubber-tired equipment the weight on the driver is
the total vehicle weight, but for other types of vehicles consultation with the manufacturer is
required to determine the weight on the drivers
Table of typical values of coefficient of traction
Type of surface Rubber tires Crawled Tracks
Concrete, dry 0.90 0.45
Concrete, wet 0.80 0.45
Earth or clay loam, dry 0.60 0.90
Earth or clay loam, wet 0.45 0.70
Gravel, loose 0.35 0.50
Quarry pit 0.65 0.55
Sand, dry, loose 0.25 0.30
Sand, wet 0.40 0.50
Snow, packed 0.20 0.25
Ice 0.10 0.15
Example / machine the value of the total weight on the driving wheels is 18,000 kg and the
highest pulling power of the machine is 8000 kg, machine is required a traction coefficient of 0.3
to work on a wet sandy surface, determine
The highest pulling power of the machine before tire sliding occur.
If you use the machine on a dry soil with a drag coefficient = 0.6, Is this the machine can make
Tires slip ?
24
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
Drag coefficient=
Since the highest pulling power of the machine is 8000 kg<10,800 kg provided by the surface.
therefore, the machine does not able to slip the tires
Factors limiting the usable power of a vehicle are:
A-Effect of Altitude:
All internal Combustion engines lose power as their elevation above sea level increases because
of the decreased density of air at higher elevation.
Manufacturer use de-rating factor to express percentage of reduction in rated vehicle power at
various altitude
There is no effect of the rise in the level of 300 m above sea level.
engine with a four-stroke = 0.03x HP x No. of times less than 3%
engine with a two-stroke = 0.01x HP x No. of times less than 1%
Example / An engine with a power of 100 horse, works on the sea level
surface. What is its horsepower ability at an altitude of 3000 m above
Sea level (engine with a four -stroke)
Solution:
loss due to altitude = 0.03x HP x No. of times less than 3%
= 0.03 x100 x
= 27 horse
25
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
H c =Ho x
A- crawler tractors
1-Surface traction power for tractors measured on a horizontal road to overcome a rolling
resistance is 50 Kg / tone in the case of the use of a different route correction must be done for
this ( correction =real rolling power -50)
2- Traction power proportional inversely to the gear number :
1st. gear (more tracking power & less speed).
Top gear (less tracking power & more speed).
3-Tractor efficiency =(0.80-0.85)
Wheeled tired tractor:
Grade-ability?
It is the highest slope degree ( grade ) to enable the vehicle to climb regular speed expressed as
a percentage of grade-ability which are changing according to:-
1-gear number
2-Vehicle mode (loaded or empty)
26
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example/ determine the grade-ability for a crawler tractor drags a loaded wheeled tire scraper,
using the following information :
Tractor net engine power (180 hp), tractor weight of 21 tons, attraction force on the first gear
15000 kg weight of a loaded scraper 40 tons on unpaved sandy road of rolling resistance to the
tractor is 73 kg / ton and a rolling resistance of the scraper is 90 kg / tone.
Solution/
Engine net power =(actual engine power x F)-(Sum of the power to overcome rolling and grade
resistances)
Traction power available in the tractor=15,000 x 0.85= 12,750 kg
Scraper rolling resistance= 40 x 90 =3,600 kg
Sum of rolling resistance forces=483+3,600=4083 kg (Note: correction :73-50=23 therefore p=23
x 21=483 kg)
the remained attraction force to overcome grade resistance=12,750-4083=8,667 kg
required attraction power to overcome a grade 1%=10kg
Total weight for the tractor and scraper =40+21=61 ton
Total attraction power required to overcome a grade 1%=10 x 61 =610 kg
grade-ability value =8667/610 =14.21%
grade-ability for the tractor without scraper
the remained power to climb the grade=12,750-483=12267 kg
required power to climb the tractor of grade 1%=21 ton x 10kg/ton=210 kg
maximum grade-ability for the tractor=12,267/210=58.4%
Grade-ability of a wheeled tractors and scrapers:
K=
K: grade-ability %
T: Motor torque(round/minute)or (kgXm)
G: gear decrease
R: The radius of the wheel rolling(m)
W: Total weight(kg)
N: Rolling resistance (kg/ton)
F: Efficiency(0.80-0.85)
Note: If k value in minus this means that the track cannot climb the slope(grade-ability=0)
27
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example / Determine the grade-ability (slope ability) for a wheeled tire tractor pulls a loaded
scraper at a speed of third gear with a motor torque 2100 R / min which is equivalent to 103.7 kg
x m reduction gear of 41, wheel radius of rolling = 0.75(m), total weight 63000 kg and the rolling
resistance 35 kg / tone
solution/ K = =2.35%
Example / a crawler tractor weighs 15 tons pull a loaded scraper weigh 25 tons ( wheeled tire
scraper ) on the road section shown bellow. If available power in the engine of the tractor is 5000
kg . What is the net power remained resulting of pulling the scraper over each section of the
road?
Road Slope% Tractor rolling resistance(kg/t) Scraper rolling resistance(kg/t)
section
AB -4 60 80
BC 0 40 90
CD +5 50 80
Solution/
Net engine power = [ total power - the required force to overcome the rolling resistance ( tractor +
scraper ) ± the required force to overcome the gradient resistance ( tractor + scraper )
Engine available power=5,000 x 0.85=4,250 kg
required force to overcome the rolling resistance ( tractor)=15 x (60-50)=150 kg (Correction
required because it is over 50)
required force to overcome the rolling resistance (scraper )=25 x80=2,000 kg
required force to overcome the rolling resistance( tractor+ scraper )=150+2,000=2,150 kg
required force to overcome the gradient resistance ( tractor)=15 x 10 x (-4)= -600 kg
required force to overcome the gradient resistance scraper )=25 x 10 x (-4)= -1000 kg
the required force to overcome the gradient resistance ( tractor + scraper )=-1000-600=-1600kg
∴Net engine power=4,250-(2,150-1600)=3700kg
∴The Tractor and the scraper can get down the section AB
28
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Section BC
required force to overcome the rolling resistance ( tractor)=15 x (40-50)=-150 kg (Correction
required because it is under 50)
required force to overcome the rolling resistance (scraper )=25 x90=2,250 kg
the required force to overcome the rolling resistance ( tractor + scraper )=-150 +2,250=2,100 kg
required force to overcome the gradient resistance ( tractor)=15 x 10 x (0)= 0 kg
required force to overcome the gradient resistance scraper )=25 x 10 x (0)= 0 kg
the required force to overcome the gradient resistance ( tractor + scraper )=0+0=0kg
∴Net engine power=4,250-(2,100-0)=2,150kg
∴The Tractor and the scraper can get down the section AB
section CD
required force to overcome the rolling resistance ( tractor)=15 x (50)=750 kg (No correction
required because it is = 50)
required force to overcome the rolling resistance (scraper )=25 x80=2,000 kg
the required force to overcome the rolling resistance ( tractor + scraper )=750+2,000=2,750 kg
required force to overcome the gradient resistance ( tractor)=15 x 10 x (5)= 750 kg
required force to overcome the gradient resistance scraper )=25 x 10 x (5)= 1,250 kg
the required force to overcome the gradient resistance ( tractor + scraper )=750+1,250 =2,000kg
Note: Rolling resistance could be negative because it is designed at 50 (which must be subtracted
from the given value ) when the given value be less than 50 will give a negative value of rolling
resistance(for crawler machine have to be corrected if it is not 50)
29
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Bulldozer uses:
1-Clean the land from the remains of trees and plants
2- Remove roads and old buildings
3- Open road in the mountainous and rocky areas
4- Pushing soil for a distance (not more than 100 m)
5- Assisting scraper for loading process
6- Distribution of a stocked soil for filling process
7- Backfilling trenches with soil
8- Clean the work site
31
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Rooters
1- Rocks extraction
2- break up and remove soil and sub-base materials(sand +gravel)
3- Roots extraction
4- Uprooting the old ways
rubber-tired (or wheel) dozers? crawler(or track) dozers?
1-High speed 1- Able to provide a high power
2-It doesn't required any transferred 2-able to work on hard and rocky
surfaces
3- able to move over paved roads 3- crawler width help to move easily in
a loose soil
4-High production
Estimating Dozer Production
production depend on
1-Soil swelling
Note / all engineering volume deal
With loose sizes (truck or shovel production )
bank volume= swelling volume
31
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
32
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
Loose volume=(0.5 x 1.2 x 1.2 ) x3.2=2.304 m3
production cycle time=(hauling time + returning time + fixed time)
={30/(2x1000/60)}+ {30/(4x1000/60)}+ 0.5=1.85 minute
cycles per hour=45/1.85 = 24.324 cycle
one day loose production=2.304x24.324x8=448.34m3
33
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2-Shovel:
A construction machine used to excavating of medium hard materials, loading hoppers and
haul units, backfilling ditches sand moving concrete and other construction materials such
as soil and rubble ,and rocks
Used like a bulldozer
Shovel types:
1-wheel loaders
2-track loaders
shovel production =bucket size x The number of cycle per hour
Shovel Productivity depends on
1-the fixed time: Time needed to fill the bucket+ rotation + discharge
2- The time required to transport the material (transport time)
3- The time required to Return ( Return time )
34
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example / Calculate the number of trucks that can work with a shovel loader using the
following information
(A) Shovel scoop size 0.6 m3 and one cycle time of 21 seconds ( cycle time = total time to
scoop loading, unloading and return )
B - a time for truck transport for a distance ( loading and unloading + Back) =7 minutes
Using
1- Truck size of 2.4 m 3
2- Truck size of 4.6 m 3
35
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The solution/
bucket cycle time = 21 seconds
The number of buckets to full the truck = = =4 scoop
time required for filling the truck =21 x4 =84 seconds = 1.4 minutes
The truck cycle time =(loading Time + transport time + Return time + lost time )
=1.4+7+0=8.4 min.
∴ Minimum number of trucks = cycle time of one truck/time of loading the truck
= =6 truck
(H.W)
Solve the example for part(2) (using the truck size of 4.6 m3)
3-Hoe
Type of a crawler tractor and called sometimes hydraulic tractor which used for soil
excavation located under the level of Hoe stand.
Production cycle time=loading time +discharge time+ rotation time + doze time
Bucket(Dipper)volume=(0.5-2.0)m3
production(m3/h)= Bucket(Dipper)size x cycle number per hour
Example/
Hydraulic Hoe has used for excavating an irrigation channel of a section as shown in the
Fig bellow. Calculate the required time for implementing the work and the cost of (1)m3
excavation by using the following information :
Scoop size=1.2 m3, time factor=45 min./h, daily work hour=8 hour, channel length=15km,
scoop filling time =12 second, rotation and discharge=6 second and doze time =2 second,
soil swelling factor =20% and the Hoe hydraulic excavator hire cost=300,000 ID / day
the solution/
Production = volume x number of cycles
cycle number=
Production=1.2x135=162m3/h
36
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
4-Scraper:
A construction machine capable of excavating, hauling, and dumping material over medium
to long haul distances. However, only the elevating scraper and pull scraper are capable of
achieving high efficiency in loading without the assistance of a pusher tractor or another
scraper.
Although, there are a number of different type of scrapers? principal types include:
A- Single-engine overhung (two-axle scrapers, three axle scrapers)
B- Twin-engine all wheel drive scrapers,
C- Elevating scrapers, auger scrapers, push-pull
D- Twin hitch scrapers
E- Pull scrapers
Two-axle or overhung scraper utilize a tractor having only one axle. such an arrangement
has a lower rolling resistance and greater maneuverability than does a three axle scraper
that is pulled by a conventional four-wheel tractor. However, the additional stability of the
three-axle scraper permits higher operating speeds on long relatively flat haul road.
All wheel drive scrapers utilize drive wheels on both the tractor and the scraper, normally
such units are equipped with twin engines, the additional power and drive wheels give
these units greater attractive effort than that a conventional scrapers
Elevating scrapers utilize a ladder-type elevator to assist in cutting and lifting material into
the scraper bowl, this type of scrapers are not designed to be push-loaded and may be
37
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
damaged by pushing.
38
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution/
Production cycle time =hauling time +return time+ fixed time
=
cycle number=60x0.83/5.1=9.8 cycle(do not change it because this represent cycle
number per one hour not the day)
production=22 x 9.8=215.6m3/h
daily production=215.6 x 8=1728.8m3/day
H.W./ To Implement a highway project scrapers were used to excavate and hauling the soil
of the amount of 16520 m3 to the dumping site distanced 1 km away from cutting area,
The work must be implemented in 4 days the scraper bowel capacity 20 m3 hauling speed
rate 25 km/h on a slope(1:3), fixed time = 2.4 minutes daily working hours 8 hour
operating efficiency 0.85
1-Calculate the scraper number that required to implement the work without delay ?
2-How to increase the productivity ( reduction in the duration of work) prove that
mathematically?
39
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
physical Properties of soil have a direct effect on the ease or difficulty of handling earth,
the selection of equipment and the production rate of equipment. these properties include
swell and shrinkage
Sw = (
Sh= (
Sw = ( =21%
Sh= ( =15%
41
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Types of soil
Soils may be classified according to the sizes of particles of which they are composed by physical
properties or by their behavior when the moisture content varied.
A contractor is concerned primarily with five types of soil
1- Gravel>6 mm
2- Sand>(6-0.05)mm
3- Silt <0.05 mm
4- Clay (0.002)mm
5- Organic matter and combination of these types
Soil Tests
prior to preparing the specification for a project representative samples of soil are collected
and tested in laboratories to determine their properties including the dry unit weight and
the percent of moisture required for maximum compacted density.
the optimum moisture content is the ratio of the weight of water in the dry weight of soil
expressed as a percent that will permit the soil to be compacted to the maximum density
with the least effort.
Laboratory tests the lab. tests that is accepted by highway departments and other agencies
are: 1- Standard Proctor test 2- Modified Proctor test
Field tests are conducted by removing samples of compacted soil from the fill at random
locations and then determining the damp and dry weights of each sample, the volume of
the hole can be determined by using dry sand, the dry and wet weight of the samples are
determined the dry weight density and moisture content of the sample can be determined.
Nuclear determination of moisture density of soil
Nuclear methods are used extensively to determine the moisture density of soils
Advantageous of nuclear method in comparison to Proctor method are?
1- Decreasing the test required time
2--Does not required the removal of soil sample from the site of the test
3- Providing a means of performing density tests on soils containing large-sized aggregate and
on frozen materials.4- Reduces or eliminates the effect of the personal element, and possible
errors that may occur in performing Proctor method.
41
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Methods of stabilization?
Firstly/Mechanical method
Mechanical – The oldest types of soil stabilization are mechanical in nature. Mechanical solutions
involve physically changing the property of the soil somehow, in order to affect its gradation,
solidity, and other characteristics. Dynamic compaction is one of the major types of soil
stabilization; in this procedure a heavy weight is dropped repeatedly onto the ground at regular
intervals to quite literally pound out deformities and ensure a uniformly packed surface. Vibro
compaction is another technique that works on similar principles, though it relies on vibration
rather than deformation through kinetic force to achieve its goals.
42
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
43
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
44
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Where :
D= Equivalent circle diameter W=
Applied load (N)
P= Pressure inside tire MPa
(N/mm2)
A= Area of circle
example
Pneumatic multiple-tired rollers type (7.5 x 15-14 Fly)with loading weight on one tire of
1500 kg with tire pressure 0.6 N/mm2 used to compact a soil, determine the maximum
height of the soil layer that required to be compacted to get at least 0.35 N/mm 2 pressure
under each layer.
The Solution:
A= =25,000 mm2
45
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Used in cement and other construction material manufacturing and used also in soil stabilizing.
CSH Ca(OH)2+ CiO2
Methods of adding chemical materials?
1- Site mixing
2-Inadvance mixing
3-Mixing in a paste form
46
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
47
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The Ideal mix contain (10-35)% fly ash (10-20)% lime the mixed soil compacted with
suitable soil moisture content.
48
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
49
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
51
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
51
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example
Multi-storey building to be constructed on a layer of soft muddy soil(soft clay) which supported by
a strong muddy layer(stiff clay) directly beneath it as shown in the figure below. Suggest a way to
stabilize the soil and calculate the amount of material required for this process if the dimensions of
the foundations of the building is (30 x20)m
Solution / stone pillar method is used to stabilize the soft muddy soil to the depth of 5 meter (by
using a 0.5 m diameter column and the 2 m spacing between the columns) and adding a
compacted layer of sub-base with a thickness not less than 25 cm.
number of columns=(1+L/S)X(1+W/S)=(1+30/2) X(1+20/2)=176 Stone pillars
Granular material filler volume=176x[(3.14/4)x0.52x5]=172.7m3
Sub-base layer volume= 20x30x0.25x1.2=180 m3
52
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Aggregate divided by
1-Course aggregate
2-Fine aggregate
Aggregates sizes differ depending on the quality of the concrete (required compressive
strength).
Gravimetric or volumetric method used to measure cement concrete components.
The gravity method (accurate) used in the central mixing stations.
Volumetric method ( inaccurate) used for mixers in the site
53
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Concrete mixers:
1-Construction mixer
2-Truck mixer
Mixing cycle time = Patching time + mixing time+ dumping time+ lost time
Mixing time = (1-1.5) minute for each 1 m3 concrete
54
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example / Find the amount of material required for one cycle of the 0.452 m3 size of a
construction mixer, one productivity cycle times of the mixer
( Loading time = 0.25 minutes, mixing time = 1 minute, time of discharge = 0.25 min,
lost time = 0.1 minutes), the required quantities for 1 m3 of concrete is
Cement Sand Gravel Water
366 kg 853 kg 1095 kg 195 liter
The Solution/ Cement volume= 0.452 x 366=165.432 kg per cycle. say 3 bags=150 kg
therefore, the corrected volume =0.452x 150/165.432=0.41 m3
Sand weight =853 x 0.41 =349.73 kg
Gravel weight= 1095 x 0.41= 448.95 kg
Water weight = 195 x 0.41 = 79.95 liter
production cycle time = 0.25 + 1 + 0.25 + 0.1 = 1.6 minutes
No. of cycle per hour = 50/1.6 =31.25 cycles
the daily production = 31.25 x 0.41 x 8 = 102.5 m3 per day
Asphalt concrete
asphalt concrete is composed of aggregates, filler materials and asphalt that are mixed
together in heated under certain temperature.
The hot asphalt production is moved to the site under certain temperature of (170-120)
Celsius degree and then spread and followed by compaction under certain Celsius degree.
55
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2- Transporting stage
Transported using trucks (16-24)m3
3- Spreading stage
Using asphalt spreader (120 Celsius degree) production (30-50) m3/h with variable width of (2-
8)m and variable thick of (5-20)cm
4- Compacting stage
A- Using steel compactor at (120 Celsius degree)
B- Using pneumatic compactor at (90 Celsius degree)
Example / A mat foundation to be poured with 340 m3 concrete using the following two
methods, analyze the possibility of using each method and the cost of 1 m3 production of
concrete for each method
56
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
A- First Method
Purchasing concrete from a central mixing producer located 15 km away from the project site, the
concrete producer can provide the following:
1- A central mixer of 0.5 m3 size with 1.6 minutes cycle time, time factor (45) minutes, and a
daily hire cost of 500,000 ID.
2- A six number of truck mixers of 5 m3 size with 40 km/h transport speed and 60 km/h return
speed and total lost time of 6 minutes, the daily hire coast 200000 ID for each truck
3- A concrete pump with 0.5 m3 /minute which cost 300,000 ID for a day
B- Second Method
A site construction mixer of 0.2 m size,90 second cycle time, 50 minutes time factor and a daily
hire cost of 400,000 ID including the production cost a working day mean 8 hours of production.
The solution/
A- the first method
1- Central mixer production=(0.5 x 45/1.6) x 8 = 112.5 m 3/day
∴ The required time to complete the work=total volume / daily production
= 340 / 112.5 = 3 days
2- The required time for truck loading=(5/0.5) x 1.6 = 16 minute
Truck cycle period = 16 + [15/(40/60)]+[15/(60/60)]+6=59.5 minute
∴the required truck number=(truck cycle time/truck loading time)
=(59.5/16)=3.72 truck (use 4 truck for three days)
∴ Truck production = (45/59.5) x 5 x 8 = 30.25 m3/day
∴ 4 truck production = 4 x 30.25 =121 m3/day> plant production=112.5m 3/day (OK)
3- The pump production=0.5 x 60 x 8 = 240 m3/day
∴ total cost = 3 x [500+(4x200)+300]=4,800,000 ID
∴ 1m3 cost = 4,800,000/340 = 14,118 ID
B- Second Method
The site concrete mixer production = 0.2 x 50 /(90/60) x 8 = 53.34 m 3/day
∴ required execution time = 340/53.34 = 6.4 days (say = 7 days)
∴ The total cost = 7 x 400,000 = 2,800,000 ID
57
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Concrete formwork
The principal requirement for concrete formwork are?:
1- Safe under working load
2- produce the desire shape and surface texture
3- To be economical
Since, formwork may account for 40-60% of the cost of concrete construction it is
essential that the formwork plan be carefully developed and thoroughly evaluated. A cost
comparison should be made of all feasible forming systems and methods of operation .
such an analysis must include the cost of equipment and labor required to install
reinforcing steel and to place and finish the concrete as well as the cost of formwork, its
erection and removal
The formwork plan that provides the required safety and construction quality at the
minimum overall cost should be selected for implementation.
58
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2-Check surrounding excavations to ensure that formwork does not fail due to
embankment failure.
3-provide adequate bracing of forms, being particularly careful of shores and other vertical
supports.
4- Control the rate and location of concrete placement so that design loads are not
exceeded.
5-Ensure that the supports are not removed before the concrete has developed the
required strength.
6-Avoid injury caused by swinging of the form due to wind forces
7-Protruding nails are a major source of injury on concrete construction sites. As forms
are stripped form lumber must be promptly removed to a safe location and nails pulled.
59
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
3-For columns
61
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
61
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
62
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
the maximum spacing of the joist will be limited by the strength of the permissible
deflection of the decking.
the maximum spacing of the stringer will be limited by the strength or the permissible
deflection of the joist .
The maximum spacing of shores under the stringer will be limited by the strength or
permissible deflection of the stringer or the capacity of the shores
in designing forms for beams and slab the design load should equal the weight of the
concrete plus an additional load of 40-50 psf
(1.92-2.4 KN/m2), to provide the weight of buggies and workers and for the storage of
materials on the slab during construction
63
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
64
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
65
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
66
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
67
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Assume shores with dimension of (0.15x0.15)m is used with unsupported length of (g=3.25m)
and Fc=5861kPa
To check shore compressive strength
Total weight on the shore =1.343x1.808x6.22=15.103 kN
Required area for compressive strength (A)= P/FC=15.103/5861=0.00258M2
Since (Supplied area) 0.15x0.15=0.0225 > (Required area) 0.00258 ok.
Checking of maximum safe applied load (KN) on shores for unsupported length
+116.8kN (ok)
68
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Estimation:
Estimate quantities of materials (volumes, areas, lengths, sum ...... etc.] for engineering projects
to find the budget and time required for the project implementation through estimating prices of
each element of the project or refining estimated cost of the similar projects to find cost-final.
Pros of estimation:
1-Project location
4- Official holidays
6-Work preparation
69
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Cost Estimation
Estimated cost of construction cost estimated under the multiple ways, the most important of these
methods are the following methods:
A- Approximate Estimation
Prepare an estimated cost of a project d for the cost before prior to preparing the final design
according to the conditions, specifications available in a contract.
Example
A constructing building with a dimension of (20x35)m consist of basement, ground floor, 1st. floor,
2nd floor and roof. the building constructing cost is (1.89) billion ID find the estimated cost of 1
m2 of the building based on these two methods
1- All three storey, basement and roof have same cost for (1 m2)
2- Basement cost for 1 m2 consist 60% of other storey cost and roof cost for 1 m2 consist 40% of
other storey cost.
71
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
solution
1st assumption
2nd assumption
This method could be more accurate than the first method due to consideration of the third
dimension (height), in this method each storey volume in m3 calculated separately according to
the cost of a similar constructed building.
71
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example
1- All three storey and basement had same cost for (1 m3)
Solution
1st assumption
2nd assumption
72
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
This method calculate the approximate amounts of different construction materials elements such
as (foundation, frame, slab, doors and windows, finishing, tiling, electricity, sanitary) each item
priced separately to get the project final cost.
B-Detailed Estimation
In this method the construction will be breakdown into items, detailed estimation of each item will
be prepared after detailed analyzing its cost including the cost of material, labor and overhead,
administration and profit cost.
this type of estimation must be done by a contractor before a tender submission or participating in
an important contract, the estimator have to breakdown the project into items including preparing
work, material, excavation, and all different related required work like site cleaning from debris.
Total detailed cost is calculated by multiplying each item quantity by its suitable implementing
cost. Due to the complexity of the calculation must be done by specialist persons and engineers
who has good contact to the different local and international market and has a widely knowledge
about different materials and labor cost, the cost in this estimation method is more representative
to the real virtual cost.
Amendments to the previous price for the purpose of approximate estimating the following points
should be taken into consideration.
73
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
1- Demanded technical specification and finishing differences or similarity between the previous
and the present project.
4-General and specific specification conditions for the previous and the present project.
74
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The Solution:
Cost factoring
Cost changes due to time factor
= 0.181=18.1%
75
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
3- Contract No contract +5
facilities facilities
Total 21.11
: : : : : :
76
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2-Earthwork
This work includes digging tunnels and drilling pillars and reservoirs, ditches, ponds septic and
foundations, or may be the excavations for the purpose of removing the top surface layer of the
Earth's natural and that may be a container on the waste and herbs and organic materials, where
required the contractor to dig to a depth appropriate depending on the nature of land, and the
excavations measured in m3.
It is usually drilling depth specified as maps and pre-defined dimensions, and the contractor using
heavy machinery such as Shovel, Bulldozer .... etc.
Excavations on the borders of the workspace are not limited only by what is planned for the
project, but there is a need for additional external spaces outside the boundaries of the project
area up to 1.0m to 1.5 m for general purposes.
after the completion of excavations perhaps there is a need to backfill and this must be
compacted according to required technical specifications, which are the following:
77
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example-1-
Estimate the amount of soil excavation needed to create the mat foundation under the building
below, note that an extra 1.5 m excavation away from all sides and to depth of 0.8 m.
Solution: we draw the outer limits of the excavation in the form of a dashed line is 1.5 m on all
sides, and then we divide the total area to secondary spaces as shown in the figure below, and
then we calculate the volume of the soil excavations.
30 30 30
Area=L m
Se L1 L2 Vol.=Area 15
1*L2
c. (m) (m) *D (m3) m
2
(m )
A` 33 48 1584 1267.2
C
B 30 33 990 792 B
A
C 30 18 540 432
78
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
in small buildings: homes, for example, are usually implemented using the adoption of strip
foundations, this type of foundations located only under the walls and not on the entire
construction area such as mat foundation.
Example-2- Estimate the size of soil excavation necessary to implement a strip foundation for two
rooms in the figure below, note that the wall thickness (0.2 m) and foundation width (0.6 m) and
depth (0.8 m).
Solution: to estimate the excavation volume of trip foundations there are two ways:
1-The method of entrances and exits of the centers: in this way is the building is divided into a
set of horizontal walls and vertical and is added to show the foundation to the horizontal walls and
raised from the vertical walls, or vice versa, and as follows:
First case: Adding to the horizontal walls and subtracting from vertical walls:
1 9.4+0.6 2 20
2 3.2-0.6 3 7.8
27.8
79
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Second case: Adding to the vertical walls and subtracting from horizontal walls:
a 3.2+0.6 3 11.4
b 4.2-0.6 2 7.2
c 5.2-0.6 2 9.2
In this way lengths centers are collected for each walls b of the building, then the following
formula will be applied:
Foundation total length = total lengths of the centre -
Where : is the number of interaction of two walls or more
is the foundation width
For the previous example:
Foundation total length=2x9.4+3x 3.2 -
For both methods Volume =27.8 x 0.6 x 0.8 = 13.344 m3
81
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
x 30
Solution: x 5.1m
0.3 1.75
steps number= 5 x 5.1=25.5m & 30-25.5=4.5 m
y 1.75
y 0.2625m
4.5 30
h 1 0.2625 0.7375m
1 0.7375 1 0.7 3
Excavation volume= 4.5 5.1 5 * 0.6 =15.35 m
2 2
Example:
abcde is a part of a mountain road, it is required to estimate the excavation volume of the
foundation with 1.2 m width and the depth of no more than 1.2 m and not less than 0.9 m and
distances between the points (a, b, c, d) are equal.
83.78
Solution: ` ad r 40 120 83.78m x 27.93m
180 3
1.2 0.95 1.2 0.95
Excavation volume= 1.2 25 27.93 3 = 140.34 m 3
2 2
3-Crushed stone under the foundation item (m 2):
is usually after the completion of the excavations works of foundations, the bottom of the
foundation covered by crushed stone or break bricks with a thickness of 8 cm or 10 cm, taking
into account the compaction as much as possible and the advantageous of crushed stone are:
81
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
We mean the transfer of pressure to Bearing that is crushed stone to prevent direct contact
between the soil and the foundation and this pressure from direct turns into indirect, and can be
likened to the soil as a piece of glass loaded by force which include the foundation and above and
this glass Easy will break, but in the case of put a piece styropor under or between force and a
piece of glass, the glass less likely to break, and a piece of styropor here represents the crushed
stone.
Also, crushed stone does not allow the descent of the water directly to the soil that might be too
dry, leading to absorption mixed concrete water which is very important in hardening concrete.
The amount of crushed stone base = length * foundation width
for Example 2,
the amount of crushed stone = 27.8 * 0.6 = 16.68 m 2
4- Pouring a concrete of foundation:
Concrete is a combination of three main materials namely cement, sand and gravel, if t the water
is added to the mixing of these three substances to prepare the concrete, the mixture loses almost
a third of its size, and the blending of these materials usually on the basis of certain volumetric
proportions, These include the following ratios:
1 1.5 3
1 2 4
1 3 6
1 4 8
1 5 11
It is preferable to determine the percentage of blending used for concrete in construction work,
and the common ratios used in buildings usually are volumetric percentages and can be weighted
percentages of the mixed elements which is more accurate, and below some construction items
and matching mixing ratios:
82
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
1) weak concrete works: is used as a modification layer and leveling layer under the concrete of
foundations, mixed ratio of 1: 4: 1 or 8: 5:10 are usually used.
2) the plain concrete works for foundations and floors usually used by mixing 1: 3: 6, and take
into account the use of resisting cement to salts when the soil or groundwater conditions require
it.
3) reinforced concrete work for the ceilings and joists and lintels and stairs ..... etc using
common mixing ratio often 1: 2: 4 may be used ratio of 1: 1.5: 3 for columns.
4) Reinforced concrete works in contact with the water, such as ponds, reservoirs and retaining
walls for the water used blending ratio of 1: 1.5: 3 or 1: 1: 2 with the addition of water proof (
Sika ) to the mix and the use of the water stopper at the joints.
In order to estimate the quantities involved in the 1m3 of concrete the following approximate
equation can be used:
Vol. = 0.67 (C+S+G)
Vol. : Concrete volume after the addition of water to its components.
c : cement volume
s: sand volume
G: gravel volume
The number 0.67 refers to the contraction in the volume of concrete components after adding
water to the mix and this contraction is one-third the size almost (0.33). Accordingly, the net
volume after the contraction is two-thirds of the total volume or approximately 0.67 of the total
volume before the water adding.
83
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
To obtained one cubic meter of concrete mix (1: 2: 4), cement, sand and gravel volume can be
estimated the as follows:
1 = 0.67(C+2C+4C)
(Cement volume) C = 0.21 m3
(Sand volume) S = 2C = 0.42 m3
(Gravel volume ) G = 4C = 0.84 m3
Cement density=1400 kg/m3
Example 5:
Estimate the amount of construction materials (cement, sand, gravel) needed to pour the
foundation of the two room in Example 2 by mixing 1: 2: 4 and on the assumption that the
thickness of the foundation is 40cm.
Vol. = 27.8*0.6*0.4 = 6.672 m3
Construction material quantities of (1:2:4) as follow
Cement quantity = 300 x 6.672 =2001.6 kg say = 2 ton
Sand = 0.42 x 6.672 = 2.8 m3 say = 3 m3
Gravel= 0.84 x 6.672 = 5.6 m3
Example 6:
Estimate the amount in tons of cement, gravel and sand in cubic meters needed to pour 30
columns of height 4.5 m. note that the hexagonal rib 30cm length of the column section, and the
mixing ratio of 1: 1.5: 3
.
Solution:
3
Vol. N 6 a2 h
4
3
Vol. 30 6 0.32 4.5 = 31.567 m3
4
31.567 = 0.67(C+1.5C+3C)
C=8.567 m3
8.567 1400
Cement = =11.99 ton
1000
Sand = 1.5C = 1.5*8.567 = 12.85 m3
Gravel = 3C = 3*8.567 = 25.69 m3
84
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example 7:
Estimate the required quantities of construction materials for lining the channel as shown bellow,
by sectional concrete layer thickness of 30cm, note that the length of the channel 3km and mixing
ratio of concrete is ( 1: 2: 4).
Solution:
A 3 1* 2 2 * 4.5 2 1.5 2 * 0.3 4.346 m 2 Vol. = 4.346*3000 = 13038 m3
Construction material quantities of (1:2:4) as follow
Cement quantity = 300 x 13038 =3,911,400 kg = 3,911.4 ton
Sand = 0.42 x 13038 = 5476 m3
Gravel= 0.84 x 13038 = 10952 m3
Example 8:
the Figure (A) Represents a section of a concrete dam and a small figure (B) Drop the dam at the
construction site, Estimate necessary required constructing materials for the implementation of the
dam using concrete mixing ratio of 1: 2: 4.
85
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
*102
A 16 * 2 132 122.46 m 2
4
A x ax
*102
122.46 x 16 * 2 * 8 132 * 8.5 * 0.424 *10 2
4
x 9.819 m
60 *
Vol. S * * A 20 9.819 * *12246 3823.983 m3
180
3823.983* 300
cement 1147.194 ton
1000
sand 3823.983* 0.42 1606m3
gravel 3823.983* 0.84 3212m3
Example 9:
Solution:
2 .6 1 .2
A 7 * 1 .5 * 5.5 1.2 * 1 22.15 m 2
2
Vol. 22.15 * 22 487.3 m3
487.3 0.67C 1.5C 3C , C 132.239 m3
132.239 * 1400
cement 185.134ton
1000
sand 1.5C 198.3 m3
gravel 3C 396.7 m3
86
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Resolve example 9 but considering that the retaining wall curved central angle of 60 ° and its
head is 25 m away from the point a.
Example 11:
Estimate the quantity of construction materials ( cement, sand and gravel) needed to pour ten
bases for four-column, note that the base pyramid-shaped four-minus the side length of the
upper base 60 cm and 120 cm, and the lower net height of 120 cm and the blending ratio of 1:
2: 4.
Solution:
H
Vol. 10 *
3
A1 A2 A1 * A2 10 *
1. 2
3
0.62 1.22 0.62 * 1.22 10.08 m3
300
cement 10.08 * 3.024ton
1000
sand 0.5 * 10.08 5.04 m3
gravel 1 * 10.08 10.08 m3
87
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Reinforced concrete: is a reinforced concrete materials that are indispensable in any structural
work, reinforcement is added to the concrete due to the lack of concrete in tension as well as to
increase compressive strength in compression zone under pressure, reinforcement is of enormous
importance because it is the most expensive construction paragraphs, and below details of the
reinforcement:
6 0.222
8 0.395 Stirrups
10 0.617
12 0.888 ----
14 1.21 ----
16 1.58 ----
18 2 For huge
20 2.47 constructions,
Dams for
25 3.86
example
Example 12)
How many tons of block 1000 rebar (Φ8) and 2000 rebar (Φ14) If you know that the length of the
one rebar is 12 m.
Solution:
mass of 1000 rebar (Φ8), 12 M length = 0.395 * 12*1000/1000 = 4.74 ton
mass of 2000 rebar (Φ14), 12 M length = 1.21 * 12*2000/1000 = 29.04 ton
Example 13)
How much the mass of reinforcement have length of 12 m & diameter of 30 mm if you know that
a 8 mm diameter rebar density is 0.395 kg / m.
Solution:
88
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
w2 w1 0.395 x
x 66.66kg
v2 v1 2
Estimating of rebar
2
* 8 *1 * 30 *12
4 4
quantities of strip foundation:
rebar must be in general:
1) free of rust and suspended solids and materials that prevent bonding with concrete such as
oils and others.
2) heat may not be used when bending rebars, particularly in the large diameters.
When taking the cross-section in a strip foundation, it would be as follows:
So notes form the figure that reinforcement is usually in a range of rebar and stirrups, In the case
of insufficient length overlap (overlap) work must be done, including, if necessary, and be a
correlation length of (25-40db ) that at least a length of 300 mm, as the db is a (diameter of bar),
and with respect to the stirrups it is observed from the figure they contain extensions and bending
and the length of each extension (6db) and that at least this extension about 10 cm, and all
bending of ( 2db). And it is usually connected using rebar steel wires to be binding in all rebar
connecting location. It is worth mentioning, the number of stirrups is as follows:
89
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
For the purpose of rebar mass estimation the following approximate equation can be adopted:
lD2
w where: w: rebar mass (kg), l: length of rebar (m), D: rebar diameter(mm)
162
This equation can be derived as follows:
D
2
lD2
w Vol. * s l * 7850 Where: s : rebar density (7850 kg / m3)
4 100`0 162
Example 14) Estimate the amount of construction materials needed to pour 40 m3 of the strip
foundation its cross-section shown in the figure below: If you know that the mixing ratio of 1: 2:
4.
Solution:
40 * 300
Cement = = 12 ton
1000
Sand = 40*0.42 = 16.8 m3
Gravel = 40*0.84 = 33.6 m3
Vol . 40
Foundation length= = =100 m
Area 1 * 0.4
100
No .of overlaps 8.33 8 Nearly to the nearest and smaller integer
12
91
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Extension + Bending
91
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
27.8
No.of overlaps 2.3 2
12
1 l1 27.8 2 * 0.56 28.92m, L1 3l1 3 * 28.4 86.76m
L1D12 86.76 *142
w1 104.97kg
162 162
2 l2 l1 28.76m, L2 2l2 2 * 28.76 57.52m
L2 D22 56.8 *122
w2 51.13kg
162 162
3 l3 20.6 2 * 0.05 0.4 2 * 0.05 0.3 1.9m
27.8
No. of stirrups 1 112.2 113 L3 113*1.9 214.7 m
0.25
L D 2 214.7 *102
w3 3 3 132.53kg
162 162
Wt w1 w2 w3 288.62kg
Example 16) Estimate the quantity of construction materials required to pour the foundation
outlined plan in the figure below: if w/c =0.45
92
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
L3 D32 918*102
w3 566.67kg
162 162
Wt w1 w2 w3 1592.92kg
Example 17) Estimate the quantities of construction materials required for pouring the foundation
outlined his plan in the figure below:
93
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Raft Foundation
Using the raft foundation when the weights on the columns are big and the soil bearing is weak,
the required foundations area to be over half the area of the original construction, and this
foundation is usually in the form of a mattress reinforced concrete of one thickness, preferred to
be reinforced with two layers of bars at the top and bottom, and linked to a set of columns
Concrete foundations for this through a series of reinforcing bars called dowels, and the mat
foundation section generally as follows:
l = overlap + H – cover + 4db + 12db = 40db + 4db + 12db + H – cover = 56db + H – cover
notes that the foundation rebar contain extension and right angle therefore an extension of (16db
for the both sides is added) this mean an adding of (32db) to the length of foundation rebar.
It also taking into consideration an addition of the dowel overlap to the foundation rebar.
Example 18) Estimate the volume of excavation and the quantity of necessary construction
materials to pour the foundation which is described in the following graph and water cement ratio
of 0.45:
94
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution)
1st. Single footing rebar calculation
2.5-2*0.075=2.35m
2.35
No. of bars 1 8.83 9
0.3
l1 2.35 32db 2.35 32 * 0.016 2.862m, L1 2.862 * 9 * 2 51.516m
L1D12 51.516 *162
w1 2 * 2* 162.816kg
162 162
l2 56db H cov er 56 * 0.025 0.45 0.075 1.775m, L2 4 *1.775 7.1m
L2 D22 7.1* 252
w2 2 * 2* 27.39kg
162 162
2nd. Raft foundation rebar calculation
30-2*0.075=29.85m long direction
10-2*0.075=9.85m short direction
No. of bars (30 m length) = (29.85/0.3)+1=100.5=101
No. of bars (10 m length) = (9.85/0.3)+1=33.83=34
No. of overlaps (30 m length)=29.85/12=2.4=2
l3 =29.85+32db+2*0.64=29.85+32*0.025+1.28=31.93m, L3=31.93*34*2=2,171m
95
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
l4 =9.85+32db=9.85+32*0.025=10.65m, L4=10.65*101*2=2151.3m
l5 =56db+H-cover=56*0.025+0.45-0.075=1.775m, L5=8*1.775=14.2m
Vol.=(30*10+2.5*2.5*2)*0.45=140.625m3
140.625=0.67(C+4C+8C)
C=16.15m3
Cement=22.6 ton, Sand=64.58 m3, Gravel=129.16 m3
w/16.15=0.45 , w =16.15 * 0.45=7.27 m3=7270 liter
96
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Stone construction is relatively slow and requires large quantity of cement mortar as well a skilled
worker and be costly in terms of transportation, but it is a relatively cheap material constructions.
Stone is up to diameters (10-35) cm.
The voids size in the stone construction is up to (25-30)% of the total volume of construction.
size cement mortar volume in 1.0 m3 of stone construction is (0.25-0.3) m 3.
2-Brick wall
The bricks are relatively normal good building material because it is a good insulator of heat and
relatively cheap prices in the central and southern regions of Iraq, but the only drawback is the
slow work.
Standard dimensions of the bricks are (23 * 11 * 7) cm, it may be produced in other
dimensions.
thickness of the cement mortar 1 cm.
brick dimensions after construction become cm (8 * 12 * 24).
The number of bricks at 13:00 3 of construction = 435 brick.
The number 435 brick is a theoretical figure the number that take the guesswork out if
taking into account the amount of bricks that damage transport time or breaks in the
course of work is 440 brick could reach 450.
for the estimation purpose the amount of mortar cement at 1 m3 of construction bricks do
the following :
The size of the actual bricks at 1 m3 435 brick
3
For the estimation purpose the amount of cement mortar at 1m of the brick construction
do the following:
the actual size of the bricks in 1m3 = 435 * 0.23 * 0.11 * 0.07 = 0.77 m 3
size cement mortar = 1 - 0.77 = 0.23 m3.
building bricks need to (1 qualified labor +4 worker) and be the productivity is up to (3-5)
m3 / day.
97
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The number 435 is the theoretical brick number. The number increase to 440 or 450 brick
if taking into consideration the amount of bricks that damage during transport time or
breaks in the action.
Example 19)
In Example 2 suppose that wall thickness the bellow DPC is 0.4 m and a height of 0.6 m,
and1:3 cement mortar mixing proportion, estimate:
1) the required amount of stone, cement and sand for the wall bellow DPC, if you know that the
size of the voids is 25% of the volume of construction.
2) the amount of bricks and cement needed for wall bellow DPC.
3) the amount of the block, cement and sand needed for wall bellow DPC.
Solution:
the wall total length = total lengths of the centre - = 9.4 * 2 +3.2 * 3 -(1/2)* 2 *
0.4 = 28 m
wall volume = 28 * 0.4 * 0.6 = 6.72 m 3
1) ratio blanks 25% , amount of stone 75% of the size of the wall
98
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
99
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
A damp-proof course (DPC) is a barrier through the structure by capillary action such as through
a phenomenon known as rising damp. Rising damp is the effect of water rising from the ground
into your property. The damp proof course may be horizontal or vertical
it is a concrete pouring by mixing ratio of (1: 2: 4). the use of cement salts -resistant with CICA
or similar sealants moisture and to be mixed with concrete according to the manufacturer
instructions,
DPC Benefits representing in adjusting the levels of construction. The thickness of the moisture
barrier is usually up to 10 cm and preferably higher than the floor level by 6-15 cm above G.L.,
calculated m length or m3.
Example 20) Estimate the amount of necessary construction materials to cast DPC of Example 2.
Solution: DPC length = total lengths of the centre - = 9.4 * 2 +3.2 * 3 -(1/2)* 2 *
0.2 = 28.2 m
net DPC length=28.2-2=26.2 m (by subtracting the doors distances)
Vol. = 26.2 * 0.1 * 0.2 = 0.524m3
Cement = 0.524 * 6 = 3.384 bag
Sand = 0.524 * 0.43 = 0.23 m3
Gravel = 0.524 * 0.86 = 0.45 m3
111
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
A) If the thickness of the partition wall of 11 cm the exposed face of the brick is nominally
8 cm x 24 cm, therefore
Number of bricks in the definitive area of one square meter 52.08 brick
53 brick can be used for the purposes of estimating, the adoption of 60 brick per 1 m 2 of the
partition, but to estimate the volume of the cement mortar shall be as follows:3
The size of mortar = partition volume - the size of the actual bricks = 1 * 0.11 - 53 * 0.07 *
0.11 * 0.23 = 0.016137 m 3
b) If the thickness of the partition wall of 7 cm the exposed face of the brick is nominally
12 cm x 24 cm, therefore
Number of bricks in the definitive area of one square meter 34.7 brick
35 brick can be used for the purposes of estimating the adoption of 40 brick per 1 m 2 of the
partition, but to estimate the volume of the cement mortar shall be as follows:
The size of mortar = partition volume - the size of the actual bricks = 1 * 0.07 - 35 * 0.07 *
0.11 * 0.23 = 0.008015 m 3
The blocks are a concrete mixture by mixing ratio of ( 1: 2: 4) on a parallel form of rectangles
and a surface rough to help adhesion mortar cement the different aspects, and be either solid or
hollow, and the second type is the best since the weight lighter and isolate sound and heat Best.
In general they are usually two method of constructing concrete block walls:
111
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
The first method: build the walls of a thickness of 20 cm and in this case, the face of the
apparent, block is 16 cm x 41 cm and therefore the number of blocks needed to build a wall area
1
of 1 m 2 is = 15.2 say=16 block. It is worth noting that this kind of construction is
0.41* 0.16
the most common method. To estimate the volume of the cement mortar: Mortar size = wall size
- the size of the actual block = 0.2 * 1-16 * 0.4 * 0.2 * 0.15 = 0.008 m 3
The second method: build the walls of a thickness of 15 cm and in this case, the face of the
apparent, block is 21 cm x 41 cm and therefore the number of blocks needed to build a wall area
1
of 1 m 2 is = =11.6 say= 12 block.
0.41* 0.21
To estimate the size of the cement mortar: volume of mortar = wall size - the size of the actual
block = 0.15 * 1-12 * 0.4 * 0.2 * 0.15 = 0.006 m 3
Note: if the conduct proportion between the wall and the volume in the first or second method the
volume of 1 m3 of concrete block wall conducted by 80 block per 1 m3 of the wall in both the first
and second method.
Example 21) Estimate the amount of the block, cement and sand needed to build the walls of the
two room in Example 2 by using cement mortar mixture ratio of 1:2 and at 2.5 m height, if you
know that every room has a door with dimensions of 2.5 m * 1.0 m and a window dimensions of
1.5 m * 2.5 m.
Solution:
Along the walls = sum of the lengths of the centers - ½ x (N) * width of the wall = 9.4 * 2 + 3.2
* 3 - ½ * 2 * 0.2 = 28.2 m
wall volume = 28.2 * 0.2 * 2.5 = 14.1 m3
size doors and windows = 2 * 0.2 * (1 * 2.5 +1.5 * 2.5) = 2.5 m 3
volume of net construction = 14.1-2.5 = 11.6 m 3 blocks = 80 * 11.6 = 928 block
mortar volume = volume of construction net - the actual size of the block = 11.6 - 928 * 0.4 *
0.2 * 0.15 = 0.464 m 3
0.464=0.75(C+2C)
112
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
B-Column
form work = column circumference * height
B-Slab
w
form work = w * l l
113
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
slab = 4 * 3 + 5 * 3 = 27
Beam (inside) = {(4 + 3) * 2 + (5 + 3) * 2} * 0.5 = 15 m2
Beam (outside) = (9.6+3.4) * 2 * 0.5 = 13 m2
Extended slab = 10.6 * 4.4 - 6.9 * 3.4 = 14 m2
water proof (outside) = (10.6 +4.4) * 2 * 0.4 = 12 m2
water proof (inside) = ( 10.2 + 4) * 2 * 0.25 * = 7.1 m 2
openings (over doors and windows) = 1 * 0.2 * 2 +2.5 * 0.2 * 2 = 1.4 m 2
formwork = 89.5 m 2
Example 23) The figure bellow shows the scheme to store with a height 0f 5 m from the inside,
Estimate the required formwork for the roof, beams and columns.
114
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Solution:
beams from the inside = [(12 + 7.4) + (12 + 8) + (7.4 + 7.4) + (7.4 + 8 )] * 2 * 0.5 = 69.6 m 2
columns = 0.4 * 4 * 5 * 9 = 72 m2
formwork = 508.04 m 2
columns small corners area is very few thus, it has been neglected
Example 24) Estimate amounts of construction materials (cement, sand, gravel, rebar) needed to
pour beams and the roof of the two rooms in Example 2, note that the reinforcement detail shown
115
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
in section (A) is for the slab and section (B)shows the beam detail reinforcement.
116
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Cement = 11.276 * = 3.3828 tons , Sand = 11.276 * 0.5 = 5.638 m3 , Gravel = 11.276
* 1 = 11.276 m3
4.36
No .of bars 1 11.9 12
0.4
l1 10.6 2 * 0.02 32db 10.56 32 * 0.012 10.944m
L1 12l1 12 * 10.944 131.328m
L1 D12 131.328* 122
w1 116.736kg
162 162
offset reinforcement:
5 m distance
2=0.5-0.02+2x0.2+2x[(5/4)-
0.11+0.16]+(5/2)+0.3x4
2=7.18m
L2=12 2=12*7.18=86.16m
117
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
9=28.2-10*0.04=27.8m
L7=4*27.8+896*0.012=121.952m
L7 D12 121.952 * 12 2
w7 108.402 kg
162 162
118
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Stirrups calculation
27.8
No .of stirrups 1 93.6 94
0. 3
l10 0.65 2 * 0.04 0.2 2 * 0.04* 2 0.3 1.68m
L8 94l10 94 * 1.68 157.92m
L8 D22 157.92 * 102
w8 97.48kg
162 162
Offset rebar beam calculation (B1 )
10-Finishing work
1- Cement plastering (m2)
The cement mortar plastering external walls are usually in the sequence of the following
specifications:
1) Clean the walls of dust and suspended solids and crystallized salts formed on the surface if the
building bricks.
2) is sprayed with water for well saturating the face of the wall.
3) Spraying the wall by cement and coarse sand by mixing 1: 1 (cement slurry) and applied in
liquid that covers the wall face to be sprinkled in the second and third days with water. This class
119
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
clog the voids of brick and block the transmission of salt to the cement plastering and be a strong
foundation for the next layer and help to absorb moisture and water from the face of the brick.
To estimate cement plastering materials for 1 m2 we suppose that the cement plastering thickness
is 2 cm and using cement mortar (1:3).
Vol. = 1*0.02=0.02m2
0.02 = 0.75(C+3C) C = 0.0067m3
Cement = 0.0067*1400 = 9.33 kg
Sand = 3C = 0.02 m3
2- Gypsum plastering (m2)
The interior walls and ceilings are usually plastered using gypsum after cleaning walls of dirt and
suspended solids, then start install rulers on the wall by whiting and weighted accurately to the
desire thickness to be the first gypsum layer, and after the cohesion of the first layer, a second
layer is placed and which is thick 6 mm and that ends the wall vertically and horizontally the
ceiling, and finally the last layer placed of a thickness of 2 mm to make the smooth face.
to estimate the required gypsum for 1 m2 we suppose that the total gypsum plastering layer is 2
cm. therefore the volume of required gypsum for 1 m2 calculated as bellow:
Vol. = 1*0.02 = 0.02m3
By considering the gypsum density is 1275 kg/m3 and loss 10% of volume after adding water to
the gypsum. Therefore, gypsum weight in 1 m2 is calculated as follow:
111
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
floor tile is a concrete material to cover the floors and surfaces as well as on the stairs and in the
lower window sills, and can be used for the tiles in a skirting the rooms and halls. It is used in the
application mortar cement after placing a mortar of sand and cement above the ground to allow
tiles free movement resulting from the expansion and cement mortar mixing ratio of 1: 3 that the
strong mortar be any water cement ratio of the few in order to ensure that tiles move because of
the weight. The thickness rate of mortar application of 2 cm, and the joints that are left between
tiles and ranges between 2-4mm.
For the purposes of the estimation average joint thickness considered 3 mm from all sides, and
after the completion of the application of tiles joints are filled with mortar of cement only semi-
liquid.
tile dimension could be (20x20)cm, (25x25)cm or (30x30)cm
To calculate the number of tiles in 1m2 we suppose the tile dimension after the application is
(30.3 x 30.3)cm where 0.3 represent 3 mm joint thickness.
Note
* Tile thickness is 3 cm and mortar thick is 2 cm therefore, the total thickness is 5cm.
* Added water to the tile cement mortar is very little and therefore, the cement mortar will loss
15% of its volume due to added water.
* Cement mortar amount of joints could be estimated by subtracting the tile number area from the
total area then multiplied by the thickness of the tile.
joints cement mortar volume=(1-0.3 x0.3 x 11) x0.03=0.003 m3
4-Skirting (m.l)
It can be worked by putting half tile around the walls to be the internal surface equality surface
with the gypsum plastering above it, and the newly available in the local markets can be used
instead of cut tiles. Skirt dimensions available on the market vary, but the most common
dimensions are 50cm * 13cm * 0.6cm and application of skirting is by using mortar cement by
mixing 1: 3. To find the number of pieces required for skirting, the parameter of the room divided
by the opted skirting length.
111
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
6-Painting (m 2):
Painting walls usually used for two main reasons: first, to maintain the walls from the weather and,
secondly, to give parallax or color desirable for walls and ceilings, and others. There are several
types of painting fit each particular purpose, including: • Dye fatty: It is used to painting metal
doors, windows and walls used in wet area.
• aqueous pigment (Amolshin): used to paint the interior and exterior walls and preferably used in
dry areas.
The amount of the dye that gives a certain number of square meters depending on the type of
pigment and the different surface roughness required dye vary, the following table shows the
surface area covered by one gallon of different types of dyes:
112
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
1 gallons 4 liter
The imperial (UK) gallon =4.54609 litres ( English gallon = 4.54609 liter )
1 US gallon = 3.78541 liters
1. cleans well the surface of the dust and the remains of construction materials,
3. Laying two layers of a thick felt that classes interfere with each including at least 10 cm and
are affixed by asphalt well.
4. Spreading another layer of asphalt thick (0.75 - 0.85) cm reverse first layer.
5. Laying a clean layer of soft soil free of( dirt, salt, stones and exotic materials) and have
thickness at least 7 cm at the gutters, and a decline at a rate of 1.5cm / m.
6. Appling a concrete tiles which dimensions (0.8 x 0.8 x 0.04 m) and fill the joints that have a
thickness of 2 cm using asphaltic fillers.
In the case of using tiles normal working joints are for the purpose of expansion is also up to 2
cm and fill with asphaltic fillers and are made every 15 m 2, other than those joints that leave
between tiles and other, which are 3 mm thick.
quantities estimated are as follows:
113
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example 25) Estimate amounts of construction materials required for the finishing items in
Example 2 according to the following specifications:
1. applying cement slurry at interior and exterior walls and ceilings and parapets with cement
mortar 1: 1 with an average thickness of 0.5 cm.
2. plastering exterior walls and parapets using cement mortar 1: 3.
3. tiling inner walls of the room (4*3) using laser ceramic (60*30*0.9cm) and at height of only
120 cm from the bottom and applying a laser belt (30*8*0.9 cm).
4. Skirting room (5 * 3)m using (50 * 13 * 0.6 cm)skirting tiles.
5. gypsum plastering the rest of the interior walls and ceiling.
6. Applying floors with mosaic tiles (30 * 30 * 3) cm.
The solution:
1-Cement slurry
Slabs = 4*3+5*3 =27m2 (+)
Internal walls = {(4+3)*2+(5+3)*2}*3 =90m2 (+)
Exterior walls = (9.6+3.4)*2*3 =78m2 (+)
Extended slab = (10.6*4.4)-(9.6*3.4) =14m2 (+)
Head wall (outside)= (10.6+4.4)*2*0.4 =12m2 (+)
Head wall (inside)= (10.2+4)*2*0.25 =7.1m2 (+)
Head wall (parameter)= (10.6*4.4)-(10.2*4) =5.84m2 (+)
Openings= 1*2.5*2*2+1.5*2.5*2*2 =25m2 (-)
total = 208.94 m2
Vol. = 208.94*0.005=1.0447m3
1.0447=0.75(C+C) C=0.696m3
Cement = 975 kg
Sand = 0.696 m3
114
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
2-Cement plastering
External wall + extended slab + head wall= 78 + 14 + (12+7.1+5.84)=116.94 m2 (+)
opening = 1*2.5*2 + 1.5*2.5*2 = 12.5 m2 (-)
104.44 m2
Vol. = 104.44*0.02=2.0888 m3
2.0888 = 0.75(C+3C) C=0.696 m3
Cement = 0.696*1400 = 975kg
Sand = 3C = 2.0888 m3
3-Ceramic tiles
Walls = (4+3)*2*1.2 = 16.8 m2 (+)
Door = 1*1.2 = 1.2 m2 (-) 15.1 m2
Window = (1.2-1)*2.5 = 0.5 m2 (-)
Joint thickness= 1 mm and ceramic tile dimension is (60.1x30.1x0.9)cm
covered area 15.1
Ceramic tiles pieces no. = = 83.47 84 قطعة
one tile area 0.301* 0.601
Ceramic belt length = (4+3)*2 – 1(Door) – 2.5(window) =10.5 m
10.5
Ceramic belt pieces no. = = 34.88 35 pieces
0.301
Ceramic total area = Ceramic area + belt area= 15.1+10.5*0.08=15.94m2
AS the gypsum thickness=2cm
Cement mortar thick=2-0.9=1.1cm=0.011m
Cement mortar volume = 15.94*0.011=0.17534 m3
0.17534 = 0.75(C+3C) C = 0.058m3
Cement = 0.058*1400 = 81.83 kg
Sand = 3C = 0.17534m3
Joint cement mortar = {(0.6+0.3)*0.001*84+(0.3+0.08)*0.001*35}*0.009=8.001*10 -4m3
8.001*10-4=0.75C C=10.668*10-4m3
White Cement = 10.668*10-4*1400=1.5kg
4-Skirting:
Skirting length = (5+3)*2-1=17m
115
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
17
Skirting pieces no.= 33.7 34 Pieces
0.503
Joint thick assumed to be 3 mm
AS skirting tile thick is 0.6 thus, cement mortar thick=2-0.6=1.4cm
Cement mortar volume=17*0.13*0.014=0.03064 m3
0.03094=0.75(C+2C) C=0.0103m3
Cement=14.44kg
Sand=0.03094m3
Joint cement mortar volume={34*0.003*(0.5+0.13)}*0.006=3.8556*10-4 m3
3.8556*10-4=0.75C C=5.1408*10-4m3
White cement=0.719712kg
5- Gypsum plastering
Internal walls= (5+3)*2*3+(4+3)*2*3 = 90m2 (+)
Slab = 4*3+5*3 = 27m2 (+)
Ceramic tiles = 15.94m2 (-) = 86.35m2
Skirting = 17*0.13 = 2.21m2 (-)
Doors and Windows = (1*2.5+1.5*2.5)*2 = 12.5m2 (-)
Gypsum volume= 86.35*0.02 = 1.727m3
Gypsum amount = 1.727*1275*1.1=2422.1175kg
6-Floor tiling
Floor area=3*5+3*4=27m2
Floor Area 27
Tile No, = = =294.1300 كاشية
One tile area 0.303* 0.303
Cement mortar = 27*0.02=0.54m3
0.54=0.85(C+3C) C=0.1588m3
Cement=222.35kg
Sand=0.476m3
Joint cement mortar volume= (27-294*0.3*0.3)*0.03=0.0162m3
0.0162=0.75C C=0.0216m3 White cement=0.0216*1400=30.24kg
Note: For all calculation which have done above for finishing items internal parameter for the
doors and windows might be added with thickness of 10 cm.
116
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
117
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
118
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example 26) Estimate the amount of construction materials (cement, sand, gravel, rebar)
required for implementing 10 m length for the earlier shown box culvert cross section.
Solution:
Triangle = + 0.5*(1.4*0.05)*2*10=
If we suppose that a concrete mixing ratio is (1:1.5:3) the quantities will be as follow :
36.4=0.67(C+1.5C+3C) , C=9.88m3
Cement = 13.83 ton, Sand = 14.82m3, Gravel = 29.63
119
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
121
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
B 8 2 * L 7.5 m
4 8 3.9 7.5
Vol . * 1.5 * 1.35 * 100 130.5 m
3
2 2
Cement 39.15ton , Sand 65.25m ,Gravel 130.5 m 3
3
121
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Rebar calculation:
9 8.4
Length= 8.7 m
2
100
space 100m , No . 1 335
0.3
l1 8.7 2 * 0.05 32db 2 * 4 db 9.24m , L1 9.24 * 335 * 2 6190.8 m
L1 D12 6190.8 * 16 2
w1 9782.99kg
162 162
100 8 .6
space 8.7 2 * 0.05 8.6 m , No .of oerlaps 8.3 8 , No . 1 36bars
12 0.25
l 2 100 8 * 0.3 102.4 m , L2 102.4 * 36 * 2 7372.8 m
L2 D22 7372.8 * 12 2
w2 6553.6 kg
162 162
w t 16336.59kg
122
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Example 27) The figure below shows the water tank is open from top, net internal
dimensions are (14 m * 35 m), its four walls reinforced symmetrically, Estimate amounts
of construction materials (cement, sand, gravel, iron) required for implementation the tank,
note that the mixing ratio of concrete is (1: 2: 4).
200 200
mm mm
14m
4.5 m
Ø16 @ 200
Ø16 @ 200 mm
mm Ø16 @ 300
Ø25 @ 350
mm
.3m mm 0.3 m
400 mm
400 mm
15 m
Ø16 @ 300 mm
The solution:
Vol.=15*36*0.4+{(14.4*35.4)-(14*35)}*4.5=304.92m3
Cement=91.476ton, Sand=152.46m3, Gravel=304.92m3
123
Kirkuk University Methods of Construction and Estimation Civil Engineering Stage:4
By: Lecturer (Yousif Salam Shwani) 2015-2016
Rebar calculation:
1- Rebar foundation
A-Main rebar
15
space 36 2 * 0.075 35.85m , No .of overlaps 1.25 1
12
35.85
l1 15 2 * 0.075 32db 1 * 0.3 15.95m , No . 1 104bars
0.35
L1 D12 3317.6 * 25 2
L1 15.95 * 104 * 2 3317.6 m , w1 12799.38kg
162 162
B-Secondary rebar
36
space 15 2 * 0.075 14.85 m , No .of overlaps 3
12
14.85
l 2 36 2 * 0.075 32db 3 * 0.3 37.262m , No . 1 51bars
0 .3
L D 2 3800.724 * 16 2
L2 37.262 * 51 * 2 3800.724m , w 2 2 2 6006.08kg
162 162
c-Dowels (Let's consider the total length is the sum of all parts)
98.8
space 35 * 2 14.4 * 2 98.8 m , No . 1 495bars
0.2
l 3 56db H cov er 56 * 0.016 0.4 0.075 1.221m
L3 D22 1208.79 * 16 2
L3 1.221* 495 * 2 1208.79m , w 3 1910.19kg
162 162
2- Rebar wall
A-Main rebar (vertical )
No . 495 bars, l 4 4.5 0.04 16db 4.716m
L4 D22 4668.84 * 16 2
L4 4.716 * 495 * 2 4668.84m , w4 7377.92kg
162 162
B-Secondary rebar (horizontal)
The wall length is considered straight with total length of 98.8m
98.8
space 4.5 0.04 4.46 m , No .of overlaps 8.2 8
12
4.46
l5 98.8 8 * 0.04 4 * 32db 8 * 0.3 102.416m , No . 1 19bars
0.25
L D 2 3891.808 * 12 2
L5 102.416 * 19 * 2 3891.808m , w5 5 3 3459.38kg
162 162
wt of ϕ12=3459.38kg, wt of ϕ16=15294.19kg, wt of ϕ25=12799.38kg, WT = 31552.95kg
124