Professional Documents
Culture Documents
BUS 214 Wing Yam Chu Final Assignment
BUS 214 Wing Yam Chu Final Assignment
Picture this: You’ve been working non-stop on a 4 month project with a budget
$4,000. Each month is expected to cost $1000
Then, you get a call from the client asking how far along you are with it. He
wants to know:
● Will you be able to deliver the project on time?
● How’s the actual cost looking like versus the budgeted cost?
● Will the project be completed within the budget?
2. After 3 months
WHATS THE PV: 75% x $4000 = $3000
2. You spent $2,500 after three months. All tasks scheduled for
completion up to this point have been completed.
Given:
● Project duration: 4 months
● Project budget (BAC): $4,000
● Elapsed time: 3 months
● Planned value: $3,000
● Actual cost: $2,500
● % complete (planned): 75%
● % complete (actual): 75%
EV = % complete (actual) x BAC
WHAT IS THE EV = 75% x $4000 = $3000