NOVEMBER 2023 1. Progress of Work (Up to 26 NOV 2023)
Plan Actual Deviation
Over All Progress 48.280 % 59.856 % + 11.576 % 2. Key Date Completion Trending 4. QA/QC : Non-Conformance Summary No. Description Finish Date in Monthly Trend Target date No Description Open Cancelled Close Total Progress 1. Civil Works 90.875 % Jan 2024 0 0 0 0 0
2. Steel Stucture Jan 2024
Works 5. Risk & Issue Fabrication 80 %
Installation 0%
3. Safety Statistic
DESCRIPTION PREVIOUS THIS MONTH TOTAL TO DATE
TOTAL Man-hour worked 17,734 250 17,984 Lost Time Incident 0 0 0 Reportable Accidents 0 0 0 Frequency Rate per 1,000,000 hour 0 0 0 Severity Rate per 1,000,000 man- 0 0 0 hour Medical Treatment Case 0 0 0 First Aid Case 0 0 0 Near Miss Aciident 0 0 0 6. Site LayOut Plan 7. Site LayOut Plan