PROJECT INFORMATION

Construction of HE- C401A


PT. ASAHIMAS CHEMICAL
Cilegon, Banten

NOVEMBER 2023
1. Progress of Work (Up to 26 NOV 2023)

Plan Actual Deviation


Over All
Progress 48.280 % 59.856 % + 11.576 %
2. Key Date Completion Trending 4. QA/QC : Non-Conformance Summary
No. Description Finish Date in Monthly Trend Target date No Description Open Cancelled Close Total
Progress
1. Civil Works 90.875 % Jan 2024 0 0 0 0 0

2. Steel Stucture Jan 2024


Works
5. Risk & Issue
Fabrication 80 %

Installation 0%

3. Safety Statistic

DESCRIPTION PREVIOUS THIS MONTH TOTAL TO DATE


TOTAL
Man-hour worked 17,734 250 17,984
Lost Time Incident 0 0 0
Reportable Accidents 0 0 0
Frequency Rate per 1,000,000 hour 0 0 0
Severity Rate per 1,000,000 man- 0 0 0
hour
Medical Treatment Case 0 0 0
First Aid Case 0 0 0
Near Miss Aciident 0 0 0
6. Site LayOut Plan
7. Site LayOut Plan

Foundation (Finish)

LC & Install Rebar


8. Progress Photos
8. Progress Photos
8. Progress Photos
9. Progress Photos ( Safety Activity )
THANK YOU