Part of the Floor Length (m) Width (m) Depth (m) Volume (m3)
Hallway 15.7 – 0.15 1.98 – 0.15 – 0.05 = 0.3 8.3037
= 15.55 1.78
Stairwell 3.5 + 0.05 – 0.05 = 2 – 0.15 – 0.05 0.3 1.89
3.5 = 1.8
Bedroom 1 2.25 – 0.05 – 0.05 = 2 – 0.15 – 0.05 0.3 1.161
2.15 = 1.8
Bathroom 1 2 – 0.05 – 0.15 1.25 – 0.05 – 0.05 = 0.3 0.621
= 1.8 1.15
Living Area 1 3.5 – 0.05 – 0.05 = 2.9 – 0.05 – 0.05 = 0.3 2.856
3.4 2.8
Bedroom 2 2.25 – 0.05 – 0.05 = 2 – 0.05 – 0.05 0.3 1.2255
2.15 = 1.9
Bathroom 2 2 – 0.05 – 0.05 1.25 – 0.05 – 0.05 = 0.3 0.6555
= 1.9 1.15
Living Area 2 3.5 – 0.05 – 0.05 = 2.9 – 0.05 – 0.05 = 0.3 2.856
3.4 2.8
Bedroom 3 2.25 – 0.05 – 0.05 = 2 – 0.05 – 0.05 0.3 1.2255
2.15 = 1.9
Bathroom 3 2 – 0.05 – 0.05 1.25 – 0.05 – 0.05 = 0.3 0.6555
= 1.9 1.15
Living Area 3 3.5 – 0.05 – 0.05 = 1.9 – 0.05 – 0.05 = 0.3 1.836
3.4 1.8
Service Area 2 – 0.05 – 0.15 2 – 0.05 – 0.15 0.3 0.972
= 1.8 = 1.8
Bathroom near 2 – 0.05 – 0.15 1.5 – 0.05 – 0.05 = 0.3 0.756
Service Area = 1.8 1.4
Kitchen + 2.9 + 6.9 – 0.05 – 3.5 – 0.05 – 0.15 = 0.3 9.603
Dining Area + 0.05 = 9.7 3.3
Living Area 4
Garage 3.9 – 0.05 3.5 – 0.05 – 0.15 = 0.3 3.8115
= 3.85 3.3
38.4282

Total Volume of Concrete = 38.4282 cubic meters


+ 10% allowance for wastage = 3.84282 cubic meters
Total Estimated Concrete Volume = 42.27102 cubic meters

CLASS A (1:2:4) Concrete Mix


42.27102 x 7.85 = 331.827507 or 332 Bags of Cement
42.27102 x 0.42 = 17.7538284 or 18 cubic meters of Sand
42.27102 x 0.84 = 35.5076568 or 36 cubic meters of Gravel

Estimated by : Hernandez, John Daryl R.