Professional Documents
Culture Documents
Procurement of Variable Frequency Drive (VFD) Training System
Procurement of Variable Frequency Drive (VFD) Training System
Procurement of GOODS
Sixth Edition
July 2020
Preface
These Philippine Bidding Documents (PBDs) for the procurement of Goods through
Competitive Bidding have been prepared by the Government of the Philippines for use by any
branch, constitutional commission or office, agency, department, bureau, office, or
instrumentality of the Government of the Philippines, National Government Agencies,
including Government-Owned and/or Controlled Corporations, Government Financing
Institutions, State Universities and Colleges, and Local Government Unit. The procedures and
practices presented in this document have been developed through broad experience, and are
for mandatory use in projects that are financed in whole or in part by the Government of the
Philippines or any foreign government/foreign or international financing institution in
accordance with the provisions of the 2016 revised Implementing Rules and Regulations of
Republic Act No. 9184.
The Bidding Documents shall clearly and adequately define, among others: (i) the
objectives, scope, and expected outputs and/or results of the proposed contract or Framework
Agreement, as the case may be; (ii) the eligibility requirements of Bidders; (iii) the expected
contract or Framework Agreement duration, the estimated quantity in the case of procurement
of goods, delivery schedule and/or time frame; and (iv) the obligations, duties, and/or functions
of the winning bidder.
Care should be taken to check the relevance of the provisions of the PBDs against the
requirements of the specific Goods to be procured. If duplication of a subject is inevitable in
other sections of the document prepared by the Procuring Entity, care must be exercised to
avoid contradictions between clauses dealing with the same matter.
Moreover, each section is prepared with notes intended only as information for the
Procuring Entity or the person drafting the Bidding Documents. They shall not be included in
the final documents. The following general directions should be observed when using the
documents:
a. All the documents listed in the Table of Contents are normally required for the
procurement of Goods. However, they should be adapted as necessary to the
circumstances of the particular Procurement Project.
b. Specific details, such as the “name of the Procuring Entity” and “address for
bid submission,” should be furnished in the Instructions to Bidders, Bid Data
Sheet, and Special Conditions of Contract. The final documents should contain
neither blank spaces nor options.
c. This Preface and the footnotes or notes in italics included in the Invitation to
Bid, Bid Data Sheet, General Conditions of Contract, Special Conditions of
Contract, Schedule of Requirements, and Specifications are not part of the text
of the final document, although they contain instructions that the Procuring
Entity should strictly follow.
1
d. The cover should be modified as required to identify the Bidding Documents as
to the Procurement Project, Project Identification Number, and Procuring
Entity, in addition to the date of issue.
f. For guidelines on the use of Bidding Forms and the procurement of Foreign-
Assisted Projects, these will be covered by a separate issuance of the
Government Procurement Policy Board.
2
Table of Contents
Bidding Documents – The documents issued by the Procuring Entity as the bases for bids,
furnishing all information necessary for a prospective bidder to prepare a bid for the Goods,
Infrastructure Projects, and/or Consulting Services required by the Procuring Entity. (2016
revised IRR, Section 5[e])
Consulting Services – Refer to services for Infrastructure Projects and other types of projects
or activities of the GOP requiring adequate external technical and professional expertise that
are beyond the capability and/or capacity of the GOP to undertake such as, but not limited to:
(i) advisory and review services; (ii) pre-investment or feasibility studies; (iii) design; (iv)
construction supervision; (v) management and related services; and (vi) other technical services
or special studies. (2016 revised IRR, Section 5[i])
Contract – Refers to the agreement entered into between the Procuring Entity and the Supplier
or Manufacturer or Distributor or Service Provider for procurement of Goods and Services;
Contractor for Procurement of Infrastructure Projects; or Consultant or Consulting Firm for
Procurement of Consulting Services; as the case may be, as recorded in the Contract Form
signed by the parties, including all attachments and appendices thereto and all documents
incorporated by reference therein.
4
CPI – Consumer Price Index.
DDP – Refers to the quoted price of the Goods, which means “delivered duty paid.”
EXW – Ex works.
Goods – Refer to all items, supplies, materials and general support services, except Consulting
Services and Infrastructure Projects, which may be needed in the transaction of public
businesses or in the pursuit of any government undertaking, project or activity, whether in the
nature of equipment, furniture, stationery, materials for construction, or personal property of
any kind, including non-personal or contractual services such as the repair and maintenance of
equipment and furniture, as well as trucking, hauling, janitorial, security, and related or
analogous services, as well as procurement of materials and supplies provided by the Procuring
Entity for such services. The term “related” or “analogous services” shall include, but is not
limited to, lease or purchase of office space, media advertisements, health maintenanceservices,
and other services essential to the operation of the Procuring Entity. (2016 revised IRR, Section
5[r])
5
communication facilities, civil works components of information technology projects,
irrigation, flood control and drainage, water supply, sanitation, sewerage and solid waste
management systems, shore protection, energy/power and electrification facilities, national
buildings, school buildings, hospital buildings, and other related construction projects of the
government. Also referred to as civil works or works. (2016 revised IRR, Section 5[u])
Supplier – refers to a citizen, or any corporate body or commercial company duly organized
and registered under the laws where it is established, habitually established in business and
engaged in the manufacture or sale of the merchandise or performance of the general services
covered by his bid. (Item 3.8 of GPPB Resolution No. 13-2019, dated 23 May 2019). Supplier
as used in these Bidding Documents may likewise refer to a distributor, manufacturer,
contractor, or consultant.
UN – United Nations.
6
Section I. Invitation to Bid
7
INVITATION TO BID FOR
Procurement of Variable Frequency Drive (VFD) Training System
1. The Batangas State University, through the PRE FY 2022 intends to apply the sum of One
Million Two Hundred Thousand Pesos only (Php1,200,000.00) being the Approved
Budget for the Contract (ABC) to payments under the contract for Procurement of
Variable Frequency Drive (VFD) Training System. Bids received in excess of the ABC
shall be automatically rejected at bid opening.
2. The Batangas State University now invites bids for Procurement of Variable
Frequency Drive (VFD) Training System. Delivery of the goods is required Fifteen
(15) calendar days upon receipt of the notice to proceed. Bidders should have completed,
within five (5) years from the date of submission and receipt of bids, a contract similar to
the Project. The description of an eligible bidder is contained in the Bidding Documents,
particularly, in Section II. Instructions to Bidders.
3. Bidding will be conducted through open competitive bidding procedures using a non-
discretionary “pass/fail” criterion as specified in the 2016 Revised Implementing Rulesand
Regulations (IRR) of Republic Act (RA) 9184, otherwise known as the “Government
Procurement Reform Act”.
5. The Batangas State University will hold a Pre-Bid Conference on March 10, 2023; 1:00
PM at Bids and Awards Committee (BAC) Office, Third Floor CEAFA Building, Batangas
State University, Alangilan, Batangas City. The Pre-bid conference shall be done
through Zoom Video Conferencing or other video conferencing applications which
shall be announced prior to the pre-bid conference. To facilitate online meeting
requirements, prospective bidders must communicate before theschedule his/her intention
to participate/attend the pre-bid conference. Upon receipt of the communication, the
secretariat shall send an online meeting link.
8
6. Bids must be duly received by the BAC Secretariat at the address below until 1:00 PM of
March 22, 2023. All Bids must be accompanied by a bid security in any of the acceptable
forms and in the amount stated in ITB Clause 18.
All bids shall be submitted only through registered mail or private courier. No bid shall be
submitted personally.
All bidders who submitted their bids must notify the BAC through email, telephone, and
cellphone calls, and text messaging to confirm that they have sent their bids and all
documents relative thereto. In the email, the bidder must attach the proof of sendingof the
said documents (i.e. actual photo of the envelopes and the official receipt issuedby the post
office or by the courier).
The bidders must assure that their bids shall be forwarded by the courier to the University
on the date and time of the bid opening. The bidders have the responsibilityto track their
documents with the courier. The date of receipt of bids shall be the date of sending of
documents, provided that the documents are actually received by the Secretariat. The BAC
shall bear no responsibility whatsoever for the delay that the courier may have caused. Bids
sent and/or received after the deadline shall be disqualified.
Bid opening shall be on March 22, 2023; 1:00 PM at Bids and Awards Committee (BAC)
Office, Third Floor CEAFA Building, Batangas State University, Alangilan, Batangas
City. The opening and preliminary evaluation of the bids shall be done in front of the
bidders and BAC members through video conferencing. Should any of the bid/s fail, the
notice shall immediately be sent to the email of the bidder concerned on the same
proceeding. Bidders must acknowledge the receipt of the same. The physical copy of the
notice shall be sent to the bidder through registered mail. Nevertheless, notices electronically
transmitted or transmitted through facsimile are deemed served.
7. The Batangas State University reserves the right to reject any and all bids, declare a
failure of bidding, or not award the contract at any time prior to contract award in
accordance with Section 41 of RA 9184 and its IRR, without thereby incurring any
liability to the affected bidder or bidders.
9
Section II. Instructions to Bidders
10
1. Scope of Bid
The Procuring Entity, Batangas State University wishes to receive Bids for the
Procurement of Variable Frequency Drive (VFD) Training System with
identification number Alangilan Project No. 2023-13.
2. Funding Information
2.1. The GOP through the source of funding as indicated below for PRE FY 2022 in
the amount One Million Two Hundred Thousand Pesos only
(Php1,200,000.00).
3. Bidding Requirements
The Bidding for the Project shall be governed by all the provisions of RA No. 9184 and
its 2016 revised IRR, including its Generic Procurement Manuals and associated
policies, rules and regulations as the primary source thereof, while the herein clauses
shall serve as the secondary source thereof.
Any amendments made to the IRR and other GPPB issuances shall be applicable only
to the ongoing posting, advertisement, or IB by the BAC through the issuance of a
supplemental or bid bulletin.
The Bidder, by the act of submitting its Bid, shall be deemed to have verified and
accepted the general requirements of this Project, including other factors that may affect
the cost, duration and execution or implementation of the contract, project, or work and
examine all instructions, forms, terms, and project requirements in the Bidding
Documents.
11
5. Eligible Bidders
5.1. Only Bids of Bidders found to be legally, technically, and financially capable
will be evaluated.
5.2. Foreign ownership exceeding those allowed under the rules may participate
pursuant to:
i. When Treaty or International or Executive Agreement as
provided in Section 5 of the RA 9184 and its 2016 revised IRR
allow foreign bidders to participate;
iii. When the Goods sought to be procured are not available from
local suppliers; or
5.3. Pursuant to Section 23.4.1.3 of the 2016 revised IRR of RA No.9184, the Bidder
shall have an SLCC that is at least one (1) contract similar to the Project the
value of which, adjusted to current prices using the PSA’s CPI, must be at least
equivalent to:
5.4. The Bidders shall comply with the eligibility criteria under Section 23.4.1 of the
2016 IRR of RA No. 9184.
6. Origin of Goods
There is no restriction on the origin of goods other than those prohibited by a decision
of the UN Security Council taken under Chapter VII of the Charter of the UN, subject
to Domestic Preference requirements under ITB Clause 18.
7. Subcontracts
The Procuring entity has prescribed that subcontracting is not allowed.
8. Pre-Bid Conference
The Procuring Entity will hold a pre-bid conference for this Project on the specified
date and time and either at its physical address Bids and Awards Committee (BAC)
12
Office, Third Floor, CEAFA Building, Batangas State University Alangilan, Batangas
City through videoconferencing as indicated in paragraph 6 of the IB.
10.2. The Bidder’s SLCC as indicated in ITB Clause 5.3 should have been completed
within five (5) years prior to the deadline for the submission and receipt of bids.
10.3. If the eligibility requirements or statements, the bids, and all other documents
for submission to the BAC are in foreign language other than English, it must
be accompanied by a translation in English, which shall be authenticated by the
appropriate Philippine foreign service establishment, post, or the equivalent
office having jurisdiction over the foreign bidder’s affairs in the Philippines.
Similar to the required authentication above, for Contracting Parties to the
Apostille Convention, only the translated documents shall be authenticated
through an apostille pursuant to GPPB Resolution No. 13-2019 dated 23 May
2019. The English translation shall govern, for purposes of interpretation of the
bid.
11.3. Any bid exceeding the ABC indicated in paragraph 1 of the IB shall not be
accepted.
13
12. Bid Prices
12.1. Prices indicated on the Price Schedule shall be entered separately in the
following manner:
ii. The cost of all customs duties and sales and other taxes already
paid or payable;
i. Unless otherwise stated in the BDS, the price of the Goods shall be
quoted delivered duty paid (DDP) with the place of destination in
the Philippines as specified in the BDS. In quoting the price, the
Bidder shall be free to use transportation through carriers
registered in any eligible country. Similarly, the Bidder may obtain
insurance services from any eligible source country.
Philippine Pesos.
1
In the case of Framework Agreement, the undertaking shall refer to entering into contract with the Procuring Entity and
furnishing of the performance security or the performance securing declaration within ten (10) calendar days from receipt of
Notice to Execute Framework Agreement. 14
14.2. The Bid and bid security shall be valid for one hundred twenty (120) calendar
days. Any Bid not accompanied by an acceptable bid security shall be rejected
by the Procuring Entity as non-responsive.
The Procuring Entity may request additional hard copies and/or electronic copies of the
Bid. However, failure of the Bidders to comply with the said request shall not be a
ground for disqualification.
If the Procuring Entity allows the submission of bids through online submission or any
other electronic means, the Bidder shall submit an electronic copy of its Bid, which
must be digitally signed. An electronic copy that cannot be opened or is corrupted shall
be considered non-responsive and, thus, automatically disqualified.
In case the Bids cannot be opened as scheduled due to justifiable reasons, the
rescheduling requirements under Section 29 of the 2016 revised IRR of RA No.
9184 shall prevail.
19.3. The descriptions of the lots or items shall be indicated in Section VII (Technical
Specifications), although the ABCs of these lots or items are indicated in the
BDS for purposes of the NFCC computation pursuant to Section 23.4.2.6 of the
2016 revised IRR of RA No. 9184. The NFCC must be sufficient for the total of
the ABCs for all the lots or items participated in by the prospective Bidder.
19.4. The Project shall be awarded as one Project having several items that shall be
awarded as one contract.
19.5. Except for bidders submitting a committed Line of Credit from a Universal or
Commercial Bank in lieu of its NFCC computation, all Bids must include the
NFCC computation pursuant to Section 23.4.1.4 of the 2016 revised IRR of RA
No. 9184, which must be sufficient for the total of the ABCs for all the lots or
items participated in by the prospective Bidder. For bidders submitting the
committed Line of Credit, it must be at least equal to ten percent (10%) of the
ABCs for all the lots or items participated in by the prospective Bidder.
20. Post-Qualification
20.1. Within a non-extendible period of five (5) calendar days from receipt by the
Bidder of the notice from the BAC that it submitted the Lowest Calculated Bid,
the Bidder shall submit its latest income and business tax returns filed and paid
through the BIR Electronic Filing and Payment System (eFPS) and to her
appropriate licenses and permits required by law and stated in the BDS.
16
Section III. Bid Data Sheet
ITB
Clause
5.3 For this purpose, contracts similar to the Project shall be:
The Bidder must have completed within five (5) years a single contract that is
similar to this Project, equivalent to at least fifty percent (50%) of the ABC.
12 The Bid prices for Goods supplied from outside of the Philippines shall be quoted
in Philippine Pesos.
14.1 The bid security shall be in the form of a Bid Securing Declaration, or any of the
following forms and amounts:
a. The amount of not less than 2% of the ABC if bid security is in cash,
cashier’s/manager’s check, bank draft/guarantee or irrevocable letter of
credit; or
b. The amount of not less than 5% of the ABC if bid security is in Surety
Bond.
17
Section IV. General Conditions of Contract
1. Scope of Contract
This Contract shall include all such items, although not specifically mentioned, that can
be reasonably inferred as being required for its completion as if such items were
expressly mentioned herein. All the provisions of RA No. 9184 and its 2016 revised
IRR, including the Generic Procurement Manual, and associated issuances, constitute
the primary source for the terms and conditions of the Contract, and thus, applicable in
contract implementation. Herein clauses shall serve as the secondary source for the
terms and conditions of the Contract.
This is without prejudice to Sections 74.1 and 74.2 of the 2016 revised IRR of RA No.
9184 allowing the GPPB to amend the IRR, which shall be applied to all procurement
activities, the advertisement, posting, or invitation of which were issued after the
effectivity of the said amendment.
Additional requirements for the completion of this Contract shall be provided in the
Special Conditions of Contract (SCC).
2.2. The Procuring Entity is allowed to determine the terms of payment on the partial
or staggered delivery of the Goods procured, provided such partial payment
shall correspond to the value of the goods delivered and accepted in accordance
with prevailing accounting and auditing rules and regulations. The terms of
payment are indicated in the SCC.
3. Performance Security
Within ten (10) calendar days from receipt of the Notice of Award by the Bidder from
the Procuring Entity but in no case later than prior to the signing of the Contract by both
parties, the successful Bidder shall furnish the performance security in any of the forms
prescribed in Section 39 of the 2016 revised IRR of RA No. 9184.
All reasonable facilities and assistance for the inspection and testing of Goods,
18
including access to drawings and production data, shall be provided by the Supplier to
the authorized inspectors at no charge to the Procuring Entity.
5. Warranty
6.1. In order to assure that manufacturing defects shall be corrected by the Supplier,
a warranty shall be required from the Supplier as provided under Section 62.1
of the 2016 revised IRR of RA No. 9184.
6.2. The Procuring Entity shall promptly notify the Supplier in writing of any claims
arising under this warranty. Upon receipt of such notice, the Supplier shall,
repair or replace the defective Goods or parts thereof without cost to the
Procuring Entity, pursuant to the Generic Procurement Manual.
If the Supplier is a joint venture, all partners to the joint venture shall be jointly and
severally liable to the Procuring Entity.
19
Section V. Special Conditions of Contract
20
Special Conditions of Contract
GCC
Clause
1
Delivery and Documents –
Delivery of the Goods shall be made by the Supplier in accordance with the
terms specified in Section VI (Schedule of Requirements).
For purposes of this Clause the Procuring Entity’s Representative at the Project
Site is Batangas State University Alangilan
Incidental Services –
21
The Contract price for the Goods shall include the prices charged by the
Supplier for incidental services and shall not exceed the prevailing rates charged
to other parties by the Supplier for similar services.
Spare Parts –
The spare parts and other components required are listed in Section VI
(Schedule of Requirements) and the cost thereof are included in the contract
price.
The Supplier shall indemnify the Procuring Entity against all third-party claims
of infringement of patent, trademark, or industrial design rights arising from use
of the Goods or any part thereof.
4 The inspections and tests that will be conducted are included on the scope of
works.
22
Section VI. Schedule of Requirements
The delivery of the project is required fifteen calendar days (15) upon receipt of the Notice to Proceed.
Statement of
Compliance
Unit Description Quantity Duration (Comply / Not
Comply)
Warranty
Motor Controls Training Board
Operations and Maintenance Manual
On-site Training
Section VII. Technical Specifications
TECHNICAL SPECIFICATIONS
Warranty
Motor Controls Training Board
Operations and Maintenance Manual
On-site Training
Technical Specifications
Technical Documents
□ (b) Statement of the prospective bidder of all its ongoing government and private
contracts, including contracts awarded but not yet started, if any, whether
similar or not similar in nature and complexity to the contract to be bid; and
□ (c) Statement of the bidder’s Single Largest Completed Contract (SLCC) similar to
the contract to be bid, except under conditions provided for in Sections
23.4.1.3 and 23.4.2.4 of the 2016 revised IRR of RA No. 9184, within the
relevant period as provided in the Bidding Documents; and
□ (d) Original copy of Bid Security. If in the form of a Surety Bond, submit also a
certification issued by the Insurance Commission;
or
Original copy of Notarized Bid Securing Declaration; and
□ (e) Conformity with the Technical Specifications, which may include
production/delivery schedule, manpower requirements, and/or after-
sales/parts, if applicable; and
□ (f) Original duly signed Omnibus Sworn Statement (OSS);
and if applicable, Original Notarized Secretary’s Certificate in case of a
corporation, partnership, or cooperative; or Original Special Power of
Attorney of all members of the joint venture giving full power and authority
to its officer to sign the OSS and do acts to represent the Bidder.
Financial Documents
□ (g) The Supplier’s audited financial statements, showing, among others, the
Supplier’s total and current assets and liabilities, stamped “received” by the
BIR or its duly accredited and authorized institutions, for the preceding
calendar year which should not be earlier than two (2) years from the date of
bid submission; and
List of all Ongoing Government & Private Contracts including contracts awarded but notyet started
Name of Contract/ a. Owner's Name Nature of Work Bidder's Role a. Date Awarded % of Value of
Project Cost b. Address b. Date Started Accomplishment Outstanding
c. Telephone Nos. Description % c. Date of Planned Actual Works
Completion
Government
Private
Total Cost
Submitted by :
(Printed Name & Signature)
Designation : Date :
One of the technical documents required to be in the Eligibility Envelope of a bidder is a list of all its on-going, completed, and awarded but not yet started contracts.
Batangas State University
BatStateU-Goods Form No. 2
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020- Amended)
Statement of Single Largest Government or Private Contracts Completed which are similar in nature
Government
Private
Submitted by :
(Printed Name & Signature)
Designation : Date :
Batangas State University BatStateU-Goods Form No. 3
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
1. I/We understand that, according to your conditions, bids must be supported by a Bid
Security, which may be in the form of a Bid Securing Declaration.
2. I/We accept that: (a) I/we will be automatically disqualified from bidding for any
procurement contract with any procuring entity for a period of two (2) years upon receipt
of your Blacklisting Order; and, (b) I/we will pay the applicable fine provided under Section
6 of the Guidelines on the Use of Bid Securing Declaration, within fifteen (15) days from
receipt of the written demand by the procuring entity for the commission of acts resulting
to the enforcement of the bid securing declaration under Sections 23.1(b), 34.2, 40.1 and
69.1, except 69.1(f),of the IRR of RA No. 9184; without prejudice to other legal action the
government may undertake.
3. I/We understand that this Bid Securing Declaration shall cease to be valid on the following
circumstances:
a. Upon expiration of the bid validity period, or any extension thereof pursuant to your
request;
b. I am/we are declared ineligible or post-disqualified upon receipt of your notice to such
effect, and (i) I/we failed to timely file a request for reconsideration or (ii) I/we filed a
waiver to avail of said right; and
c. I am/we are declared the bidder with the Lowest Calculated Responsive Bid, and I/we
have furnished the performance security and signed the Contract.
IN WITNESS WHEREOF, I/We have hereunto set my/our hand/s this day of [month]
[year] at [place of execution].
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
Batangas State University BatStateU-Goods Form No. 04
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
Delivery of the project is fifteen (15) calendar days upon receipt of the Notice to
Proceed(NTP).
Statement of Compliance
Name of Project Schedule (Comply / Not Comply)
Warranty
Motor Controls Training Board
Operations and Maintenance Manual
On-site Training
Batangas State University BatStateU-Goods Form No. 6
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
REPUBLIC OF THE
PHILIPPINES)
CITY/MUNICIPALITY OF ) S.S.
AFFIDAVIT
I, [Name of Affiant], of legal age, [Civil Status], [Nationality], and residing at [Address of
Affiant],after having been duly sworn in accordance with law, do hereby depose and
state that:
5. [Name of Bidder] is authorizing the Head of the Procuring Entity or its duly
authorized representative(s) to verify all the documents submitted;
[If a sole proprietorship:] The owner or sole proprietor is not related to the Head
Batangas State University BatStateU-Goods Form No. 6
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
of theProcuring Entity, members of the Bids and Awards Committee (BAC), the
Technical Working Group, and the BAC Secretariat, the head of the Project Management
Office or the end-user unit, and the project consultants by consanguinity or affinity up to
the third civil degree;
[If a partnership or cooperative:] None of the officers and members of [Name of Bidder] is
related to the Head of the Procuring Entity, members of the Bids and Awards Committee
(BAC), the Technical Working Group, and the BAC Secretariat, the head of the Project
Management Office or the end-user unit, and the project consultants by consanguinity or
affinity up to the third civil degree;
[If a corporation or joint venture:] None of the officers, directors, and controlling
stockholders of [Name of Bidder] is related to the Head of the Procuring Entity, members
of the Bids and Awards Committee (BAC), the Technical Working Group, and the BAC
Secretariat, the head of the Project Management Office or the end-user unit, and the
project consultants by consanguinity or affinity up to the third civil degree;
7. [Name of Bidder] complies with existing labor laws and standards; and
9. [Name of Bidder] did not give or pay directly or indirectly, any commission, amount, fee, or
any form of consideration, pecuniary or otherwise, to any person or official, personnel or
representative of the government in relation to any procurement project or activity.
10. In case advance payment was made or given, failure to perform or deliver any of the
obligations and undertakings in the contract shall be sufficient grounds to
constitute criminal liability for Swindling (Estafa) or the commission of fraud with
unfaithfulness or abuse of confidence through misappropriating or converting any
payment received by a person or entity under an obligation involving the duty to
deliver certain goods or services, to the prejudice of the public and the government
of the Philippines pursuant to Article 315 of Act No. 3815 s. 1930, as amended, or
the Revised Penal Code.
[Jurat]
[Format shall be based on the latest Rules on Notarial Practice]
Batangas State University BatStateU-Goods Form No.7
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
Year 20
1. Total Assets
2. Current Assets
3. Total Liabilities
4. Current Liabilities
B. The Net Financial Contracting Capacity (NFCC) based on the above data is computed as follows:
NFCC = [(Current assets minus current liabilities) (15)] minus the value of all outstanding or
uncompleted portions of the projects under ongoing contracts, including awarded contracts yet
to be started, coinciding with the contract to be bid.
NFCC = P
The value of bidder’s current assets and current liabilities shall be based on the latest Audited
Financial Statements submitted to the BIR.
Herewith attached are certified true copies of the audited financial statement: stamped “RECEIVED” by
the BIR or BIR authorized collecting agent for the immediately
NOTE:
1. If Partnership or Joint Venture, each Partner or Member Firm of Joint Venture shall submit the above
requirement.
Batangas State University BatStateU-Goods Form No.8
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
BID FORM
Date:
Project Identification No.:
a. to deliver the goods in accordance with the delivery schedule specified in the Schedule
of Requirements of the Philippine Bidding Documents (PBDs);
b. to provide a performance security in the form, amounts, and within the times prescribed
in the PBDs;
c. to abide by the Bid Validity Period specified in the PBDs and it shall remain binding
upon us at any time before the expiration of that period.
We understand that you are not bound to accept the Lowest Calculated Bid or any Bid
you may receive.
The undersigned is authorized to submit the bid on behalf of [name of the bidder] as
evidenced by the attached [state the written authority].
Batangas State University BatStateU-Goods Form No.8
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
We acknowledge that failure to sign each and every page of this Bid Form, including the
attached Schedule of Prices, shall be a ground for the rejection of our bid.
Name:
Legal capacity:
Signature:
Duly authorized to sign the Bid for and behalf of:
Date:
Batangas State University BatStateU-Goods Form No. 9
Bidding Documents (Based on Revised IRR of RA 9184, Sixth Edition, July 2020)
1 2 3 4 5 6 7 8
Item Description Country of Quantity Unit price 12% VAT Unit Price with VAT Total Price Delivered
origin per item Application Final Destination
Name:
Legal Capacity:
Signature:
Date of Letter
Dear Sir:
PURCHASE AGREEMENT
This Purchase Agreement is made and entered into in the City of Batangas this day
of , 2023 by and between
And
WITNESSETH:
WHEREAS, the PURCHASER needs the services of a competent and responsible SUPPLIER to undertake the
supply and delivery of the said goods/supplies/products within the PURCHASER’s time frame;
WHEREAS, the Bids and Awards Committee (BAC) of the PURCHASER, in a resolution dated
, recommended to the Finance Committee of BatStateU Boardof Regents,
through the University President, the award of the above-mentioned project to ABCDCorporation for being the Single
Calculated and Responsive Bid in accordance with the provisionsof Republic Act 9184, otherwise known as “The
Government Procurement Reform Act” and its Revised Implementing Rules and Regulations (RIRR);
WHEREAS, the award of the project has been approved by the University President pursuant to his authority per
Board of Regents Resolution No. 00, s. of 2022;
NOW THEREFORE, for and in consideration of the above premises, and the covenants hereinafter stipulated, the
parties hereto, hereby voluntarily agree as follows:
Page 1
1
ARTICLE I
CONTRACT DOCUMENTS
1.01. The following documents are hereby made integral parts hereof and shall, except asmodified
by mutual agreement of the parties, form part of this AGREEMENT:
Further, all other Contract documents that may be required by existing laws and/or by the
PURCHASER, including the Bidding Documents, shall form and be interpreted and construed as
part of this Agreement.
1.02. All stipulations, documentary requirements, warranties and other terms and conditions which are,
and can be, agreed upon by the PURCHASER and the SUPPLIER during andafter the bidding
process for this Project, but are not explicitly provided herein, shall formpart of this Agreement.
1.03. Any and all deficiencies that can be found in this Agreement which are intended to be covered by
it, but are not expressly stated herein, shall be supplied by any of the aforesaidContract Documents.
1.04. In case of doubt or conflict between and among the provisions of this Agreement, and/or between
and among the above Contract Documents and this Agreement, the SUPPLIER shall refer the same
in writing to the PURCHASER for clarification and guidance. The clarification or determination
made by the PURCHASER shall be binding and conclusiveupon the parties. The SUPPLIER shall
not make any change or alteration in the plans, conditions, and specifications of the Project without
prior approval by the PURCHASER.
1.05. The parties herein may, in writing, agree to any revision, alteration, or addition to the terms and
conditions of this Agreement, provided the same shall not be in violation of any law, rules or
regulations governing contracts of government.
ARTICLE II
APPLICABILITY OF OTHER LAWS
2.01. The provision of Republic Act No. 9184 or the Philippine Government Procurement Reform Act and
its Revised Implementing Rules and Regulations shall govern thisContract. All other laws which
are not inconsistent with the aforesaid law shall likewise apply.
ARTICLE III
DUTIES AND RESPONSIBILITIES OF THE PARTIES
3.01. The SUPPLIER shall be responsible for the source(s) of his goods/supplies/products and shall
make deliveries in accordance with schedule, quality and specifications of the award.Failure by the
SUPPLIER to comply with the same shall be ground for cancellation of theaward issued to the
SUPPLIER and forfeiture of performance security and other available actions to the
PURCHASER.
3.02. Make complete delivery of the goods/supplies/products subject of this agreement within
fifteen (15) calendar days from the issuance of the Notice to Proceed.
3.03. Subject to the provisions of the preceding paragraph, where the SUPPLIER has acceptedthe award
but fails to deliver the required goods/supplies/products within the time called for in the same order,
he shall be given a maximum extension of fifteen (15) calendar days under liquidated damages to
make good of his delivery. Thereafter, if SUPPLIER has not completed delivery within the
extended period, the order shall be cancelled and the award for the undelivered balance shall be
withdrawn from that SUPPLIER. The PURCHASER shall then purchase the required
Page 2
1
goods/supplies/products from such other source(s) as it may determine, with the difference in price
to be charged against the DEFAULTING SUPPLIER. Refusal by the DEFAULTING
SUPPLIER to shoulder theprice difference shall be ground for his disqualification from future
bids of the same or all items, without prejudice to the imposition of other sanctions prescribed under
RA 9184and its IRR.
3.04. All deliveries by SUPPLIER shall be subject to inspection and acceptance by the PURCHASER.
All necessary laboratory tests undertaken by the PURCHASER on the item(s) shall be for the
account of the SUPPLIER.
3.06. The SUPPLIER shall guarantee his deliveries to be free from defects. Any defective
goods/supplies/products, therefore, that may be discovered by the PURCHASER within three (3)
months after acceptance of the same, shall be replaced by the supplier within seven (7) calendar
days upon request of a written notice to that effect.
3.07. The SUPPLIER shall hold the PURCHASER, its officers, agents and employees, free and
harmless against any claim, losses, damages, or injuries of whatever kind or nature thatmay be filed
or claimed against the PURCHASER by any third person, firm or entity arising out of or in
connection with the matters undertaken by the SUPPLIER under this Agreement, or by negligence
of the SUPPLIER, its agents, servants and employees.
3.08. The SUPPLIER shall not assign or sublet this Agreement, or any portion hereof, nor anymonies
due or to become due to him hereunder without previous written consent of the PURCHASER and
shall not deviate from the plans, specifications and details except on written order of the
PURCHASER.
ARTICLE IV
PERFORMANCE BOND, WARRANTY, RETENTION MONEY,
TERM OF PAYMENTAND LIQUIDATED DAMAGES
To guarantee the faithful performance by the SUPPLIER of its obligations under this agreement,
the SUPPLIER shall post a performance security prior signing of this agreement. The performance
security shall be posted in favor of the procuring entity whichshall be forfeited in the event it is
established that the SUPPLIER is in default in any of its obligations under this purchase agreement.
The Performance Bond shall be co-terminuswith the date of final acceptance by the PURCHASER.
It shall be in the form and amountstipulated in the Instruction to Bidders. The same shall be released
by the PURCHASER after issuance of Certificate of Final Acceptance, provided that the
PURCHASER has no claims filed against the SUPPLIER or the surety company and in
accordance with pertinent provisions of RA 9184.
4.02. Warranty.
4.02.1 The SUPPLIER hereby warrants and guarantees that all goods/supplies/products to be
supplied by it under this AGREEMENT are new, first class, free from defects and shall
fully comply in every respect with the specifications, approved samples and other
requirements of the contract plan and other related Contract Documents.The SUPPLIER
shall make no substitution for goods/supplies/products required to be furnished by it under
the AGREEMENT unless written approval is first obtained from the PURCHASER. The
SUPPLIER warrants that the goods/supplies/products to be supplied by it are free and
clear of all liens and encumbrances.
4.02.2. In order to assure that manufacturing defects shall be corrected by the SUPPLIER, a
warranty security shall be required from the SUPPLIER for a minimum period of three (3)
months, in the case of Expendable Supplies, or a minimum period of one (1) year, in the
case of Non-expendable Supplies, after acceptance by the procuring entity of the delivered
supplies. The obligation for the warranty shall becovered by either retention money in an
amount equivalent to one percent (1%) of every progress payment, or a special bank
guarantee equivalent to one percent (1%)of the total contract price. The said amounts shall
only be released after the lapse of the warranty period or, in the case of Expendable
Page 3
1
Supplies, after consumption thereof: Provided, however, that the supplies delivered are free
from patent and latent defects and all the conditions imposed under the contract have been
fully met.
4.03. Term of Payment and Retention Money. Payments shall be made only upon a certification by
the Head of the PURCHASER to the effect that the goods/supplies/products have been delivered
and installed in accordance with the terms ofthis purchase agreement and have been duly inspected
and accepted. Five percent (5%) of the amount of each payment shall be retained by the
PURCHASER to cover the SUPPLIER warranty obligations unless a special bank guarantee per
Section 4.02.2 is posted by the SUPPLIER.
4.04. Liquidated Damages. When the SUPPLIER fails to satisfactorily deliver goods/supplies/products
under the contract within the specified delivery schedule, inclusive of duly granted time extensions,
if any, the SUPPLIER shall be liable for damages for the delay and shall pay the PURCHASER
liquidated damages, not by way ofpenalty, an amount equal to one-tenth (1/10) of one percent (1%)
of the cost of the delayed goods scheduled for delivery for every day of delay until such
goods/supplies/products arefinally delivered and accepted by the PURCHASER.
The PURCHASER need not prove that it has incurred actual damages to be entitled to liquidated
damages. Such amount shall be deducted from any money due or which may become due to the
SUPPLIER, or collected from any securities or warranties posted by the SUPPLIER, whichever
is convenient to the PURCHASER.
In no case shall the total sum of liquidated damages exceed ten percent (10%) of the total contract
price, in which event the PURCHASER shall automatically rescind the contract and impose
appropriate sanctions over and above the liquidated damages to be paid.
4.05. All provisions with respect to warranties contained in this Agreement are cumulative and all
alternatives are in addition to such warranties as may be provided by law or contained in the other
provisions of this Agreement.
ARTICLE V
CONTRACT PRICE
5.01. The PURCHASER shall pay the SUPPLIER, in consideration for the satisfactory, full and faithful
performance and accomplishment of all its obligations, which the SUPPLIERagreed to
undertake, the total contract price of
(Php ).
5.02. Taxes on all transactions subject of this agreement shall be in accordance with the NationalInternal
Revenue Code (NIRC) and other pertinent tax laws, rules and regulations.
ARTICLE VI
MISCELLANEOUS PROVISIONS
6.01. Any breach or violation by either party of the obligations and covenants under this Agreement shall
entitle the aggrieved party to rescind or cancel this Agreement, after fifteen (15) days written notice
to that effect. In addition, the party that breached or violatedthis Agreement agrees and obligates
itself to pay for the actual damage incurred by the other party;
6.02. Any failure of the PURCHASER to enforce its rights and privileges under this Agreementshall not
be construed as a waiver or renunciation of such rights and privileges;
6.03. It is hereby agreed that any suit or proceeding, which either party may in virtue of, or in relation
to, or connected with this Agreement, shall be filed with the proper court of the City of the Batangas
to the exclusion of all other courts.
ARTICLE VII
EFFECTIVITY AND SEPARABILITY CLAUSES
7.01. This Agreement shall take effect within three (3) days after the receipt of the Notice to Proceed
from the PURCHASER’s technical representative, which Notice shall be given only when this
Agreement has been perfected and shall be in force and effect until the final acceptance of the
PURCHASER;
Page 4
1
7.02. To the best knowledge and belief of the parties, this Agreement contains no provision thatis contrary
to Philippine Laws or any ruling or regulation. Should, however, any provisionof the Agreement,
at any time during its term be in conflict with any such law, ruling or regulation, then such provision
of this Agreement is thus held inoperative, the remaining provisions of this Agreement shall,
nevertheless remain in full force and effect.
7.03. It is agreed that the SUPPLIER shall bear all the expenses for the execution of this Agreement.
IN WITNESS WHEREOF, the parties have hereunto affixed their signatures this day of
2023 at Batangas City, Philippines.
PURCHASER SUPPLIER
Represented by: Represented by:
Page 5
1
REPUBLIC OF THE PHILIPPINES)
IN THE CITY OF ) SS.
BEFORE ME, a Notary Public for and in the above jurisdiction, personally appeared this
day of , 2023 at , Philippines.
Known to me to be the same persons who executed the foregoing instruments consisting of six (6)
pages including this page on which this Acknowledgement appears and they acknowledged to me
that same is their free act and voluntary act and deed and those of the principals they respectively
represented.
IN WITNESS WHEREOF, I hereunto set my hand and seal on the date and place first above
mentioned.
Doc. No.
Page No.
Book No.
Series No. 2022
Page 6