ZB CHAMBtrT{S" FLOOR TEL: +263 2425*4548

ChlR IST ST & GiSII-LJNDIKA AVE CELL:+263 7851 82052


HARARtr +263 77238 1 745
Emai I : earthlygatecivils@gmail.com

To: lriewhoiland
From :Earthlygate Precast and Civil Contractors
Date:A1 fi312*24

On the 27 Febrmry 2024 as I was working with TLB Newholland at Greystone Park Project, I
saw a safety bar used for safety by the mechanics to support the bucket during the service of the
machine scraping the bornet cover at the front of the machine. When I stopped the machine to see
the cause i discovered that the pin was bend.

Operator: Vhovha Trymcre

XD no: fi4-130783 F 04

signaturffi.....