TIME SHEET

Name of Vessel : MV.MANALAGI SAMBA VOY.NO=11/23


Port of Loading ( Log Pond ) : Muara Berau Anchorage, East Kalimantan, Indonesia
Destination Port : MOROSI
Description of cargo : Indonesian Steam Coal In Bulk
Quantity loaded as per B/L : 50,896 MT
SHIPS POSITION
Arrived at Quarantine Station plt.stn : 0210 Hrs on Oct 25th, 2023
Pilot on board : 0210 Hrs on Oct 25th, 2023
Nor tendered : 0210 Hrs on Oct 25th, 2023
Dropped anchor : 0322 Hrs on Oct 25th, 2023
Free pratique : Hrs on Oct 25th, 2023
Commenced Loading : 1630 Hrs on Oct 25th, 2023
Completed Loading : 1600 Hrs on Oct 29th, 2023

WORKING RECORDS : Page No.1


HOLD LOADING PROGRESS
DATE & DAY WEATHER R E M A R K'S
No. WORK'S Hrs REMARKS

Oct 25,th2023 Cloudy 0210 ARRIVAL


Wednesday 0210 PILOT ON BOARD
0210 NOR TENDERED
021-1410 NO LOADING ACTIVITY-WAITING LOADING SCHEDULE FROM SHIPPER
0322 DROPPED ANCHORE
0330 PILOT OFF BOARD
0900 AGENT ON BOARD
1000 AGENT LEFT DOWN
1230 1st STEVEDORE ON BOARD
1230 FOREMANT AND TEAM ON BOAR
1300 LCT. SYAHIR JAYA 01 along aside at portside
1300-1400 Transfer Bulldozer from LCT. SYAHIR JAYA01 to deck Ship by C3 and Install fender
1400 LCT syair jaya 01 casted off
1400-1500 INITIAL DRAFT SURVEY, HOLD CLEAN INSPECTION AND CALCULATION
1630 1st BG. KBT 12 along side starbordside
1630 COMMENCED LOADING H12/C12 Bg. KBT 12
1630-1645 Transfer Bulldozer from deck to Bg. KBT 12
1645 Started loading H3/C3 Bg. KBT 12
1830 2nd Bg telaga makmur 18.as at p/side
2400 Continue loading H123/C123 frm bg kbt 12 to next day
Oct 26,th2023 Cloudy 0000 Continue loading H123/C123 frm bg kbt 12 frm last day
Thursday 0845 Stop loading H123/C123 due to Finish Cgo bg KBT 12
0845 Resume loading H245/C124 frm bg telaga makmur 18
0845-0900 Transfer b/dozer frm bg KBT 12 to bg telaga makmur 18 by c3
0900 Bg KBT 12 Casted off
0900 Started loading H4/C3 Bg.telaga makmur 18
1215 3rd.Bg telaga makmur 01.as at stbd
We hereby certify that the above is true and correct.

PT.MEC PT.RFS PT. Borneo Persada Utama MV.MANALAGI SAMBA

Shipper Agent For Stevedoring Master


TIME SHEET
WORKING RECORDS : Page No.2
HOLD LOADING PROGRESS
DATE & DAY WEATHER R E M A R K'S
No. WORK'S Hrs REMARKS
1945 Shifting H2/C1 to H1/C1 & Resumed loading H135/C124 Bg. Telaga Makmur 01
1945-2000 Transfer bulldozer from Bg. Telaga Makmur 18 to Bg. Telaga Makmur 01 by C3
2000 Bg telaga makmur 18 casted off
2000 Resume loading H4/C3 bg telaga makmur 01
2215 4th.Bg telaga makmur 17 as at p/side
2400 Continue loading H1345/C1234 to next day
Oct 27,th2023 Cloudy 0000 Now continue loading H1345/C1234 frm last day
Friday 1015 Stop loading finish cgo bg telaga makmur 01
1015-1030 Transfer b/dozer frm bg telaga makmur 01 to bg telaga makmur 17 by c3
1030 Bg telaga makmur 01 Casted off
1030 2nd stevedor on board
1030 Resume loading H1345/1234 Bg telaga makmur 17
1100 5th.Bg telaga makmur 11 as at stbd
1130-1300 No activity due to muslim friday
1300 Resume loading H1245/C1234 Bg telaga makmur 17
2400 Continue loading H1245/C1234 next day
Oct 28,th2023 Cloudy 0000 Continue loading H1245/C1234 frm last day
Saturday 0300 Stop Loading due to finish cgo bg telaga makmur 17
0300 Resume loading H134/C134 bg telaga makmur 11
0300-0315 Transfer b/Dozer frm bg telaga makmur 17 to bg telaga makmur 11 by c2
0315 Bg telaga makmur 17 Casted off
0315 Resume loading H2/C2 bg telaga makmur 11
0600 6th.Bg charles 206 as at p/side
1245 Stop Loading Finish Cgo bg telaga makmur 11
1245 Resume loading H235/C124 bg charles 206
1245-1300 Transfer b/dozer frm bg telaga makmur 11 to bg Charles 206 by c3
1300 Bg Telaga makmur 11 Casted off
1300 Resume loading H4/C3 bg Charles 206
1510 7th.Bg KBT 25 as at stbd
2400 Continue loading H2345/C1234 to next day
Oct 29,th2023 Cloudy 0000 Continue loading H2345/C1234 frm last day
Sunday 0200 Stop loading Finish Cgo bg Charles 206
0200 Resume loading H235/C124 bg KBT 25
0200-0215 Transfer b/Dozer frm bg Charles 206 to bg KBT 25
0215 Bg Charles 206 Casted off
0215 Resume loading H4/C3 bg KBT 25
0930 Shifting loading H234/C123 bg KBT 25
0930-1400 Resume loading H1235/C1234 bg KBT 25
1400-1500 intermedite draft survey
We hereby certify that the above is true and correct.

PT.MEC PT.RFS PT. Borneo Persada Utama MV.MANALAGI SAMBA

Shipper Agent For Stevedoring


TIME SHEET
WORKING RECORDS : Page No.3
HOLD LOADING PROGRESS
DATE & DAY WEATHER R E M A R K'S
No. WORK'S Hrs REMARKS
1500 Resume loading H23/C23 bg KBT 25
1600 Completed loading
1600-1700 Final Draft survey

We hereby certify that the above is true and correct.

PT.MEC PT.RFS PT. Borneo Persada Utama MV.MANALAGI SAMBA

Shipper Agent For Stevedoring


TIME SHEET
WORKING RECORDS : Page No.4
HOLD LOADING PROGRESS
DATE & DAY WEATHER R E M A R K'S
No. WORK'S Hrs REMARKS

We hereby certify that the above is true and correct.

PT.MEC PT.RFS PT. Borneo Persada Utama MV.MANALAGI SAMBA

Shipper Agent For Stevedoring