Download as pdf or txt
Download as pdf or txt
You are on page 1of 48

CAT-SBWIP-PMT-T-4256-2022 Revised Quality control procedure for Installation of Epoxy grout for

equipment machinery support Rev1

Comment:

Approved.

PID Civil NA OIL FACILITIES

Mahmoud Ayead

6-June-2022
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 2 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

Table of Contents
1. PROCEDURE NO.

2. APPLICABILITY

3. SCOPE

4. RESPONSIBLITY

5. GENERAL

6. DEFINITIONS

7. PROCEDURE

7.1. Epoxy Grout Materials Receiving and Storage


7.2. Epoxy Grout Pre-installation – Substrate preparation
7.3. Inspection of Equipment / Machinery Prior to Grouting
7.4. Anchor Bolts in Preformed Pockets Epoxy Grouting
7.5. Machine / Equipment Base Plate installation
7.6. Material & Equipment Availability
7.7. Epoxy Grout Forms
7.8. Expansion Joints
7.9. Epoxy Grout Mixing & Placement
7.10. Epoxy Grout Sampling & Testing
7.11. Epoxy Grout Curing/ Protection and Final Inspection

8. RECORDS

9. REFERENCES

10. ATTACHMENTS

10.1. SATIP-Q-011-01 – Epoxy Grout for Machinery Support


10.2. Sample IFC drawings
10.3. DCP – Flow-Grout EPCG MTDS
10.4. DCP – Flow-Grout EPCG MOS
10.5. DCP – Flow-Grout EPCG MSDS

Note: Table of Contents similarly based on GI - 400. 001 Matrix or Scheme Index
2
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 3 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

1. PROCEDURE NO.

QA/P-EPG-001.Doc

2. APPLICABILITY

All Projects

3. SCOPE

This procedure covers all phases of epoxy grout for use in equipment &
machinery anchor bolt pockets & base supports including but not limited
to forming, handling, mixing, placement, curing & testing inspections.
This procedure is submitted in order to ensure that the work is properly
prepared and finished in accordance with the Client specification, drawings, and
applicable standards. This procedure ensures that all the inspection and testing
activities are properly executed and documented.

As per IFC drawings, there are two scenarios where epoxy grout will be
utilized:

• Preformed anchor bolts pockets for equipment / machinery


foundations are filled with epoxy grout and base plates of
equipment / machinery are filled with cementitious Non-Shrink
Grout.
• Only water injection Pumps will have epoxy grout in Preformed
anchor bolts pockets and under pump base.

4. RESPONSIBILITY

4.1 Project Manager (PM) shall be responsible for the overall implementation of
the company safety plan and this work procedure. The PM shall liaise / co-
ordinate with the planning and control (P & C) department and subcontractors
to ensure efficient execution of works in accordance with the specification
requirements.

4.2 Construction Manager shall be responsible to ensure that the project site is
safe to work for workers and equipment. The CM shall manage all site
supervisors on their respective discipline and give proper instruction to all site
supervisors ensuring safety and quality work is observed during the construction.
The CM shall coordinate with Safety personnel to imposed safety compliance.
The CM shall ensure the working condition of all subcontractors doing
subcontracted works.

3
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 4 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

4.3 Quality Assurance Manager shall be responsible for the review and approval
of Special Process Procedure. The QAM shall review the program of application
activities for the pre-construction meeting agenda and ensure this is conducted
by the QC Manager and Construction Manager. The QA Manager shall ensure
that the quality of work is in accordance to approved Project Quality Plan. The
QAM shall ensure that all documents have been properly collated and filed. The
QAM ensures that the Company QMIS has been effectively enforced in the
project.

4.4 Quality Control Manager shall review and implement the Special Process
Procedure and conduct pre-construction meeting with the Construction Manager
to all involve personnel. The QCM give instruction to his supervisor for the
proper deployment of QC Inspector. The QCM manage Quality Control
personnel and monitor inspection progress, inspection reports and
documentation, upon completion of work ensure that all requirements have been
met. He shall report to the QA Manager for any Quality violation committed at
site.

4.5 QC Inspector submit “RFI” (Request for Inspection) to the coordinating


contractor and other parties involved in-house verification of the completed work
by the construction team to ensure full compliance to specification requirements.
It is the responsibility of QC Inspector to ensure all inspection are performed on
all relevant inspections are accomplished as per project specification and Saudi
Aramco Standard. The QC Inspector to coordinate with Site Supervisor/Engineer
and contractor representative during inspection. QCI to secure quality
documents approval.

4.6 Discipline Engineer shall also plan enabling activities to ensure timely work
packages for the construction teams, which are safe to construct using off site
and modular building techniques. The role will include providing technical
support during the construction phase, also during project close out.

4.7 Discipline Foreman is responsible for training, directing, supervising, and, if


necessary, disciplining the crews and workers throughout the project,
the foreman is expected to monitor employee efforts, evaluate progress, and
provide workers with guidance and assistance to help increase efficiency.

4.9 Land Surveyor shall be solely responsible for road surveying by making
exact measurements and providing relevant data to shape, contour, gravitation,
location, elevation, or dimension of land or land features on or near the earth's
surface for equipment & machinery. He is responsible for the control of lines and
level on site. Carry out the layout as per approved IFC drawing. Surveyor to
conduct internal check of lines and levels prior to official survey inspection with
Aramco PID. As-built record (Handwritten) shall be placed in survey.

4
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 5 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

4.10 Epoxy Grout Preparation & Application Crew are skilled personnel
responsible for the preparation and application of Epoxy Grout.

5. GENERAL

The responsibility for the Inspection and Testing of the Epoxy Grout Works rests
primarily with the QC Inspector, the Discipline Engineer, Discipline Foreman and
the Land Surveyor with assistance from an audit by the QA & QC Managers.

The Discipline Engineer and the Discipline Foreman shall ensure the required work
permits are available and in place daily. Similarly, they shall ensure that utilized
drawings are the latest revision

The Project QA & QC Managers shall perform reviews on all Quality related
contractual documentation

The QC Inspector shall be responsible for witnessing tests and inspections and
ensure appropriate documentation in accordance with relevant SATIP’s.

All Epoxy Grout works shall comply fully with the applicable laws SATIP’s and
Client requirements and specifications.

In the case that Epoxy Grouting works may be subcontracted, then Specific Quality
Documentation shall be submitted to C.A.T. by Subcontractor which upon
completion of review shall be submitted to the client for review and comments.

However, whenever the subcontracted works are only for execution of the
Grouting works, then the responsibility to conduct all inspections,
witnessing tests and ensuring the appropriate documentation in accordance
with relevant SATIP’s, shall be under C.A.T. QC Team.

All activities inclusive of mixing, installation and testing shall be in accordance with
client specifications and SATIP-Q-011-01.

6. DEFINITIONS

Epoxy Grout: An epoxy or cementitious material used to provide a uniform


foundation support and load transfer link for the installation of rotating machinery.
This material is typically placed between a piece of equipment's concrete
foundation and its mounting plate.

5
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 6 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7. PROCEDURE

7.1. EPOXY GROUT MATERIAL RECEIVING & STORAGE

7.1.1. The All materials shall be delivered to the site in original unopened
packages. All materials shall be stored in accordance with
manufacturer’s recommendations.

7.1.2. Resin component of the epoxy grout materials shall consist of a


premeasured, prepackaged, solvent free, liquid epoxy resin specifically
formulated for the grout system used.

7.1.3. The hardener component shall consist of a premeasured,


prepackaged liquid specifically formulated to produce the specified final
properties when mixed with the other component.

7.1.4. The resin and catalyst components are free of hard sediment, gelatin
in a freshly opened can, and are of proper consistency to enable
thorough mixing to a smooth homogenous state. The components
show no gelling when stored as indicated in the data sheets from the
date of manufacture in unopened containers at temperatures of 32°C.

7.1.5. Resin and catalyst containers have no leak when subjected to normal
shipping and storage.

7.1.6. All components, resin, hardener and aggregate shall be properly


labeled, including batch numbers, shelf life and storage requirements.

01 7.1.7. All components which have already expired shall be segregated from
newly delivered materials and moved to the quarantine area.

7.2. EPOXY GROUT PRE-INSTALLATION - SUBSTRATE PREPARATION OF


FOUNDATION

7.2.1. Laitance and oil-soaked or damaged concrete are removed with


chipping hammer to sound fractured aggregate, or to a minimum of the
top 1 inch (25 mm) of concrete.

7.2.2. Concrete chipping and removal shall not be performed with heavy
tools such as jackhammers as they could damage the structural
integrity of the foundation.

6
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 7 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.2.3. Concrete foundation has reached the curing period up until the
compressive strength has reached 70% of the specified strength, but
not less than 7 days after placement.

7.2.4. The top of concrete foundation shall be a minimum of 150 mm above


finished grade or as shown in IFC Drawings.

7.2.5. Leveling shims are installed with a minimum top elevation of 25 mm


from the top of concrete foundation.

7.2.6. The minimum grout thickness under any portion of the


baseplate/soleplate shall be 25mm.

7.2.7. Concrete in contact with the epoxy grout shall be clean, dry and oil
free.

7.3. INSPECTION OF EQUIPMENT / MACHINERY PRIOR TO GROUTING

7.3.1. Equipment or machinery Support Structure or Foundation (Pre-


Installation inspection) shall be completed by other discipline.

7.3.2. Equipment / machinery alignment should be completed & verified by


other discipline, prior to proceeding with epoxy grout for anchor bolt
pockets.

7.3.3. Equipment / machinery alignment should be completed & verified by


other discipline, prior to proceeding with epoxy grout under base plate.

7.3.4. When type of grout is not specified by the equipment Manufacturer


01
epoxy grout shall be used for any of the following situations:

a. Equipment with driver horsepower of 500 (373 kW) or greater.


b. Equipment with speeds greater than 3600 RPM.
c. Equipment that has a combined weight (machine, driver, and
baseplate) of greater than 2,270 kg.
d. All reciprocating machinery with driver horsepower greater than 50
(37 kW).

7.4. ANCHOR BOLTS IN PREFORMED POCKETS EPOXY GROUTING.

7.4.1. Grouting of anchor bolts pockets may be done after the installation of
the Equipment / machinery with the required clearance from other
discipline.

7
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 8 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.4.2. Depending on site condition, epoxy grouting of anchor bolts pockets


may be done in advance prior to installing the Equipment / machinery,
once clearance from other discipline is provided.

7.4.3. Concrete surface in preformed pockets shall be chipped to sound


concrete.

7.4.4. Pockets shall be cleaned prior to installation of anchor bolts.

7.4.5. Anchor Bolts are installed as per IFC drawings.

7.4.6. All anchor bolts’ locations, projections, and diameter shall be field
verified to match the anchor bolt hole pattern in the mounting plate.

7.4.7. Anchor bolts are not tilted, or bolt bound and shall be perpendicular.

7.4.8. Anchor bolts are protected, and exposed threads are wrapped with
duct tape to prevent adherence of the epoxy grout.

7.4.9. It is important that the filling of the anchor pockets is done as a


separate process to the general grout application to ensure the anchor
pockets are filled without entrapping air.

7.4.10. The epoxy grout manufacturer's recommendations on


maximum depth of pour and length to width ratio shall be followed.

7.4.11. For the grouting of anchor bolts pockets, the maximum depth
of pour and the intervals between initial pour and next layer shall be as
per manufacture’s recommendation for the initial curing of 1st layer.

7.4.12. Next layer of pour shall be after initial curing of the previous
layer. Initial curing period shall be as manufacturer’s recommendations.

7.4.13. The top surface of the initial pour shall be free from dust or
debris prior to placing next layer.

7.5. MACHINE/ BASEPLATE INSTALLATION

7.5.1. The base plate will first be positioned and leveled to the required
height leaving a gap to be grouted. The following are several leveling
method commonly used on site.

7.5.2. Threaded Bolt with 2 Nuts – This is a common way to level small
base plates in non-critical applications. The lower nuts under the base
plate can be adjusted up or down the base plate to suit and the top nut
is tightened to “Sandwich” the base plate into position. This method is
NOT recommended after grouting the weight of the machine is still

8
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 9 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

resting mostly on the lower nut and the threaded bolt, post-tensioning is
impossible (tightening) the top nut just squashes the base plate without
tensioning it down.

7.5.3. Metal Shim Plates – A common process used to level large


equipment. The machine is lifted and metal shims are placed between
the base plate and the concrete foundation, then the machine is
lowered on to the shims. However, the shims are removed after
grouting, they will (like the bolt and 2 nuts above) bear most of the
weight and post tensioning is not possible unless the shims are
removed.

7.5.4. Leveling Screw (Bolts) – The best method. Threaded holes are made
through the base plate of the machine. Bolts are threaded into these
holes from the top and the tip of the bolt as well as the nut is resting on
metal pads positioned on the foundation. The bolts are then adjusted up
or down to achieve the correct level of the machine. Then grout is
installed. When the grout is hard enough the bolts can be backed out of
the threaded holes leaving only the grout to support the weight of the
machine. One of the things to make this process a success is to isolate
the thread of the leveling bolts from adhering to the grout (especially
resin grouts) this can be achieved with petrolatum tape or rubber tubing
around the bolts.

7.6. MATERIAL & EQUIPMENT AVILABILITY

7.6.1. An adequate quantity of epoxy grout (i.e., 10-25 percent extra) shall
be on hand before starting to mix and place epoxy grout.

7.6.2. Clean tools, mixing equipment, and safety supplies shall be readily
available at the jobsite.
01 7.6.3. Safety and fist aid supplies shall be readily available at jobsite.

7.7. EPOXY GROUT FORMS

7.7.1. Epoxy grout forms were constructed to be liquid-tight with adequate


strength, rigidity, and dimension to support epoxy grout placement.

7.7.2. Three coats of paste wax shall be applied to the inside surface of
forms to prevent epoxy grout adherence to the forms. Other approved
form release agents or bond breakers may be used as recommended
by the epoxy grout manufacturer. Oil or liquid wax is not permitted.

9
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 10 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.7.3. Epoxy grout form elevation shall be checked to ensure that the top
surface of the epoxy grout will match the elevation shown on the
construction drawings.

7.7.4. Chamfer strips [3/4 inch (20 mm), 45°] shall be installed at each
vertical corner and at the horizontal surface of the epoxy grout forms.

7.7.5. All form joints and interfaces between forms and concrete foundation,
including expansion joints, shall be sealed using epoxy grout
manufacturer’s recommended sealant. If epoxy grout manufacturer has
no recommendations for sealant, use room-temperature vulcanizing
(RTV) silicone sealant.

7.8. EXPANSION JOINTS

7.8.1. Expansion joints shall be incorporated into large epoxy grout pours to
reduce the possibility of cracking, especially when machinery-to-grout
temperature differentials of 30°Care encountered. Expansion joints
should be placed at approximately 1.2 m to 1.8 m intervals in the grout
foundation.

7.8.2. Expansion joints should be made from 12 mm to 25 mm (1/2 in. to 1


in.) thick closed-cell neoprene foam rubber. Polystyrene may also be
used. Ensure that the expansion joint material is compatible with the
grout.

7.8.3. Expansion joints require sealing after the grout has cured with elastic
epoxy seam sealant (liquid rubber) or silicone rubber room temperature
vulcanizable (RTV).

7.9. EPOXY GROUT MIXING & PLACEMENT

7.9.1. The resin and hardener shall be mix at 200-250rpm per the grout
manufacturer's specified time period prior to introducing the aggregate.
There should be no entrained air in the resin/hardener mixture.

7.9.2. Full bags of aggregate shall be slowly added to the blended


resin/hardener liquid and sufficiently mixed to completely wet-out the
aggregate.

7.9.3. Grout shall be mixed in a clean, slow speed (15-20rpm) portable


mixer but not a concrete mixer.

7.9.4. Epoxy grout shall be mixed with the manufacturer's written


requirements including temperature restrictions.

10
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 11 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.9.5. An adequate quantity of grout ingredients shall be on hand before


starting to mix and place the grout. No partial units of epoxy, resins,
hardener, or aggregate shall be used. Ratios of components shall not
be varied, and solvents shall not be added to change the grout
consistency.

7.9.6. Adequate enclosures or shelter shall be provided for weather


protection to maintain foundation and baseplate temperature within the
acceptable range specified by the grout manufacturer.

7.9.7. Grout placements shall be started at one end of forms, and the cavity
shall be filled completely while advancing toward the other end to
prevent air entrapment.

7.9.8. If epoxy grout is placed through grout holes, the epoxy grout shall be
placed into one hole continuously until the epoxy grout has passed a
second hole. A liquid head pressure shall be maintained at the first
access hole until a head pressure has been established at the next
hole. Epoxy grout placement shall continue from the next hole in a
similar fashion.

7.9.9. If epoxy grout is not placed through grout holes:

• Epoxy grout shall be placed starting at one end of the forms and
filling the cavity completely while advancing toward the other
end.

• Epoxy grout shall be placed along only one side of the baseplate
allowing it to slowly flow under the baseplate to the opposite
side.

7.9.10. Vibration or other forms of dynamic distribution shall not be


permitted.

7.9.11. Unless otherwise specified in the manufacturer's data sheets, grout


shall be applied only when surrounding temperatures (recommended
working temperatures) are between 15°C and 32°C (60°F and 90°F).

7.9.12. All leaks shall be sealed to prevent voids from forming in the grout.

11
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 12 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.9.13. Final checking of soleplate elevation and level shall be made


before the grouts sets

7.9.14. Any air bubbles rising to the surface of the epoxy grout shall be
removed by lightly spraying the bubble surface with the solvent
approved by the manufacturer.

7.9.15. Baseplate fill and vent holes shall not be plugged until the epoxy
grout has set because plugging can cause baseplate distortion because
of epoxy grout expansion.

01
7.9.16. Grout shall not be applied during bad weather conditions (rain,
sandstorm etc.).

7.9.17. A layered combination of non-shrink cement and epoxy grout may


01 be used, as permitted by SAES-Q-007 for large baseplates that have
structural webs deeper than 230 mm.

7.10. EPOXY GROUT SAMPLING & TESTING

7.10.1. Sampling and testing shall be performed by a Saudi Aramco


approved independent testing laboratory. Third Party Agency's Quality
personnel assigned to the Work must be technically competent to
perform their duties.

7.10.2. For each epoxy grout shipment or manufacturing lot, a minimum of


nine samples shall be tested for compressive strength in accordance
with ASTM C579, Method B modified.

7.10.3. Three cubes shall be tested at 24 hours, three cubes at three days,
and three cubes at seven days.

7.10.4. All samples shall be labeled, and their batch placement location
noted.

7.10.5. Minimum compressive strength shall be 80 MPa (12,000psi) at


7days.

7.11. EPOXY GROUT CURING / PROTECTION & FINAL INSPECTION.

7.11.1. Suitable shelter or enclosures shall be provided to protect the


grouted foundations from direct sunlight and weather

12
CUSTOMER: BI / JOB CONTRACT
SAUDI ARAMCO 10-00622 6600044086

PLANT LOCATION:
JUBAIL SAUDI ARABIA QA/P-EPG-001.Doc
PROJECT: Rev.
Br. CAT International Sh. 13 of 13
Co. Ltd. BERRI DEVELOPMENT – EXPAND WATER INJECTION 01
SYSTEM

7.11.2. Foundation and baseplate temperature are within the acceptable


range specified by the grout manufacturer until the grout has cured.

7.11.3. The grout shall be checked for voids after the grout has cured. Any
voids shall be filled according to epoxy grout manufacturer’s
recommendations.

7.11.4. After the void grout has cured, the baseplate shall be rechecked to
ensure that all voids are filled with grout. Any voids still exist shall be
rectified.

7.11.5. Exposed expansion joints shall be sealed with the epoxy grout
manufacturer’s recommended sealant or Expansion joints shall be
sealed with RTV silicone sealant.

7.11.6. After epoxy grout has hardened, baseplate periphery shall be


sealed with RTV silicone sealant.

7.11.7. The final level of the epoxy grout is flush with the top horizontal
chamfer edges built into the formwork

8. RECORDS

Inspection, Certificates, and records relevant to inspection and testing shall be kept
by the QA/QC Department on Site for the duration of the project and transferred to
the Area Head Office, at the achievement of the Project, to be filed, archived, and
kept for a period of Three years

9. REFERENCES

CAT-QAM-001.Doc – Quality Assurance Manual


SAES-Q-011
01 SAES-Q-007
PIP STS0360
PIP REIE 686
Applicable SATIPS and reporting formats will be referenced once discussed with
the Project Inspection Representative.

10. ATTACHMENTS

10.1. SATIP-Q-011-01 – Epoxy Grout for Machinery Support


10.2. Sample IFC drawings
10.3. DCP – Flow-Grout EPCG MTDS
10.4. DCP – Flow-Grout EPCG MOS
10.5. DCP – Flow-Grout EPCG MSDS

13
SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.00 31-Mar-18
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Epoxy Grout For Machinery Support SATIP-Q-011-01 14-May-18 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

1.0 DOCUMENT REVIEW

Contractor - "RH" of Documents and "H" for Material


Sampling and Testing.
Sampling, Testing Epoxy Grout and
SAIC-Q- S.ARAMCO - "RH" of Documents and "H" for Material
1.1 Review of Compressive Strength Test SAIC-Q-1051
1051
RH /H RH /H Sampling and Testing for Mega Projects for first 2 days
Report
production and "W" the remaining production days and
on other Projects.

RECEIVING
2.0
INSPECTION

Grout Materials Receiving and Storage SAIC-Q- S. ARAMCO - Witness first two days delivery of grout
2.1
Inspection
SAIC-Q-1052
1052
W S material and once every 5 occurrences thereafter.

3.0 INSTALLATION

SAIC-Q-
3.1 Epoxy Grout Pre-installation Inspection SAIC-Q-1053
1053
H H

Contractor - "H" for Material Sampling and Testing.


S. ARAMCO - "H" for Material Sampling and Testing for
Grout Mixing, Placement, Sampling & SAIC-Q-
3.2
Testing Inspection
SAIC-Q-1054
1054
H H/ W first 2 batches and once every 5 batches thereafter on
Mega Projects. "W" for Material Sampling and Testing
for other Projects.

Foundation and Grout Curing/ SAIC-Q-


3.3
Protection and Final Inspection
SAIC-Q-1055
1055
W W

4.0 PRE-COMMISSIONING

4.1 Not Applicable

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU - 14-May-2018 - REV. 2018.03.00 (Standards Cutoff -March 31, 2018) Rev. 2018.03.00 31-Mar-18
SATIP No. APPROVED DATE DISCIPLINE:
SAUDI ARAMCO TYPICAL INSPECTION PLAN
Epoxy Grout For Machinery Support SATIP-Q-011-01 14-May-18 CIVIL
PROJECT TITLE: WBS/BI/JO/NO. CONTRACTOR/SUBCONTRACTOR

INSPECTION RESPONSIBILITY
ITEM PROJECT PHASE & QUALITY QUALITY ASSIGNMENTS
TASK / ACTIVITY REMARKS
NO. ACTIVITY CODE PROCEDURE RECORD SAUDI
CNTRCTR
ARAMCO

GENERAL NOTES
The first three incidents of each Inspection or testing activity listed require 100 % participation by Saudi Aramco Site Inspection Personnel. After this period, Saudi Aramco Inspection may adjust
1 the levels of Saudi Aramco participation based upon the Contractor’s performance.
2 Surveillance: QA/QC organization to monitor work in progress without notice from Construction Organization
Witness: QA/QC organization shall be notified of the timing of Inspection or test in advance. However, the inspection or test shall be performed as scheduled if the QA/QC organization
3 representative is not present.
Hold: QA/QC organization shall be notified of the timing of inspection or test in advance. Inspection or test shall not be carried out without the QA/QC organization representative in
4 attendance.
5 If the Main Contractor delegates the assigned responsibility to the Subcontractor, then the Main Contractor will have the same degree of responsibility as assigned to Saudi Aramco.

LEGEND
H Hold Point for QC Inspection/ Test R Review of Documents
W Witness Inspection/Test RH Review and Approval of Documents
S Surveillance I 100% Contractor Inspection

Saudi Aramco: Company General Use


Technical
Datasheet
DESCRIPTION
TECHNICAL PROPERTIES @ 25 C:

Mixed density: 2.1 ± 0.1 g/cm3


thicknesses up to 300 mm. Compressive
strength*:
ASTM C579-82,
Method B

the needed properties. ASTM C580-74


Tensile strength*:
APPLICATIONS
ASTM C307-83

ASTM C531
o
C
ASTM C580-74 o
C

25 x 10-6/oC
ASTM C531-81

ASTM C413
ADVANTAGES o
C

#1):

& 35oC
strengths.
o
C
Working life: o
C
Recommended
15 - 35oC

VOC:
ASTM D2369
RESIN FILLER RATIO

Temperature @25oC

pours medium pours pours


Fill #1 Fill #2 Fill #3

ml volume: 15 - 16 cm 16 - 17 cm 18 - 19cm
BS 890

1.8 g/cm3

METHOD OF USE PLACING AND FINISHING

SUBSTRATE PREPARATION

:
MIXING
Notes: CAUTIONS

HEALTH AND SAFETY

Sheet.
CLEANING
FIRE

MORE FROM DON CONSTRUCTION PRODUCTS


PACKAGING

THICKNESSES AND SIZE LIMITATIONS

Flooring systems.

Adhesives.

YIELD Building products.

STORAGE
Method
Statement
www.dcp-int.com

Flo-Grout EPCG Method Statement


(High strength pourable epoxy foundation resin grout)
Section A : General Comments

High temperature working

It is suggested that, for temperatures above 35°C, the following guidelines are adopted as good working
practice:
(i) Unmixed materials and equipment should be stored in a cool shaded area and away from direct
sunlight.
(ii) Avoid application during peak temperature of the day.
(iii) Plan for enough materials, tools and labour to ensure continuous applicant process.

Low temperature working

It is suggested that, for temperatures below 15°C, the following guidelines are adopted as good working
practice:
(i) Store unmixed materials in a warm (preferably temperature controlled) environment, avoiding
exposure to frost or temperatures below 5oC.
(ii) Cold temperatures will decrease the flow properties of the grout.
(iii) Avoid applying the epoxy grout if there temperature around 5oC and falling.

Equipment
Personal protection : Protective overalls
: Good quality gloves and goggles
Equipment : Mixer
: Large paddle
: Empty bucket (25 ltr)
: Electrical hummer
: Chisel and hammer
: Feeding hopper

Section B : Application

1.0 Substrate Preparation

1.1 The substrate should be sound, clean and free from contamination. Surface laitance should be
removed by scabbling or grit blasting.
www.dcp-int.com

1.2 The concrete surfaces should be dry.


1.3 All anchor pockets, sleeves or holes drilled for anchor bolts must be free of water and cleaned from
dust and loose debris using suitable brush or compressed air.
1.4 Steel surfaces should be grit blasted to remove all rust and scale.
Base plate underside preparations:
The underside of the base plate should be clean and free from oil, grease, rust, scale or other loosely
adherent material.

2.0 Formwork

2.1 Ensure that the area to be grouted is clean, before fixing any formwork.
2.2 The formwork itself must be constructed to be water tight (leak proof), to prevent any possible grout loss
from any formwork joints. This can be achieved by sealing underneath the formwork and at the joints by
using appropriate release.
2.3 To obtain maximum flow distance (free flowing grout application), a side shutter feed (feeding hopper) with
100 mm side height should be erected to build the required hydrostatic head.
Note: At 100 mm of head, a flow distance of 1250 and2100 mm can be achieved at gap thicknesses of 40 and 75 mm
respectively @ 35oC ambient temperatures.
2.4 Pouring side: Erect formwork approximately 200 mm from the base plate edge (see sketch below) (i.e. pour
the mixed grout into the prepared forms from one side only to prevent air entrapment).
2.5 The grout should be poured from the shortest distance across the baste plate.
2.6 The formwork should be fixed in such a way as to allow easy stripping, without causing damage or stress on
the grout. Suitable formwork release agent could be used.
2.7 All dust, dirt and any other foreign materials have to be removed from the grout area before the last piece of
formwork is fixed and sealed.
2.8 Opposite the grout filling side: Erect the formwork at least 50 mm above and beyond the base plate edge.
(see sketch below).
2.9 Make air release holes (if necessary) at the highest points within any enclosed areas of the
machinery/equipment.
www.dcp-int.com

100 mm
50 mm

Feeding
Hopper
system

Opposite the filling side Pouring side

3.0 Mixing

3.1 A mechanically powered mixer or drill fitted with suitable paddle should be used to ensure proper
mixing.
3.2 Pour all the contents of the hardener pack into the base container. Make sure the hardener container
is fully emptied into the resin component. Mix the two components for 2 minutes until homogenous is
obtained.
3.3 The filler should be gradually added while mixing. Mixing should continue for 3 minutes or until a
uniform consistency obtained.

4.0 Placing
4.1 It is essential that the machine mixing capacity, material supply and labour availability is adequate to enable
the grouting operation to be carried out continuously.
4.2 Apply the grout as immediately as possible after preparation and cleaning to prevent reoxidising/rust
formation on the surfaces.
4.3 Prior to placement, ensure that all surfaces are dry and free from any standing water.
4.4 Always mix only that quantity of the grout that can be used within its pot life. Never reduce the mixing time.
4.5 Continuous grout flow during the grouting operation is essential. Sufficient grout must be available prior to
starting, and time taken to pour a mixed batch must be regulated to the time taken to prepare the next one.
4.6 The grout head must be maintained at all times so that a continuous grout flow is achieved.
4.7 When the grout reaches the open side of the formwork, and rises above the underside of the base plate,
pouring should continue slowly down the length of the base plate until completed.
4.8 In case of using Flo-Grout EPCG for pile head encapsulation, start pouring the grout down the area edges.
Move the pouring point slowly along the perimeter of the area edges; always ensure that the grout has risen
up on the sides.
www.dcp-int.com

Notes:
 If temperatures are less than 15oC, the cure rate will be slow, but eventually will go to completion if the
temperatures remain above 5oC.
 Place the grout down/along any slope, not against/up.
 Apply the grout across the shortest width of the equipment/base.
 Height of the epoxy grout: Place sufficient epoxy grout in the forms for it to rise slightly above the underside
(approximately 3 mm) of the base plate.
It is recommended that during placement of the epoxy grout, the level of the grout has to be slightly above
the level of the bottom of the base plate to ensure complete fill of the base. The final height of the epoxy grout
should be finished level with the bottom of the base or only slightly higher.
This will eliminate any subsequent breaking off or edge ‘spalling’ of the grout should the equipment be
subjected to a rapid increase in temperature later on.

Equal with
baseplate
~ 3 mm

Fresh Epoxy Grout after placing Cured Epoxy Grout

5.0 Protection

5.1 On completion of the grouting operation, all areas of grout should be protected from solar heat gain by
providing shade over the whole areas.

6.0 Cleaning

6.1 All tools should be cleaned immediately after finishing using a suitable epoxy thinner. Hardened
materials should be cleaned mechanically.
6.2 Brush away and remove any excess grout into appropriate containers for disposal before it has
hardener.
6.3 Always dispose of excess or waste materials in accordance with local regulations.

7.0 Remarks

7.1 Confirm powder type and availability for the mixing equipment.
www.dcp-int.com

7.2 Calculate the time required for preparing and mixing the epoxy grout and include tis in the program. In
many cases, a two working teams are necessary to supply the feed hopper and to maintain the work
flow. Do not reduce the mixing time, even when in a hurry.
7.3 Check the substrate in advance. Ensure that the substrate is in good condition and clean.
7.4 Do not change the product mixing ratio.
7.5 Do not subject epoxy grouts to sudden temperature changes especially during early curing stages.
7.6 Do not vibrate the epoxy grout during placing.
7.7 Wherever possible unrestrained ‘shoulders’ are to be avoided. These have a tendency to crack and/or
deboned.
7.8 Contact DCP Technical Services Department for advice on control spacing for large base plate grouting
projects.
7.9 This method statement does not include ‘Confined Spaces’ situation. For working in Confined Spaces,
ventilation system must be used and a Confined Space entry permit system should be followed under
supervision from the project health, safety and environment (HSE) department.

Section C : Approval and variations

This method statement is offered by DCP as a ‘standard proposal’ for the application of Flo-Grout EPCG. It
remains the responsibility of the Engineer to determine the correct method for any given application. Where
alternative methods are to be used, these must be submitted to DCP for approval, in writing, prior to
commencement of any work. DCP will not accept responsibility or liability for variations to the above method
statement under any other condition.
Material
Safety Data
Sheet
(MSDS)
Material SAFETY DATA SHEET
Flo-Grout EPCG - Base
1: PRODUCT AND COMPANY IDENTIFICATION

Product Name: Flo-Grout EPCG - Base


Description: Base component of three part high strength pourable epoxy foundation
resin grout
Manufacturer: DCP Saudi Co
P.O. Box 66241, Riyadh 11576 Kingdom of Saudi Arabia
Tel. + 966 11 4612003 Fax: + 966 11 2792059
www.dcp-int.com
Date Prepared: 01.10.15
MSDS Number: DCP/03/03/28-B

2: COMPOSITION / INFORMATION ON INGREDIENTS

Composition: Modified epoxy resin, nonreactive additives.


Hazardous Ingredient(s) Symbol Risk Phrases CAS No. %
Bisphenol-A epoxy resin Xi R36/38, 43 25068-38-6 > 85
Alkyl(C12-C14)glycidylether Xi, N R36/38, 43, 51/53 68609-97-2 < 15

Refer to Section 8 for Occupational Exposure Limits.

3: HAZARDS IDENTIFICATION

Hazard Information: Irritating to eyes and respiratory system.


May cause sensitization by skin contact.
Toxic to aquatic organisms, may cause long-term adverse effects in the
aquatic environment.
Classification: Xi, N. R36/38, 43, 51/53.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 1 of 6


4: FIRST AID MEASURES

Eyes: Irrigate immediately with copious quantities of water for 15 minutes,


Eyelids should be held away from the eyeball to ensure thorough rinsing.
Obtain medical attention if irritation persists.
Skin: Wash thoroughly with soap and water or suitable skin cleanser as soon as
possible. Remove contaminated clothing. Obtain medical advice if skin
disorder develops.
Inhalation: Move to fresh air. Obtain medical attention if needed.
Ingestion: Immediately give plenty of water (if possible charcoal slurry). If a person
vomits when lying on his back, place him in a recovery position. Do not
induce vomiting. Obtain medical advice.

5: FIRE FIGHTING MEASURES

Flash Point: > 150˚C.


Special Exposure Hazards: Formation of toxic gases is possible during heating or in case of fire.
Extinguishing Media: Foam, dry powder, carbon dioxide, water spray jet.
Personal Protective Equipment: Wear protective clothing and use self-contained breathing apparatus.

6: ACCIDENTAL RELEASE MEASURES

Personal Precautions: Put on adequate protective equipment.


Environmental Precautions: Keep away from drains, surface-water, ground-water and soil.
Decontamination Procedures: Collect as much as possible in a container for disposal. Soak up the
remainder with inert absorbent. Disposal according to local regulations.

7: HANDLING AND STORAGE

Handling: Do not breathe vapour. Avoid contact with skin and eyes.
Storage: Keep in a dry cool ventilated place. Direct sunshine should be avoided.
Keep away from ignition sources – No smoking.
Keep container tightly closed.
Keep away from food, drinks and animal food.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 2 of 6


8: EXPOSURE CONTROLS AND PERSONAL PROTECTION

Ingestion: Prevent eating, drinking or smoking in the area of product use.


Eye Contact: Safety glasses or chemical goggles.
Skin Contact: Impervious gloves (e.g. PVC).
Inhalation: When mist occurs during spraying operations, wear suitable respiratory
protective equipment.
Respiratory Protection: In case of insufficient ventilation, wear suitable equipment.
Engineering Controls: Use only in well ventilated areas. Local exhaust ventilation is
recommended.

9: PHYSICAL AND CHEMICAL PROPERTIES

Form: Viscous liquid


Colour: White
Odour: Weak
Flash Point (closed cup) (oC): > 150
o
Boiling Point ( C): Not applicable
Explosive Properties (%): Not applicable
o
Freezing Point ( C): Not applicable
o
Relative Density (@25 C): 1.10 – 1.20
Water Solubility: Insoluble

10: STABILITY AND REACTIVITY

Stability: Stable.
Conditions to Avoid: Excessive heating. Direct sunshine should be avoided. Electric discharge.
Chemical Incompatibility: Strong acid, strong base, strong oxidizer and amines.
Hazardous Decomposition Products: Formation of toxic gases is possible during heating or in case of fire.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 3 of 6


11: TOXICOLOGICAL INFORMATION

The following toxicological assessment is based on knowledge of the toxicity of the product’s components.
Expected oral LD50, rat > 3000 mg/kg.
Health Effects
On Eyes: Irritant.
On Skin: Irritant.
By Inhalation: Irritant.
By Ingestion: Irritant.
Chronic: Not applicable.

12: ECOLOGICAL INFORMATION

Environmental Assessment: When used and disposed off as intended, no adverse environmental
effects are foreseen.
Mobility: Not applicable.
Degradability: Not biodegradable.
Bioaccumulation: Not applicable.
Acute Fish Toxicity: Toxic to aquatic organisms.

13: DISPOSAL CONSIDERATION

Disposal must be in accordance with local and national legislation.


Unused Product: Dispose off through an authorized waste contractor to a licensed site.
Used/ Contaminated Product: As for unused product.
Packaging: May be steam cleaned and recycled.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 4 of 6


14: TRANSPORT INFORMATION

UN/SI Number: 3082


Transport Name: Environmentally hazardous substance, liquid, n.o.s.

Transport Type: Class: Pack Group: Item: Marine Pollutant:

At Sea IMO 9 III No

Air Transport IATA/ICAO 9 III

At land RID/ADR 9 III

15: REGULATORY INFORMATION

Hazard Label Data: Xi N

Irritant Dangerous for


the environment

Contains: Modified epoxy resin.


Risk Phrases:
R36/38 Irritating to eyes and respiratory system.
R43 May cause sensitization by skin contact.
R51/53 Toxic to aquatic organisms, may cause long-term
adverse effects in the aquatic environment.
Safety Phrases:
S24 Avoid contact with skin.
S28 After contact with skin, wash immediately with plenty of
water.
S37/39 Wear suitable gloves and eye/face protection.
S60 This material and its container must be disposed of as
hazardous waste.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 5 of 6


16: OTHER INFORMATION

Issue Date: 01/10/2015 Revised Date:

Disclaimer: The information contained herein is derived from the best available sources and is
believed to be accurate. However, no guarantee is expressed or implied regarding
the accuracy of the data given in the use of this product.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG - Base Page 6 of 6


Material SAFETY DATA SHEET
Flo-Grout EPCG - Hardener
1: PRODUCT AND COMPANY IDENTIFICATION

Product Name: Flo-Grout EPCG - Hardener


Description: Hardener component of three part high strength pourable epoxy
foundation resin grout
Manufacturer: DCP Saudi Co
P.O. Box 66241, Riyadh 11576 Kingdom of Saudi Arabia
Tel. + 966 11 4612003 Fax: + 966 11 2792059
www.dcp-int.com
Date Prepared: 01.10.15
MSDS Number: DCP/03/03/28-H

2: COMPOSITION / INFORMATION ON INGREDIENTS

Composition: Epoxy resin hardening agent.

Hazardous Ingredient(s) Symbol Risk Phrases CAS No. %


Polyoxypropylendiamin C, Xn R22, 34 9046-10-0 10 - 65
nonylphenol C, Xn, N R22, 34, 62, 50/53, 63 25154-52-3 10 - 55
2-piperazin-1-ylethylamine C, Xn R21/22, 34, 43, 52/53 140-31-8 10 - 35

Refer to Section 8 for Occupational Exposure Limits.

3: HAZARDS IDENTIFICATION

Hazard Information: Corrosive.


Harmful if swallowed.
Causes burns.
Irritating to eyes and skin.
May cause sensitisation by skin contact.
Toxic to aquatic organisms, may cause long-term adverse effects in the
aquatic environment.
Possible risk of impaired fertility.
Possible risk of harm to the unborn child.
Classification: C, Xn, N. R22, 34, 36/38, 43, 51/53, 62, 63.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 1 of 6


4: FIRST AID MEASURES

Eyes: Irrigate opened eye immediately with copious quantities of water for 15
minutes. Obtain medical attention immediately.
Skin: Wash immediately with soap and water or suitable skin cleanser. Remove
contaminated clothes and shoes. Obtain medical advice if irritation
persists.
Inhalation: Remove from exposure; obtain medical attention if respiratory irritation
develops or if breathing becomes difficult.
Ingestion: Drink plenty of water. Do not induce vomiting. Obtain medical attention.
Beware of aspiration if vomiting occurs.
General: Symptoms of poisoning may even occur after several hours; therefore
medical observation for at least 48 hours after the accident.

5: FIRE FIGHTING MEASURES

Flash Point (Closed Cup): > 100oC.


Extinguishing Media: CO2, extinguishing powder or water jet. Fight larger fires with water jet or
alcohol-resistant foam. For safety reasons do not use Water with a full
water jet.
Personal Protective Equipment: Self-contained breathing apparatus. Standard aluminized suit.
Special Exposure Hazards: Toxic fumes. Carbon monoxide (CO), nitrogen oxides (NOx).

6: ACCIDENTAL RELEASE MEASURES

Personal Precautions: Ensure adequate ventilation immediately issue NO SMOKING and NO


NAKED FLAMES warnings. Wear suitable protective clothing, gloves and
eye/face protection.
Environmental Precautions: Prevent entry into drains, sewers and water courses.
Decontamination Procedures: Soak up with inert absorbent like sand. Gather into labeled containers.
Dispose off as applicable regulations.

7: HANDLING AND STORAGE

Handling: Maintain good standards of personal hygiene. Avoid skin and eye contact.
Do not eat, drink or smoke whilst using this product. Ensure adequate
ventilation. In case of insufficient ventilation, wear suitable respiratory
equipment.
Storage: Keep container tightly closed in a cool dry area away from sources of heat
and out of direct sunlight to avoid pressure build up. Store in conformity
with local fire regulations. Store away from sources of ignition. Keep away
from food containers. Store at 15 - 25°C.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 2 of 6


8: EXPOSURE CONTROLS AND PERSONAL PROTECTION

Eye Protection: Tightly sealed safety glasses/goggles.


Skin Protection: Impervious gloves (e.g. PVC). Suitable protective clothing.
Respiratory Protection: Breathing filters apparatus.
Hygiene Measures: Change contaminated clothing and clean before re-use.
Engineering Controls: Use only in well ventilated area. Local exhaust ventilation is
recommended.
Exposure Guidelines: None assigned.

9: PHYSICAL AND CHEMICAL PROPERTIES

Form: Liquid
Colour: Yellowish
Odour: Amine-like
o
Boiling Point ( C): > 200
o
Flash Point (closed cup) ( C): > 100
o
Autoflammability ( C): Product is not selfigniting
Explosive Properties (%): Product is not explosive
o
Relative Density (@25 C): 0.98 – 1.00
Water Solubility: Not miscible or difficult to mix

10: STABILITY AND REACTIVITY

Stability: Contains volatile solvent. Stable if used as directed.


Conditions to Avoid: Any source of ignition. Temperature above 35oC.
Chemical Incompatibility: Strong acids. Strong alkalis. Strong oxidizing agents.
Hazardous Decomposition Products: Thermal decomposition yield oxides of carbon, nitrogen compounds.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 3 of 6


11: TOXICOLOGICAL INFORMATION

The following toxicological assessment is based on knowledge of the toxicity of the product’s components.
Expected oral LD50, rat > 1000 mg/kg.
Classified as skin sensitizer.
Health Effects
On Eyes: Strong caustic effect.
On Skin: Corrosive - causes burns. May cause sensitization.
By Inhalation: Harmful by inhalation. May cause respiratory irritation.
By Ingestion: Harmful if swallowed. May cause irritation of mouth, throat and digestive
tract. Ingestion of significant amounts may result in severe systemic
effects.
Chronic: Repeated and prolonged skin contact will result in severe irritation leading
to burns.

12: ECOLOGICAL INFORMATION

Environmental Assessment: When used and disposed as intended, no adverse environmental effects
are foreseen.
Mobility: Mobile liquid. Insoluble in water.
Degradability: Not readily biodegradable.
Bioaccumulation: Not Known.
Acute Fish Toxicity: Expected to be ecotoxic to fish/ daphnia/ algae.

13: DISPOSAL CONSIDERATION

Disposal must be in accordance with local and national legislation.


Unused Product: Classified as a special waste. May be reacted with base component to give
an inert polymeric material.
Used/ Contaminated Product: Classified as a special waste. Dispose off through an authorized waste
contractor to a licensed site.
Packaging: Must be disposed off through an authorized waste contractor.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 4 of 6


14: TRANSPORT INFORMATION

UN Number: 1760
Transport Name: Corrosive substances.

Transport Type: Class: Pack Group: Marine Pollutant

At Sea IMDG 8 II Yes

Air Transport IATA/ICAO 8 II

At land RID/ADR 8 III

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 5 of 6


15: REGULATORY INFORMATION

Hazard Label Data: C N

Corrosive Dangerous for


the environment

Named Ingredients: 2-piperazin-1-ylethylamine


Nonylphenol
UN Number: 1760

Risk Phrases: R22 Harmful if swallowed.


R34 Causes burns.
R36/38 Irritating to eyes and skin.
R43 May cause sensitisation by skin contact.
R51/53 Toxic to aquatic organisms, may cause long-term
adverse effects in the aquatic environment.
R62 Possible risk of impaired fertility.
R63 Possible risk of harm to the unborn child.
Safety Phrases:
S26 In case of contact with eyes, rinse immediately with
plenty of water and seek medical advice.
S28 After contact with skin, wash immediately with plenty of
water.
S36/37/39 Wear suitable protective clothing, gloves and eye/face
protection.
S45 In case of accident or if you feel unwell, seek medical
advice immediately (show the label where possible).
S60 This material and its container must be disposed of as
hazardous waste.

16: OTHER INFORMATION

Issue Date: 01/10/2015 Revised Date:

Disclaimer: The information contained herein is derived from the best available sources and is
believed to be accurate. However, no guarantee is expressed or implied regarding
the accuracy of the data given in the use of this product.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Hardener Page 6 of 6


Material SAFETY DATA SHEET
Flo-Grout EPCG - Filler
1: PRODUCT AND COMPANY IDENTIFICATION

Product Name: Flo-Grout EPCG - Filler


Description: Filler component of three part high strength pourable epoxy foundation
resin grout
Manufacturer: DCP Saudi Co
P.O. Box 66241, Riyadh 11576 Kingdom of Saudi Arabia
Tel. + 966 11 4612003 Fax: + 966 11 2792059
www.dcp-int.com
Date Prepared: 01.10.15
MSDS Number: DCP/03/03/28-F

2: COMPOSITION / INFORMATION ON INGREDIENTS

Composition: Mixture of silica sand.

3: HAZARDS IDENTIFICATION

Hazard Information: Long term inhalation may cause health problems.

4: FIRST AID MEASURES

Eyes: Irrigate immediately with copious quantities of water for 15 minutes.


Obtain medical attention if irritation persists.
Skin: Wash immediately with soap and plenty of water or suitable skin cleanser.
Inhalation: Remove from exposure; obtain medical attention if any discomfort
continues.
Ingestion: Rinse mouth thoroughly. Drink plenty of water. Do not induce vomiting.
Obtain medical attention if any discomfort continues.

5: FIRE FIGHTING MEASURES

Extinguishing Media: None, not flammable.


Personal Protective Equipment: None.
Special Exposure Hazards: None.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Filler Page 1 of 3


6: ACCIDENTAL RELEASE MEASURES

Personal Precautions: Avoid inhalation of dust.


Environmental Precautions: Prevent entry into drains, sewers and water courses.
Decontamination Procedures: Reuse if possible, or collect in plastic bags, residues can be removed with
vacuum cleaner.

7: HANDLING AND STORAGE

Handling: Avoid breathing dust. In case of insufficient ventilation, wear suitable


respiratory equipment. Avoid skin and eye contact.
Storage: Store in a dry, cool area.

8: EXPOSURE CONTROLS AND PERSONAL PROTECTION

Eye Protection: Safety glasses/goggles.


Skin Protection: Use suitable protective gloves.
Respiratory Protection: Wear approved dust mask.
Hygiene Measures: Wear appropriate clothing to prevent repeated skin contact.
Engineering Controls: Use in well ventilated area.
Exposure Guidelines:
Silica, crystalline TWA (8 hours): 4 mg/m3 (respirable dust)

9: PHYSICAL AND CHEMICAL PROPERTIES

Form: Granulated powder


Colour: Pigmented
Odour: Not applicable
pH (concentrate): Not applicable
o
Boiling Point ( C): Not applicable
Flash Point (closed cup) (oC): Not applicable
Water Solubility: Insoluble

10: STABILITY AND REACTIVITY

Stability: Stable.
Conditions to Avoid: None Known.
Chemical Incompatibility: None.
Hazardous Decomposition Products: None.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Filler Page 2 of 3


11: TOXICOLOGICAL INFORMATION

Health Effects
On Eyes: Irritating and may injure eye tissue if not removed promptly.
On Skin: Unlikely to irritate on brief or occasional exposure.
By Inhalation: May cause respiratory irritation.
By Ingestion: Unlikely to occur. Low order of acute toxicity.
Chronic: Respirable dust constitutes a health hazard if inhaled over long period.
Inhalation of free particles of free silica, in the respirable range can give
rise to fibrosis of the lung.

12: ECOLOGICAL INFORMATION

Environmental Assessment: Not expected to be hazardous to the environment.


Mobility: Insoluble in water.
Degradability: Not applicable.
Bioaccumulation: Not expected to be bioaccumulate.
Acute Fish Toxicity: Not expected to be ecotoxic to fish/daphnia/algae.

13: DISPOSAL CONSIDERATION

Disposal must be in accordance with local and national legislation.


Unused Product: Dispose off in an approved manner.
Used/ Contaminated Product: As for unused product.
Packaging: Must be disposed off as per the local authority.

14: TRANSPORT INFORMATION

The product is not classified as dangerous for transport.

15: REGULATORY INFORMATION

Safety Phrases: S22 Don’t breathe dust.

16: OTHER INFORMATION

Issue Date: 01/10/2015 Revised Date:

Disclaimer: The information contained herein is derived from the best available sources and is
believed to be accurate. However, no guarantee is expressed or implied regarding
the accuracy of the data given in the use of this product.

Issue No.: 01 Rev. No.: 00 Flo-Grout EPCG – Filler Page 3 of 3

You might also like