1. Basis specification

Item Specification

Model HFT-90N-6CE

1. Rating input 600V 700 Hz

(1) surroundings temperature 0~40℃


(2) that there is not (dew 30~90% humidity)
(3) cooling quantity of water 3 L/min over
(4) cooling water temperature 30℃below
2. Use condition
(5) Max.water pressure 1Mpa less than(for water inlet)
(6) height above sea level 1000 or less m
(7) To not exist atmosphere corrosiveness gas etc.
(8) dirt density 1 mg/m3 following

3. Resisting pressure AC2500V-one minute

4. Landing C class (400V for) the landing construction work

Turn ratio 56
Secondary non-load
10.7V
voltage
5. Secondary max
18,000A
Out currents
power Rating capacity 90kVA

Max capacity 193kVA

Duty cycle 10% (10 cycle heat max)

6. Insulation class F class

(1) ratings 120VAC 15A / 240VAC 8.3A


7. Thermostat capacity (2) cycles 100,000 cycles drift of open temperature should be
2455RBV-117-281 within 3% of initial temperature after testing
(3) contact resistance less than 100mΩ DC0.7A 1V

7. External form measure 130 (W)×190 (H)×392 (L)

8. Mass 27kg

-1-
2. Attachment

Please do connection etc. in accordance with the following procedure, when you are used the inverter
transformer.

(1) The attachment of the inverter transformer


Please tighten the 8 hence top with the bolt of M10 by utilizing the tap of the aluminum frame, when
you attach the inverter transformer to the bracket of welding gun etc. The effective tap depth of the
aluminum frame is 19 mm. Please pay attention sufficient to the selection of the bolt so as not to
become 19 or more mm.

(2) The attachment of the secondary conductors


Please tighten it by utilizing, when you attach the secondary conductors with the bolt of M8 (+) the
taps of the secondary terminals of side 4 place, (-) the side 4 places. The effective tap depths of the
secondary terminals are 18 mm. Please pay attention sufficient to the selection of the bolt so as not
to become 18 or more mm.

(3) Connection of cooling water


As for cooling water, there are the entrance of a diode and transformer at the side of the secondary
terminals. It supplies it previously from the diode without fail, in the case that it is connected (PT1/8)
the diode and transformer to the series. It drains to the transformer, after that. (There is the fear that
the semiconductor (the diode) that was incorporated inside damage, when it supplies it conversely.
Therefore please pay attention sufficient toward the supply.)

(4) The attachment of the signal line for the thermostat


You connect the signal line for the thermostat from inverter control unit etc., to the terminal unit with
signal line attachment for the thermostat that is in an input end aluminum frame.

(5) The attachment of the primary input cable


You connect to the tap with the input terminal unit and also ground cable attachment that are in an
input end aluminum frame a piece the ground cable of two pieces, (power cable the primary input
cable. Please tighten it firmly to there be not looseness at the time of connection. The joint of the
power cable is M6.Therefore please use the terminal that it matched.

(6) The confirmation of cooling water leak


It pours cooling water actually, whether or not you are not doing water leak from the secondary
conductors and other parts that attached and please confirm.