LAPORAN MINGGU KE 11

PEKERJAAN : RENOVASI RUMAH (PENAMBAHAN LANTAI 2)


TAHUN : 2024
L0KASI : KOT MAKASSAR, SULAWESI SELATAN
OWNER : PAK LUCAS MONGOLO

URAIAN RENCANA ANGGARAN BIAYA


VOLUME REALISASI MINGGU LALU MINGGU INI KOMULATIF BOBOT
NO URAIAN PEKERJAAN BOBOT (%)
Vol. Sat. Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%)
1 2
A PEKERJAAN PENDAHULUAN
- Pek. Pembersihan Lahan 1.00 Ls 0.22 1.00 100.00 0.22 0.00 0.00 1.00 100.00 0.22
- Pek. Pembongkran 1.00 Ls 0.57 1.00 100.00 0.57 0.00 0.00 1.00 100.00 0.57
B PEKERJAAN STRUKTUR - -
I PEKERJAAN STRUKTUR BETON BERTULANG - -
1 PEK. PONDASI POER - -
- Pek. Galian Tanah 10.24 M3 0.28 10.24 100.00 0.28 0.00 0.00 10.24 100.00 0.28
- Pek. Beton K.250 3.01 M3 0.71 3.01 100.00 0.71 0.00 0.00 3.01 100.00 0.71
- Pek. Pembesian 456.68 Kg 1.91 456.68 100.00 1.91 0.00 0.00 456.68 100.00 1.91
- Pek. Bekisting 27.84 M2 0.39 27.84 100.00 0.39 0.00 0.00 27.84 100.00 0.39
2 PEK SLOEF - -
- Pek. Beton K.175 2.28 M3 0.54 2.28 100.00 0.54 0.00 0.00 2.28 100.00 0.54
- Pek. Pembesian 411.22 Kg 1.72 411.22 100.00 1.72 0.00 0.00 411.22 100.00 1.72
- Pek. Bekisting 18.18 M2 0.54 18.18 100.00 0.54 0.00 0.00 18.18 100.00 0.54
3 PEK. KOLOM K1 (400 x 150) - -
- Pek. Beton K.175 3.84 M3 0.91 3.84 100.00 0.91 0.00 0.00 3.84 100.00 0.91
- Pek. Pembesian 906.67 Kg 3.79 906.67 100.00 3.79 0.00 0.00 906.67 100.00 3.79
- Pek. Bekisting 70.40 M2 2.83 70.40 100.00 2.83 0.00 0.00 70.40 100.00 2.83
4 PEK. KOLOM K2 (150 x 150) - -
- Pek. Beton K.175 0.90 M3 0.21 - - 0.00 0.00 0.00 - - 0.00
- Pek. Pembesian 177.60 Kg 0.74 135.43 76.26 0.57 0.00 0.00 135.43 76.26 0.57
- Pek. Bekisting 12.00 M2 0.48 - - 0.00 0.00 0.00 - - 0.00
5 PEK. BALOK LATEI (150 / 150) - -
- Pek. Beton K.175 0.31 M3 0.07 - - 0.00 0.00 0.00 - - 0.00
- Pek. Pembesian 32.96 Kg 0.14 - - 0.00 0.00 0.00 - - 0.00
- Pek. Bekisting 4.14 M2 0.06 - - 0.00 0.00 0.00 - - 0.00
6 PEK. BALOK INDUK BI (250/300) - -
- Pek. Beton K.175 5.42 M3 1.28 5.42 100.00 1.28 0.00 0.00 5.42 100.00 1.28
- Pek. Pembesian 768.70 Kg 3.21 768.70 100.00 3.21 0.00 0.00 768.70 100.00 3.21
- Pek. Bekisting 58.92 M2 2.40 58.92 100.00 2.40 0.00 0.00 58.92 100.00 2.40
7 PEK. BALOK ANAK BA (200/250) - -
- Pek. Beton K.175 1.71 M3 0.41 1.71 100.00 0.41 0.00 0.00 1.71 100.00 0.41
- Pek. Pembesian 144.08 Kg 0.60 144.08 100.00 0.60 0.00 0.00 144.08 100.00 0.60
- Pek. Bekisting 18.69 M2 0.76 18.69 100.00 0.76 0.00 0.00 18.69 100.00 0.76
8 PEK. RING BALOK RB (150 / 200) - -
- Pek. Beton K.175 3.22 M3 0.76 - - 0.00 0.00 0.00 - - 0.00
- Pek. Wiremesh M.8 484.40 Kg 2.02 - - 0.00 0.00 0.00 - - 0.00
- Pek. Bekisting 42.92 M2 1.75 - - 0.00 0.00 0.00 - - 0.00
9 PEK. PLAT BETON - -
- Pek. Beton K.175 8.00 M3 1.90 8.00 100.00 1.90 0.00 0.00 8.00 100.00 1.90
- Pek. Pembesian 484.40 Kg 2.13 484.40 100.00 2.13 0.00 0.00 484.40 100.00 2.13
- Pek. Bondek 0.65 88.90 M2 2.90 88.90 100.00 2.90 0.00 0.00 88.90 100.00 2.90
10 PEK. DAK TALANG BETON - -
- Pek. Beton K.175 1.38 M3 0.33 - - 0.00 0.00 0.00 - - 0.00
- Pek. Pembesian 192.70 Kg 0.81 - - 0.00 0.00 0.00 - - 0.00
- Pek. Bekisting 19.66 M2 0.27 - - 0.00 0.00 0.00 - - 0.00
11 Pek. Lantai Kerja Beton K-175 - 0.00
II PEKERJAAN STRUKTUR DAN PENUTUP ATAP -
1 PEK. RANGKA ATAP SPANDEK A -
- Pek. Rangka Baja Ringan 76.29 M2 2.72 - - 0.00 0.00 0.00 - - 0.00
- Pek. Atap Spandek 0,35 76.29 M2 1.02 - - 0.00 0.00 0.00 - - 0.00
- Pek. Lisplank Woodplank 400.20.8 mm 15.09 M' 0.17 - - 0.00 0.00 0.00 - - 0.00
2 PEK. RANGKA ATAP SPANDEK B - -
- Pek. Rangka Baja Ringan - M2 0 -
- Pek. Atap Spandek 0,35 - M2 0 -
- Pek. Lisplank Woodplank 400.20.8 mm - M' 0 -
VOLUME REALISASI MINGGU LALU MINGGU INI KOMULATIF BOBOT
NO URAIAN PEKERJAAN BOBOT (%)
Vol. Sat. Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%)
1 2
C PEKERJAAN ARSITEKTUR -
I PEKERJAAN DINDING -
1 PEKERJAAN DINDING -
- Pas Batu bata 60.53 M2 1.85 15.13 25.00 0.46 21.19 35 0.65 36.32 60.00 1.11
- Pas. Bata Ringan T.10cm 432.48 M2 13.19 - - 0.00 0.00 0.00 - - 0.00
- Pek. Plesteran 1SP : 4PP 864.96 M2 6.55 - - 0.00 0.00 0.00 - - 0.00
- Pek. Acian 864.96 M2 5.75 - - 0.00 0.00 0.00 - - 0.00
- Beton Profil 7.00 M2 0.37 - - 0.00 0.00 0.00 - - 0.00
II PEKERJAAN LANTAI DAN DINDING KERAMIK - -
1 PEK. FINISHING KERAMIK - -
- Pas. Granit Uk. 60x60 Titanio Staturio Ex. Indogress 133.00 M2 5.21 - - 0.00 0.00 0.00 - - 0.00
- Pas. Keramik Uk. 30x30 Unpolished 31.06 M2 1.17 - - 0.00 0.00 0.00 - - 0.00
- Pas. Keramik Uk. 30x60 Polished 14.22 M2 0.63 - - 0.00 0.00 0.00 - - 0.00
III PEKERJAAN PLAFOND - -
1 PEK. PEMBONGKARAN PLAFON - -
- Pek. Pembongkaran Plafon Gypsum 66.50 M2 0.22 66.50 100.00 0.22 0.00 0.00 66.50 100.00 0.22
2 PEK. RANGKA PLAFOND - -
- Pek. Rangka Hollow 40.40.3,5 60x60 145.90 M2 3.89 - - 0.00 0.00 0.00 - - 0.00
3 PEK. FINIFHING PLAFOND - -
- Pek. Plafon PVC Motif 145.90 M2 3.81 - - 0.00 0.00 0.00 - - 0.00
- Pek .List Plafon PVC Motif 214.60 M' 0.93 - - 0.00 0.00 0.00 - - 0.00
IV PEKERJAAN KUSEN PINTU DAN JENDELA - -
1 Pintu Entrance PE (2 UNIT) - -
- Daun Pintu Multiplek Rangka Kayu Fin. HPL 2.00 BH 1.09 - - 0.00 0.00 0.00 - - 0.00
2 Pintu Kamar P1 (3 UNIT) - -
- Daun Pintu Multiplek Rangka Kayu Fin. HPL 3.00 BH 0.98 - - 0.00 0.00 0.00 - - 0.00
3 Pintu Kamulfase PK (1 UNIT) - -
- Daun Pintu Multiplek Rangka Kayu 1.00 BH 0.22 - - 0.00 0.00 0.00 - - 0.00
- Wall Panel WPC 5.40 M2 0.41 - - 0.00 0.00 0.00 - - 0.00
4 Pintu Toilet PT ( 1 UNIT ) - -
- Pintu WC PVC 1.00 BH 0.18 - - 0.00 0.00 0.00 - - 0.00
5 Jendela J1 (2 UNIT) - -
- Kusen Aluminium 4'' + Kaca 5mm 2.00 BH 0.74 - - 0.00 0.00 0.00 - - 0.00
6 Bouven Light BV (2 UNIT) - -
- Kusen Rangka Aluminium 4'' + Kaca 5mm 2.00 BH 0.15 - - 0.00 0.00 0.00 - - 0.00
V PEKERJAAN PENGECETAN - -
1 Pek. Pengecetan Exterior - -
- Pek. Pengecetan Waterprof 145.60 M2 1.74 - - 0.00 0.00 0.00 - - 0.00
2 Pek. Pengecetan Interior - -
- Pek. Pengecetan Dinding 334.68 M2 2.57 - - 0.00 0.00 0.00 - - 0.00
3 Pek. Pengecetan Dak Beton - -
- Pek. Pengecetan Waterprof 24.58 M2 0.29 - - 0.00 0.00 0.00 - - 0.00
VI PEKERJAAN RAIRLING - -
1 Pek. Railing Tangga - -
- Pek. Railing Tangga Besi Hollow 7.20 M2 1.10 - - 0.00 0.00 0.00 - - 0.00
2 Pek. Railing Balkon - -
- Pek. Railing Custom 12.00 M2 2.22 - - 0.00 0.00 0.00 - - 0.00
D MEKANIKAL, ELEKTRIKAL, PLUMBING - -
1 PEKERJAAN ELEKTRIKAL - -
- MCB 3.00 Ttk 0.04 - - 0.00 0.00 0.00 - - 0.00
- Saklar Tunggal 4.00 Ttk 0.05 - - 0.00 0.00 0.00 - - 0.00
- Saklar Ganda 3.00 Ttk 0.05 - - 0.00 0.00 0.00 - - 0.00
- Stop Kontak 10.00 Ttk 0.14 - - 0.00 0.00 0.00 - - 0.00
- Downlight 20W White 7.00 Ttk 0.18 - - 0.00 0.00 0.00 - - 0.00
- Downlight 9W Warm 2.00 M' 0.03 - - 0.00 0.00 0.00 - - 0.00
2 PEKERJAAN PLUMBING DAN SANITASI - -
1 PEKERJAAN AIR BERSIH - -
- Shower 1.00 Bh 0.04 - - 0.00 0.00 0.00 - - 0.00
- Jet Washer 1.00 Bh 0.09 - - 0.00 0.00 0.00 - - 0.00
- Kran Air 1.00 Bh 0.03 - - 0.00 0.00 0.00 - - 0.00
- Pek. Saluran Air Bersih Pipa PVC Ø 3/4 Inchi 18.00 M' 0.17 - - 0.00 0.00 0.00 - - 0.00
- Pek. Saluran WH PVC Ø 3/4 Inchi 18.00 M' 0.25 - - 0.00 0.00 0.00 - - 0.00
2 PEKERJAAN KOTOR - -
- Floor Drain 6.00 Bh 0.147 - - 0.00 0.00 0.00 - - 0.00
- Kloset Duduk Monoblock 2.00 Bh 0.967 - - 0.00 0.00 0.00 - - 0.00
- Pek. Disposal Cair Pipa PVC Ø 2 Inchi 30.00 M' 0.515 21.00 70.00 0.36 0.00 0.00 21.00 70.00 0.36
- Pek. Disposal Padat Pipa PVC Ø 3 Inchi 16.00 M' 0.506 11.20 70.00 0.35 0.00 0.00 11.20 70.00 0.35
VOLUME REALISASI MINGGU LALU MINGGU INI KOMULATIF BOBOT
NO URAIAN PEKERJAAN BOBOT (%)
Vol. Sat. Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%) Volume Realisasi Pek. (%) Bobot Pek. (%)
1 2 JUMLAH VOLUME REALISASI 100.00 VOLUME MINGGU LALU 31.95 VOLUME MINGGU INI 0.65 KOMULATIF BOBOT 32.60