Professional Documents
Culture Documents
Stage 1 - Project Integration Management-6
Stage 1 - Project Integration Management-6
Hint:
Which form of expert judgment is associated with the Develop Project Charter process?
Correct Answer: A
Explanation:
The question is asking for the form of expert judgment that might be beneficial in the development of the project charter. All of the answer choices describe forms of expert judgment.
However, only technical knowledge of the industry and focus area of the project is relevant to the Develop Project Charter process. All of the incorrect answer choices describe forms of
expert judgment for use in other project management processes. Therefore, of the available options. interviewing someone with technical knowledge of the product to be developed is
the best answer to the question asked.
Details for Each Option:
A Interview someone with technical knowledge of the product to be developed
Correct. This answer choice best describes expert judgment in technical knowledge of the industry and focus area of the project. This form of expert judgment may be beneficial in the
creation of the project charter.
B Speak with someone who specializes in the project scheduling Software
İncorrect. The project charter may include a summary milestone schedule but not at the level of detail that is provided by project scheduling Software. This form of expert judgment may
be necessary during the Develop Schedule process, but not the Develop Project Charter process.
C Meet with a group of quality assurance experts
İncorrect. A meeting with a group of quality assurance experts may be beneficial in the development of the quality management plan. However, the quality management plan is not
created until later in the project during project planning.
D Talk with the individual in charge of the organization's Communications technology
İncorrect. Expert judgment in the organization's Communications technologies may be useful in the development of the Communications management plan, but this level of detail is not
necessary for the creation of the project charter.
Incorrect. There is no Information in the question to determine if the project involved any procurements.
Your research assistant may have found a better way to save lives. Think about what needs to happen first to make sure this is possible.
Correct Answer: D
Explanation:
A change request is a formal proposal to modify a document deliverable, or baseline. After a change request has been submitted, it must be reviewed and analyzed using the Perform Integrated Change Control process as outlined in the change
management plan. This includes an analysis of the impact of the change request on project constraints such as scope, schedule, cost, quality, risk, etc. A change control board or authorized individual such as the project sponsor will review.
approve, postpone or deny change requests based on the results of this analysis. Since the question describes a situation in which a team member has already drafted a change request, the next step is to begin the Perform Integrated Change
Control process and discover in what ways (if at all) the change request impacts the project and its constraints.
A Have the members of the change control board decide on the change request
Incorrect A change request is a formal proposal to modify a document, deliverable, or baseline. After a change request has been submitted, an analysis must be carried out to determine the impact of the change request on project constraints
such as project scope, schedule, cost, quality, risk, etc. Afterward, a change control board or authorized individual, e.g., the project manager or a designated team member, may approve, postpone or deny the change requests based on the results
of the analysis. Based on the scenario described, the change request has not yet been analyzed. Since a change control board typically makes a decision 'after' analysis of a change request has been performed, this answer choice is not the best of
those provided.
Incorrect. The configuration management plan is a component of the project management plan that describes configurable items for the project and identifies which items will be recorded and updated so that the product of the project remains
consistent and operable. Before any project documentation can be updated, a change request must first be submitted and processed through the Perform Integrated Change Control process. If approved, the configuration management plan
would then be used to identify which project documents need updating as a result of the change. A better answer choice would have been to receive an approved change request and then update the project documents affected, however, that
option is not listed.
C Instruct the team to implement the change since the new vaccine may save lives
Incorrect. A change request is a formal proposal to modify a document, deliverable, or baseline. Change requests and the procedures used to analyze their impacts are part of a greater project change control system. While this change request
may result in a new vaccine that saves lives, proper change control is mandatory for every project so as to prevent scope creep, or the uncontrolled expansion to product or project scope without adjustments to time, cost, and resources. Without
a controlled analysis of the impacts of this change request on the project, it is possible greater schedule or budget issues could arise as a result of improper implementation and analysis. As such, this answer choice is not the best of those
provided.
D Make sure the impact of the change request on project constraints is analyzed
Correct. Before a change request can be implemented, an analysis of its impacts to the project must be conducted as part of the Perform Integrated Change Control process. This includes a thorough review of which project constraints the change
request will affect, and if the change request is in keeping with organizational! objectives laid out in the project management plan Once this analysis is complete, an authorized individual or a group (such as members of a change control board)
will decide on the change request. As such, this answer choice is the best of those provided.
Explanation:
Note the wording of the question, "With all deliverables accepted, the project is nearing its end." This implies that the project has entered the Close Project or Phase process and that the Validate Scope process
has already been completed. During project closure, accepting the deliverables would be redundant since this has already been done during the Validate Scope process. What is done during project closure is the
'confirmation' of the acceptance, or, in other words, final acceptance. By obtaining final acceptance, the project manager is essentially 'confirming' the delivery and formal acceptance of deliverables by the
relevant stakeholders. Sometimes, this can be viewed as ticking a checkbox in the checklist of the activities carried out during project closure. İt is like asking a question, "Have the deliverables been accepted
earlier in the project as part of the Validate Scope process?". If the answer is "Yes", check the box. This would eventually confirm that the deliverables have already been accepted and that the relevant
stakeholders are aware of this fact and agree that the project can now be closed.
Incorrect. Delivering the final product to the customer is not reliant on reassigning people and equipment to other projects. Reassignment can be done before, during, or after delivery. The release of project
resources is typically specified in the resource management plan. Additionally. if there are closing tasks that shou/d be performed by the team members, reassigning the team members before the project is
formally closed is a premature action.
B Confirm the delivery and formal acceptance of the deliverables
Correct. As part of project closure implied by the scenario, the project manager should formally confirm the delivery and formal acceptance of the deliverables. İn other words, during the Close Project or Phase
process, relevant stakeholders should be formally informed of the acceptance of the deliverables, acceptance that has been already obtained earlier during the Validate Scope process.
Incorrect. The delivery of the final product to the customer is conducted prior to the closing of the project, not after the project is closed and considered complete. Therefore, closing the project is not what the
project manager should do first.