Doc No.

GA/PRD/WI/09
Rev No. 00
WORK INSTRUCTION Date. 01.10.2018
Page 1 of 1
TITLE: KNOCK OUT

INSTRUCTIONS :

1. The poured moulds will be kept for cooling depending upon the average
thickness of the castings. The Lowest thickness less than 10mm for 2 hours, the
highest thickness more than 1&1/2 “ for 8 hours or till the castings are black hot.
2. Ensure correct direction of hitting. Knock out is purely manual.
3. Remove the castings from moulds with the help of pocking bar, hammer & over
head crane.
4. With the help of trolley or over head crane take the castings to fettling decoring
area.

Safety precautions :-

1. Use shoes
2. Use goggles
3. Mask
4. Hand gloves
5. Ear plugs

PREPARED BY PRD I/C APPROVED BY CEO