Weekly Construction Schedule
Weekly Construction Schedule
Weekly Construction Schedule
CONSULTANT: Kunhwa Engineering & Consultant Co., Ltd. JV Dongsung Engineering Consulting Co. Ltd.
(tons) 1.53 2.00 3.00 1.80 1.50 3.60 2.00 12.50 As of 25 April 2024
Protection Works
Pre-Casting of RCPC
610mm Dia.
910mm Dia. On-Hold Production,
1070mm Dia. waiting for cement
test approval
1220mm Dia.
1520mm Dia.
SUMMARY OF ACCOMPLISHMENT (THIS WEEK)
Contract Amount AMOUNT (USD) PERCENTAGE COMPLETED
SN DESCRIPTION UNIT
(Original) Previous This Week To Date Previous This Week Total
100 General Requirements USD 741,796.80 476,395.05 14,833.78 491,228.83 2.01 0.06 2.07
200 Earthworks USD 4,302,942.46 113,506.63 101,889.80 215,396.43 0.48 0.43 0.91
300 Subbase and Base Course USD 2,073,895.00 - - - - - -
400 Surface Course USD 3,348,070.10 - - - - - -
600 Drainage and Slope Protection Structures USD 9,635,971.62 233,577.50 18,207.40 251,784.90 0.98 0.08 1.06
700 Miscellaneous Structures USD 308,299.41 - - - -
800 Bio-Engineering USD 357,641.00 - - - -
Emergency Works/Daywork USD 2,282,273.48 - - - -
Provisional Sum USD 490,000.00 - - - -
Contingency Amount USD 200,000.00 10,357.41 0.04 - 0.04
Total 23,740,889.87 3.51 0.57 4.08
Submitted by: Received by: Approved by:
Project Manager - Contractor Senior Work Inspector - Consultant Team Leader - Consultant