Timor-Leste Branch Road Project (TLBRP)

Upgrading and Maintenance of Hatubuilico - Letefoho Road Section


(Km. 11+900 to Km. 30+307.88)

CONSULTANT: Kunhwa Engineering & Consultant Co., Ltd. JV Dongsung Engineering Consulting Co. Ltd.

CONTRACTOR: CHINA CIVIL ENGINEERING CONSTRUCTION CORPORATION

WEEKLY CONSTRUCTION SCHEDULE


THIS WEEK WORK (WORK DONE) NEXT WEEK (PLAN)
REMARKS
SECTION DESCRIPTION 04 May 05 May 06 May 07 May 08 May 09 May 10 May 11 May 12 May 13 May 14 May 15 May 16 May 17 May

Elevation Stake-out and Construction Limit


Km24.0~Km28.0 Km28+000 ~ Km29+500
Clearing & Grubbing
(Ha) Km24+600 ~ Km 29+500 = 6.12 Ha
200 - Earthworks

Spoil Disposal 1st TEAM: Km23+600 ~ Km24+000


Km23.30 ~ Km23.40
2nd TEAM: Km24+000 ~ Km25+500

Common, Hard & Soft Rock to


Slope Excavations
Km23.30 ~ Km23.40 1st TEAM: Km23+600 ~ Km24+000 = 9,638 cu.m be classified base on the signed
(cu.m) report by the Engineer
972.00 1530.00 1260.00 900.00 738.00 1080.00 1200.00 2nd TEAM: Km24+000 ~ Km25+500 = 21,500 cu.m
Total Rebars Fabricated =
Pre-fabrication of RCBC rebars
161,690.75 Kg
600 - Drainage and Slope

(tons) 1.53 2.00 3.00 1.80 1.50 3.60 2.00 12.50 As of 25 April 2024
Protection Works

Pre-Casting of RCPC
610mm Dia.
910mm Dia. On-Hold Production,
1070mm Dia. waiting for cement
test approval
1220mm Dia.
1520mm Dia.
SUMMARY OF ACCOMPLISHMENT (THIS WEEK)
Contract Amount AMOUNT (USD) PERCENTAGE COMPLETED
SN DESCRIPTION UNIT
(Original) Previous This Week To Date Previous This Week Total
100 General Requirements USD 741,796.80 476,395.05 14,833.78 491,228.83 2.01 0.06 2.07
200 Earthworks USD 4,302,942.46 113,506.63 101,889.80 215,396.43 0.48 0.43 0.91
300 Subbase and Base Course USD 2,073,895.00 - - - - - -
400 Surface Course USD 3,348,070.10 - - - - - -
600 Drainage and Slope Protection Structures USD 9,635,971.62 233,577.50 18,207.40 251,784.90 0.98 0.08 1.06
700 Miscellaneous Structures USD 308,299.41 - - - -
800 Bio-Engineering USD 357,641.00 - - - -
Emergency Works/Daywork USD 2,282,273.48 - - - -
Provisional Sum USD 490,000.00 - - - -
Contingency Amount USD 200,000.00 10,357.41 0.04 - 0.04
Total 23,740,889.87 3.51 0.57 4.08
Submitted by: Received by: Approved by:

Project Manager - Contractor Senior Work Inspector - Consultant Team Leader - Consultant