SPECIFICATIONS DEMOLITION
SELECTIVE DEMOLITION
PART 1- GENERAL
1.1. SECTION INCLUDES
1.1.1. Removal of designated construction as indicated on drawings.
1.1.2. Identification of utilities.
1.1.3. Removal and storage of items as indicated on drawings.
1.2. DEFENITION
1.2.1. Remove and salvage – items indicated to be removed and salvaged remain the
Employer’s property. Remove, cleaned and pack or crate items to protect against
damage. Identify contents of containers and deliver to Employee’s designated
storage area.
1.2.2. Existing to remain -Project construction indicated to remain against damage and
soiling during selective demolition.
1.3. SUBMITALS
1.3.1. Qualification Data: For firms and persons specified in “Quality Assurance”
Article to demonstrate their capabilities and experience. Includes lists of
completed projects with project names and addresses, names and addresses of
architects and Employer’s, and other information specified.
1.3.2. Proposed dust control and noise control; submit statement or drawing that
indicates the measures proposed for use.
1.3.3. Schedule of Selective Demolition Activates.
1.4. PROGECT RECORD DECUMENTS
1.4.1. Accurately record actual locations of capped utilities.
| SECTION******
SELECTIVE DEMOLITION
JALYANAH PROJECTS SELECTIVE
SPECIFICATIONS DEMOLITION
1.5.1. Confirm to referenced standards and local code for demolition work, safety of
structure, dust and noise control.
1.5.2. Obtain required permits from authorities.
1.5.3. Notify affected utility companies before starting work and comply with their
requirements.
1.5.4. Do not close or obstruct egress width to exits.
1.5.5. Conform to procedure applicable when discovering hazardous or
contaminated materials.
1.7. SEQUANCING
1.7.1. Schedule work to coincide with new construction.
1.7.2. Describe demolition removal procedures and schedule.
PART 3- EXCUTION
3.1. EXAMINATION
3.1.1. Verify that utilities have been disconnected and capped.
3.1.2. Survey existing conditions and correlate with requirements indicated to determine
extent of selective demolition.
3.1.3. Maintain existing utilities indicated to remain in service and protect them against
damage during operation.
| SECTION******
SELECTIVE DEMOLITION
JALYANAH PROJECTS SELECTIVE
SPECIFICATIONS DEMOLITION
3.1.4. When unanticipated mechanical, electrical, or structural elements that conflict with
intended function or design are encountered, investigate and measure the nature
and extent of conflict. Promptly submit a written report to Engineer.
3.1.5. Engage a professional engineer to survey condition of building to determine removing
any elements might results in structural deficiency or unplanned collapse of any
portion of structure or adjacent structures during selective demolition operations.
| SECTION******
SELECTIVE DEMOLITION
JALYANAH PROJECTS SELECTIVE
SPECIFICATIONS DEMOLITION
| SECTION******
SELECTIVE DEMOLITION
JALYANAH PROJECTS SELECTIVE
SPECIFICATIONS DEMOLITION
| SECTION******
SELECTIVE DEMOLITION
JALYANAH PROJECTS SELECTIVE
SPECIFICATIONS DEMOLITION
3.4.4. Masonry: Demolition in small sections cut masonry at juncture wit construction to
remain, using power-driven saw, then remove masonry between saw cuts.
3.5. DISPOSAL OF DEMOLISHED MATERIALS
3.5.1. Promptly dispose of demolished material. Do not allow demolished materials to
accumulate on site. Transport demolished materials and dispose of at designated
spoil areas.
END OF SECTION
| SECTION******
SELECTIVE DEMOLITION