Professional Documents
Culture Documents
HDPE Installation Procedure
HDPE Installation Procedure
SIGNATURE
DATE
ARLC/QP/013/2023 1
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
TABLE OF CONTENTS
1. Scope………………………………………………3
2. Purpose…………………………………………….3
3. Definition ………………………………………….3
5. Responsibilities…………………………….……5 and 6
1. SCOPE
ARLC/QP/013/2023 2
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
1.1 The Scope is to define the procedure that will be followed for the installation of
HDPE Pipes for the project.
2. PURPOSE
2.1 The purpose of this document is to ensure that the HDPE pipes in HDD and in
Trench for Communication systems are performed safely, efficiently, and in
accordance with the recommended working practice, and Saudi Aramco standards &
Specifications in Robaya Onshore Maintain Potential Projects (OMPP). The procedure
is intended to provide general application guidance, and establish controls for the
execution of the HDPE Pipes installations.
3. DEFINITION
ARLC/QP/013/2023 3
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
ARLC/QP/013/2023 4
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
5. RESPONSIBILITIES
5.1 QA/QC Manager: Responsible for the overall discipline of QA/QC Inspection,
verification of the project specification, documentation and QC records for final
acceptance.
5.2 HSE Manager: Responsible for Safety implementation and ensuring all safety
requirements have been implemented within the construction areas.
5.3 Telecom Engineer: Prepare and submit procedure and material submittal for
Saudi Aramco review and approval. Responsible for material requisition of approved
permanent materials, estimation and reconciliations of material final quantity, shop
drawing and as -built. Responsible to pursue and provide latest revision of IFC
drawings, procedures, material specifications, standards and technical specifications.
5.4 Telecom Supervisor: Ensure relevant permits are raised and received prior to
commencement of work, with full compliance by all electrical foremen, electricians
and labor pertaining to execution of the work in accordance with Saudi Aramco
project requirements and specifications. Review and plan the work with due
diligence. Confirm the availability of all materials, tools, equipment, and required
personnel who will carry out the work safely.
5.5 Telecom Foreman: Ensure relevant permits are raised and received prior
commencement of work, with full compliance by all associated craftsmen to the
requirements of this procedure. Responsible for the execution of the work,
manpower assignments and hourly work monitoring, and for preparing the work
activities for the electrician. Ensure the safe work atmosphere of the workmen by
conducting a daily safety reminder prior to commencement of work.
5.6 Quality Control Inspector: Monitor, on a daily basis, Telecom activities and verify
compliance to Customer’s Specifications. Perform activities in accordance with the
ARLC/QP/013/2023 5
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
Project QA Manual and Quality Control Inspection Plan. Prepare QC records daily, and
final acceptance documentation. Maintain a close working relationship with the
Customer’s Representative.
5.7 Safety Supervisor: Monitor that the work is carried out in accordance with Saudi
Aramco project safety procedures.
5.8 Store Keeper: The Store Keeper’s responsibility is to identify the location, and to
maintain preservation of the materials or equipment at the storage area, while
keeping record and Control of all the material / equipment release.
6. DETAILED PROCEDURE
Check that all the HDPE pipes and accessories materials are in
acceptable working conditions.
ARLC/QP/013/2023 6
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
Over hanging from the trailer / truck body of any HDPE Pipes
material is not allowed. Ensure that they are properly and
adequately secured / supported.
Plan the work area with separate storage, work and waste
disposal locations, to avoid congestion and enable systematic
installation.
ARLC/QP/013/2023 7
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
Check that all debris has been removed and that the trench
bottom is smooth and level and void of any items that could
deform or damage the conduit.
Ensure that all spoil is kept at least 600mm from the trench edge
during the excavation.
ARLC/QP/013/2023 8
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
ARLC/QP/013/2023 9
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
ARLC/QP/013/2023 10
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
All stages of work shall be entirely attended, inspected and test witnessed by
Contractor QC, PMT, and PID representatives in accordance with the Approved
Project Quality Control Inspection Plan and Saudi Aramco Standard requirements.
All Saudi Aramco Safety and Security Requirements and Policies shall be
observed, refer to SAES-A-114 for “Excavation and Backfill”, GI-0002.100,
SAES-B-Series, HCIS & the Safety Directives, and the Saudi Aramco Safety
Policy (Loss Prevention Policy Statement in GI-0005.002.)
Barricade the working area and secure necessary work permit prior to
commencing the work.
Wear full body harness when working at heights and Underground.
Ensure that only authorized personnel are within the affected area.
Keep the work area free from debris at all times.
The work shall be executed with the approved JSA.
Kindly refer to the sections applicable to the scope of this procedure in the
approved Project Hazard Identification Plan and Job Safety Analysis
ARLC/QP/013/2023 11
U PROJECT:
ONSHORE MAINTAIN POTENTIAL PROJECT CONTRACT NO: 6600051148
documents, and in the specific documents for each of the Contract Release
Purchase Orders.
ARLC/QP/013/2023 12