TOWELL CONSTRUCTION & CO. L.L.C.

PROJECT : 88 VILLAS AT AL KHOUDH

CHECKLIST FOR PAINTING

Area/ Bldg : Date :

Drawing No :
Location :

Sl.No. Description Obserbed results Remarks

1 Completion of plastering ,readiness for painting Yes No N.A

2 Mock up & batch certificates Yes No N.A

2 Check for type of Paint,Manufacturer & Colour shade,approval of Clients Yes No N.A

3 All joints finished smooth, patches & un eveness filled Yes No N.A

4 Surface clean, dry, free from oil, grease, loose particles ,efflorenscence Yes No N.A
& other foreign materials

5 Primer coat has done as per specification Yes No N.A

6 Check for application of putty as per specification Yes No N.A

7 All visible uneneness surface are covered by putty application Yes No N.A

8 Finishing at corners, joints uniform Yes No N.A

9 Check for application of paint in three coats as per Manufacturer's instruct. Yes No N.A

10 Check for visual inspection ie. Good opacity,uniform surface , no patchiness, Yes No N.A
free from peeling, blister & chalkiness , no discoluration & fading.

11 Check for cleanliness of area where work is carried out. Yes No N.A

12 Check for suitability & safety of scaffolding Yes No N.A

13 Touch up & repair (if any) completed Yes No N.A

TOWELL CONSTRUCTION TRAID OMAN

TCC/167/CL/022/20.01.11 Page 1 of 1