Justification for Action Priority (AP): Increased audits frequency in case of Hight risk
Risk Assessment :
*Predefined quality limits should be established to identify systematic issues that can impact subject safety or data integrity.
*Detection of deviations from the predefined quality limits should signal a need for further action.
Corrective/ Corrective/
Preventive Corrective/ Preventive
Actions not Preventive Actions closed
properly Actions in agreed
Compliance followed:4 delayed: 2 timescale: 1
Methodology risk
score Validation is Validation is Validationis
Validation of incomplete and incomplete or complete and
method/ methodology is methodology is methodology is
Established under under well
methodology development :6 development: 4 established: 1