AMNIT-CU-100-LST-1001-A0 - Precommissioning & Commissioning Plan 1111
AMNIT-CU-100-LST-1001-A0 - Precommissioning & Commissioning Plan 1111
AMNIT-CU-100-LST-1001-A0 - Precommissioning & Commissioning Plan 1111
FOR APPROVAL
DATE 28-10-2020
王军亭
2020.10.28
08:36:08 +08'00'
TOTAL OR PARTIAL REPRODUCTION AND/OR UTILIZATION OF THIS DOCUMENT ARE FORBIDDEN WITHOUT PRIOR WRITTEN
AUTHORIZATION OF KAN
Document No. : A0
AMNIT-CU-100-LST-1001-A0
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
AMNIT-CU-100-LST-1001 Page 2 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
AMNIT-CU-100-LST-1001 Page 3 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
TABLE OF CONTENT
Contents
1. OBJECTIVE ..................................................................................................................... 5
3. REFERENCES ................................................................................................................ 7
8. ATTACHMENT............................................................................................................... 13
AMNIT-CU-100-LST-1001 Page 4 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
1. OBJECTIVE
This document provides guidance for execution of precommissioning and commissioning
works in AMMONIUM NITRATE PROJECT. In this document describe detail executions
of precommissioning and commissioning activities including readiness/preparation and
acceptance criteria for each activity.
AMNIT-CU-100-LST-1001 Page 5 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
3. REFERENCES
The procedures take as reference
· Site Quality Control Procedure : AMNIT-QC-100-ITP-1002
· Pre-Commissioning Check Sheet Form : AMNIT-CU-100-LST-1002
· Pre-Commissioning Test Sheet Form : AMNIT-CU-100-LST-1003
· Piping Cleaning Procedure : AMNIT-CU-100-PRC-1012
· Steam Blowing Procedure : AMNIT-CU-100-PRC-1013
· N2 Purging Procedure : AMNIT-CU-100-PRC-1014
· Tightening Procedure : AMNIT-CU-100-PRC-1015
· Leak Test Procedure : AMNIT-CU-100-PRC-1016
· Lube Oil Flushing Procedure : AMNIT-CU-100-PRC-1017
· Motor Solo Run Procedure : AMNIT-CU-100-PRC-1018
· No Load Test Conveyor : AMNIT-CU-100-PRC-1019
· Mechanical Run Procedure : AMNIT-CU-100-PRC-1020
· Mechanical Cleaning & Box Up Procedure : AMNIT-CU-100-PRC-1021
· Instrument Loop Test Procedure : AMNIT-CU-100-PRC-1022
· Electrical Energize Procedure : AMNIT-CU-100-PRC-1023
· Mechanical Completion Procedure : AMNIT-CU-100-PRC-1024
· Commissioning of Diesel Generator Procedure : AMNIT-CU-100-PRC-1025
· Process Description : To be added
· P&ID all System : To be added
· Single Line Diagram : To be added
4. SCOPE OF WORK
General scope of work for precommissioning is to convince that all equipment are ready
to be operated and could start its own function normally. Commissioning performed by
CONTRACTOR based on classification of system and subsystem of this PROJECT.
AMNIT-CU-100-LST-1001 Page 7 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
5. COMMISSIONING REQUIREMENTS
Ø Before executing commissioning, make sure that all precommissioning activities
already conducted and all punchlist “A” categories already completed
Ø Commissioning team has been formed consist of leader, engineer, supervisor and
other that involved in commissioning.
Ø During commissioning, plant Ammonium Nitrate Project must be stated closed for all
public activities except who get permission. Identification card (badge) must be used
AMNIT-CU-100-LST-1001 Page 8 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
installed LOTO
· The personnel who responsible to conduct LOTO is supervisor and operator.
· Uninstall LOTO only can be conducted by operator/supervisor who installed it
or by someone who already coordinate and have permission from
operator/supervisor who installed it.
6.2. Equipment
o First, check and make sure all equipment are ready for conducted commissioning
activities. Check all report related to installation, erection and precommissioning
work. It must be completed
o All system already energized and ready for running equipment
o Rotation of rotating equipment already checked
o Rotating equipment has been lubricated
o Measurement tools has been prepared for taking data during commissioning
o The measurement tools are already calibrated
o General tools are available for troubleshooting necessity
6.3. Personal
o Make sure that all personnel are in good condition
o All personnel understand about the activity, the risk of the activity and how to
handle the risk
o All personnel must be ready on the location that already plotted
o Each personnel understand their job
o Each personnel know what have to do if any emergency situation happen and
know to coordinate with
6.4. Communication
o Communication system is using handy talky (HT)
o Before executing commissioning, a coordination meeting must be held to
determine the radio channel for each personnel
o Emergency contact must be shared before executing commissioning
AMNIT-CU-100-LST-1001 Page 10 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
8. ATTACHMENT
Attachment – 1 Precommissioning, Commissioning and Start Up Execution Plan
AMNIT-CU-100-LST-1001 Page 13 of 14
AMMONIUM NITRATE PROJECT 75,000 MTPY AMMONIUM NITRATE & 60,000 MTPY NITRIC ACID
PT. KALTIM AMONIUM NITRAT
ATTACHMENT – 1
PRECOMMISSIONING, COMMISSIONING, START UP, & PERFORMANCE TEST
EXECUTION PLAN
AMNIT-CU-100-LST-1001 Page 14 of 14
PT KALTIM AMONIUM NITRAT
75.000 MTPY AMMONIUM NITRATE PROJECT PLANT
Completion Punch "A" Items Completion Punch "A" Items Completion Punch "B" Items Completion Punch "B" Items Completion Punch "B" Items
MC