A-Inspection and Test Plan Checklist For Termite Control-New
A-Inspection and Test Plan Checklist For Termite Control-New
A-Inspection and Test Plan Checklist For Termite Control-New
Client: Project Management Consultant and Engineer: Construction Supervision Consultant: Contractor:
Doucment Title Termite control (Anti termite treatment) Activity -Check List No.1 WIR No: SEVEN Project ID 2KHRJ17- KHRJ-08
Client: Saudi Entertainment Ventures Revision 0 Start Date 20-Mar-24 End Date 18-Dec-24
Remove foreign matter which could decrease effectiveness Technical Specifications , SECTION
1.0
of treatment on areas to be Treated. 313116, item 3.1.A
Apply termiticide to soil in critical areas under slabs, including entire inside perimeter inside of foundation walls,
Technical Specifications , SECTION
2.0 along both sides of interior partition walls, around plumbing pipes and electric conduit penetrating slab and
313116, item 3.2.B.1
around interior column footers.
Apply termiticide along outside edges of the building. Dig a trench 150 mm to 200 mm wide along the outside
Technical Specifications , SECTION
3.0 of foundation to a depth of not less than 300 mm. Mix chemical solution with the soil as it is being replaced in
313116, item 3.12B.2
trench.
At Hollow Masonry Foundations or Grade Beams: Treat voids with termiticide by pouring directly into the hollow Technical Specifications , SECTION
4.0
spaces. 313116, item 3.2.C
Remarks
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
The work is ready for inspection Document Reviewed Work Inspected Test Records Verified
5 Leak Testing
6
Earthwork - Site Preparation, Excavation and Backfill
7 Fireproofing Concrete
18 Centrifugal Pump
19 Positive Displacement Pump
31 Pressure Instrumentation
34
Motor Operated Valves (MOV) and Control Valves (CV)
53
Testing, Adjusting and Balancing of HVAC Systems
58 Leak Testing
88 HVAC Equipment
94 Grounding / Bonding
95 Lighting Protection Systems
96 LV Induction Motors
98 Diesel-Generator Set
99 Cranes, Hoists and Elevators
100
Annunciator Metering and Protection Relaying Cabinets
101 MV Switchgear
102 MV Control gear
107 LV Panelboards
120
Portland Cement Concrete - Batch Plant Management
122
Pre-Cast Concrete Fence Posts at Fabrication Yards
Structural Precast / Prestressed Concrete at Fabrication
123
Yard
166 Valves
167 Installation of storm drains
168 Valves
o Add or remove Remove Items to be in line with the Contractors scope of works.
P List must be submitted as an Appendix when Submitting the PQP.
Check Lists ITP Number Discipline
MEP
Review of Pneumatic Testing Procedure MEP
Filling & Pressurization for Pneumatic Testing MEP
Visual Inspection of Pneumatic Test MEP
Depressurization of Pneumatic Test MEP
MEP
Review of Hydrostatic Pressure Testing Procedure for
MEP
Plant Piping
Review of Test Packages MEP
Review of Lay-up Procedures MEP
Verification of Test Medium MEP
Verification of Test Equipment and Test Instruments for
MEP
Pressure Testing
Pre-Test Punch listing MEP
Inspection of Pressure Test Preparation MEP
Internal Cleanliness Inspection of Piping & Vessels MEP
Inspection of Filling & Pressurization for Pressure Testing
MEP
of Piping
Visual Inspection of Pressure Test MEP
Pneumatic Testing of Reinforcing Pads MEP
Depressurization & Disposal of Hydrotest Water MEP
Lay-up Application for Piping and Vessels MEP
MEP
Review of Hydrostatic Pressure Testing Procedure for
MEP
Pipelines
MEP
Review of Hydrotest Procedure for Pressure Vessels MEP
Inspection of Filling & Pressurization for Pressure Testing
MEP
of Vessels
Pre-Test Inspection of Pressure Vessels MEP
MEP
Review of Leak Testing Procedure MEP
Pressurization for Leak Testing MEP
Inspection of Leaks for Tightness Testing MEP
Civil
MEP
Fire Alarm System - Cable and Accessories - Material
MEP
Receiving
Fire Alarm System - Control Panel - Material Receiving MEP
Fire Alarm System - Audible / Visual Annunciators -
MEP
Material Receiving
Fire Alarm System - Smoke/Heat Detector - Material
MEP
Receiving
Fire Alarm System - Smoke/Heat Detector - Installation MEP
MEP
MEP
MEP
MEP
MEP
MEP
MEP
MEP
Structural
Structural
Structural
Civil
Fence and Gates Components Receiving Inspection Civil
Pre-Cast Posts Receiving Inspection Civil
Location, Depth of Trench / Boreholes and Elevations
Civil
Inspection
Pre-pour Inspection Civil
Final Inspection Civil
Civil
Concrete Masonry Unit (CMU) compressive strength and
Civil
aggregate test reports
Concrete Masonry Units/Bricks Receiving Inspection Civil
Concrete Surface Preparation Inspection Civil
Concrete Masonry Units (CMUs)/Brick Walls and Plaster
Civil
Installation Inspection
Concrete and CMU Surface Preparation and Protection Civil
Civil
Gypsum Wall Board System Receiving and Storage
Civil
Inspection
Gypsum Wall Board Pre-Installation Inspection Civil
Gypsum Wall Board Framing, Insulation and Pre-closing
Civil
Inspections
Gypsum Wall Board System Plastering, Finishing and
Civil
Final Insp.
Civil
Ceramic Wall and Floor Tiles and Accessories Receiving
Civil
and Storage Inspection
Ceramic Wall and Floor Tile Pre-Installation and Surface
Civil
Preparation Inspection
Ceramic Wall and Floor Tiles Installation and Final
Civil
Inspection
Civil
Metal Doors and Windows Receiving Inspection Civil
Metal Doors and Windows Pre- Installation Inspection Civil
Metal Doors and Windows Installation Inspection Civil
Metal Doors and Windows Final Inspection Civil
Civil
MEP
Review of Magnetic Particle Testing Procedure MEP
Review of Personnel Qualification for Magnetic Particle
MEP
Testing
Inspection/Verification of Magnetic Particle Testing
MEP
Devices
Storage and Handling of Magnetic Particle Testing
MEP
Devices
Inspection/Verification Requirements Prior to MPI
MEP
Application
In-Process Inspection of Magnetic Particle Testing MEP
Evaluation of Test and Test Report MEP
Demagnetization & Post Cleaning (MPT) MEP
Civil
Fence and Gates Components Receiving Inspection-
Civil
SSD/1 Fence
Pre-Cast Posts Receiving Inspection for SSD/1 Fence Civil
SSD/1 Location, Depth of Trench/Boreholes & Elevation
Civil
Inspection
Pre-Pour Inspection for SSD/1 Fence Civil
Final Inspection for SSD/1 Fence Civil
MEP
MEP
MEP
MEP
MEP
MEP
General - Electronic Equipment, Storage Handling &
MEP
Preservation
General - Electrical Equipment, Storage Handling &
MEP
Preservation
General - Switchgear Room / Substation, Equipment Pre-
MEP
Installation Inspection
UPS/DC Vented Ni-Cad Wet Cell, Storage Handling &
MEP
Preservation
UPS/DC Vented Lead-Acid Wet Cell, Storage Handling &
MEP
Preservation
UPS/DC Valve Regulated Lead-Acid (VRLA) Gelatin Cell,
MEP
Storage Handling & Preservation
UPS/DC Aqueous Sulfuric Acid Electrolyte, Storage
MEP
Handling & Preservation
UPS/DC Dry Potassium or Sodium Hydroxide Electrolyte,
MEP
Storage Handling & Preservation
UPS DC/AC Inverter, Material Receiving MEP
UPS Static Switch, Material Receiving MEP
UPS Transfer Switch Material Receiving MEP
UPS Bypass Line Transformer Material Receiving MEP
UPS Maintenance Bypass Switch Material Receiving MEP
UPS Panelboards / CB's Material Receiving MEP
UPS/DC Battery Rectifier / Charger Material Receiving MEP
UPS/DC Vented Ni-Cad Wet Cell Material Receiving MEP
UPS/DC Vented Lead-Acid Wet Cell Material Receiving MEP
UPS/DC VRLA Gelatin Cell Material Receiving MEP
UPS/DC Aqueous Sulfuric Acid Electrolyte Material
MEP
Receiving
UPS/DC Dry Potassium or Sodium Hydroxide Material
MEP
Receiving
UPS/DC System and Battery Accessories, Material
MEP
Receiving
UPS/DC Battery Room, Equipment Pre-Installation
MEP
Inspection
UPS/DC Equipment and Battery Rack, Installation and
MEP
Pre-Commissioning
UPS/DC System Electrochemical Battery Installation and
MEP
Pre-Commissioning
MEP
DC Switchboard / CB's, Material Receiving MEP
DC Panelboard / CB's, Material Receiving MEP
MEP
General - Hazardous Location Conduit and Cable Sealing
MEP
Special Work Procedure, Document Review
Cable Storage, Handling, & Preservation MEP
Low Voltage UL / NEC Power and Control Cable, Material
MEP
Receiving
Low Voltage NEC / SASO / IEC Unjacketed Wire, Material
MEP
Receiving
Low Voltage IEC Armored Cable, Material Receiving MEP
Low Voltage IEC Unarmored Cable, Material Receiving MEP
MEP
MEP
Very High Voltage Cable - Material Receiving MEP
MEP
General - Exothermic (Thermite) Welding Materials,
MEP
Molds, & Tools - Material Receiving
GES - DCS/ESD/PLC/SCADA Grounding Installation MEP
GEC/EGC - AC UPS System Grounding MEP
GEC/EGC - DC System Grounding Installation MEP
Grounding - GES - Ground Rods - Material Receiving MEP
Electrical Grounding System - Final Inspection MEP
Grounding - GES - Zinc and Magnesium Anode Electrodes
MEP
- Material Receiving
Grounding - GES - Ground Electrode Cable - Material
MEP
Receiving
Grounding - Bare Copper Ground Conductor - Material
MEP
Receiving
Grounding - Bare Tinned Copper Ground Conductor -
MEP
Material Receiving
Grounding - Hydraulic Compression Fittings and Tools -
MEP
Material Receiving
Grounding and Bonding Accessories - Material Receiving MEP
MEP
MEP
MEP
Overhead Transformer - Material Receiving MEP
MEP
Civil
Civil
Civil
Review of Engineering Properties of
Civil
Foamed Stabilizing Agents and Subbase Materials
Stabilization Equipment Set-Up Inspection Civil
Placement Compaction & Quality Control of
Civil
Foamed Stabilization Materials
Civil
Grout Samples Compressive strength test reports Civil
Wet Well and Wet Well / Dry Well lift stations installation MEP
MEP
MEP
Receiving and Storage of electric water coolers MEP
Installation of electric drinking water coolers MEP
MEP
MEP
Brazer Qualifications Document Review MEP
Brazing Procedures Document Review MEP
Copper Pipe and Brazing wire receiving MEP
Copper Pipe Installation MEP
Civil