A-Inspection and Test Plan Checklist For Termite Control-New

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 78

P2 Al-Kharj Entertainment Complex

Client: Project Management Consultant and Engineer: Construction Supervision Consultant: Contractor:

Document Number Issue Date 12-May-24 Contract No: 183.23

Doucment Title Termite control (Anti termite treatment) Activity -Check List No.1 WIR No: SEVEN Project ID 2KHRJ17- KHRJ-08

Client: Saudi Entertainment Ventures Revision 0 Start Date 20-Mar-24 End Date 18-Dec-24

Project Management Consultant EllisDon Issued by HAC


£ Landscape WBS SUBCONTRACTOR (if any)

Discipline: ¢ Civil £Architecture £ Plumbing


Construction Supervision Consultant DAR International for Engineering Consultancy £ Mechanical
£ Electrical £ Construction Management £ Other (specify if
Contractor Hassan Allam Construction
other):
ITP Checklist
Termite control (Anti termite treatment) Activity
ITEM NO. Check Points Reference Pass Fail Not Applicable Re-Inspection

Remove foreign matter which could decrease effectiveness Technical Specifications , SECTION
1.0
of treatment on areas to be Treated. 313116, item 3.1.A

Apply termiticide to soil in critical areas under slabs, including entire inside perimeter inside of foundation walls,
Technical Specifications , SECTION
2.0 along both sides of interior partition walls, around plumbing pipes and electric conduit penetrating slab and
313116, item 3.2.B.1
around interior column footers.

Apply termiticide along outside edges of the building. Dig a trench 150 mm to 200 mm wide along the outside
Technical Specifications , SECTION
3.0 of foundation to a depth of not less than 300 mm. Mix chemical solution with the soil as it is being replaced in
313116, item 3.12B.2
trench.

At Hollow Masonry Foundations or Grade Beams: Treat voids with termiticide by pouring directly into the hollow Technical Specifications , SECTION
4.0
spaces. 313116, item 3.2.C

Technical Specifications , SECTION


5.0 At Expansion Joints, Control Joints and Grade Areas: Apply termiticide to areas of penetration through the slabs.
313116, item 3.2.D

Remarks

Contractor Construction Supervision Consultant


Contractor Construction Supervision Consultant

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified

Name Signature Date Name Signature Date

Contractor QC Inspector Third Party (if applicable)

The work is ready for inspection Document Reviewed Work Inspected Test Records Verified

Name Signature Date Name Signature Date


The Contractor may opt to Add or remove Remove Items to be in line with the Contractor
The initial ITP List must be submitted as an Appendix when Submitting the P
Item
Inspection & Test Plan (ITP)
Number
1 Pneumatic Pressure Testing

2 Pressure Testing-Hydrostatic Test of Plant Piping

3 Pressure Testing-Hydrostatic Test of Pipelines

4 Pressure Testing of Pressure Vessels

5 Leak Testing

6
Earthwork - Site Preparation, Excavation and Backfill
7 Fireproofing Concrete

8 Intumescent Fire Proofing

9 Fire Detection and Alarm Systems


10 Portable Fire Protection Equipment Installation

11 Emergency Eyewash Shower/Shower System

12 Pressure Vessel Installation


13 Shop Fabrication Storage Tank Installation

14 Heat Exchanger Installation - Shell and Tube

15 Air Cooled Heat Exchanger - Fin Fan Cooler

16 Fired Heaters Field Installation

17 Forced Draft Fan

18 Centrifugal Pump
19 Positive Displacement Pump

Lubrication, Shaft Sealing and Oil System for Rotating


20
Equipment

21 Cement Lining of Pipes and Fittings


22 External FBE Coating of Field Welded Joints

23 Alkyd Enamel Coatings


24 Epoxy Coatings
25 Tape Wrapping
26 Organic and Inorganic Zinc Coating as applicable
27 Pipe Internal Coating and Installation
28 Coating Application on Concrete Surfaces

29 Instrument Pipe and Tubing


30 Flow Instrumentation

31 Pressure Instrumentation

32 Liquid Level Instrumentation


33 Temperature Instrumentation

34
Motor Operated Valves (MOV) and Control Valves (CV)

35 Instrument Control Loop Checking

36 Metallic Instrumentation and Control Cable

Factory Assembled (Packaged) Auxiliary


37
Instrumentation Systems

38 Fiber Optic Cable


39 Electronic Control Systems- DCS ESD PLC SCADA

40 Instrumentation Racks and Panels (Open); Terminal


Boxes and Instrument Cabinets (Enclosed)

41 Intrinsically Safe (IS) Systems

42 Centrifugal & Axial Fan

43 Air Handling Units


44 HVAC Metal Duct System

45 Chilled Water Piping

46 Chilled Water System

47 Packaged Air Conditioning Units


48 Refrigerant Piping

49 Air Filtration Devices

Through-the Wall and Window-Mounted Air


50
Conditioners

Air Ventilation / Cooling Systems


51
(Exhaust Hoods and Passively Cooled Shelters)
52 A/C Split System

53
Testing, Adjusting and Balancing of HVAC Systems

54 Hot Tap Installation


55 On-Land and Near-Shore Pipelines

56 Pipeline Construction / Installation

57 Liquid Penetrant Testing

58 Leak Testing

Structural Steel, Piperack & Miscellaneous Steel


59
Supports and Aluminum Structures
60 Verification Testing
Welding of Structural Steel and Miscellaneous Steel-On
61
Shore
62 Security Fence and Gates

63 Concrete Masonry Units & Building Bricks

64 Water Proofing of Roof Slabs

65 Structural Steel for Buildings


66 Pre-engineered Metal Buildings

67 Gypsum Wall Board System

68 Ceramic Wall and Floor Tiles

69 Metal Doors and Windows

70 Acoustical False Ceiling

71 Glass and Glazing


72 Resilient Vinyl Composition Floor Tiles and Base

73 Magnetic Particle Testing

74 Security Fence and Gates

75 Liquid Penetrant Testing


76 Leak Detection (NDE)
77 Magnetic Particle Testing
78 Radiographic Testing
79 Ultrasonic Testing
80 AC UPS Systems
81 Direct Current Power Systems

82 Low Voltage (600V to 1kV) Cable

83 Medium Voltage (1.0kV to 35kV) Cable

84 Cable Tray, Fittings and Accessories


Boxes (Junction, Terminal and Pull) Wire Troughs &
85
Wireways

86 Above-Grade Conduits, Fittings and Accessories


87 Below-Grade Conduit, Fittings and Accessories

88 HVAC Equipment

89 Electrical Heat Tracing


90 High Voltage (35.001kV to 69kV) Cable

91 Very High Voltage (Above 69kV) Cable


92 Receptacles and Cord-Connected Equipment

93 Over-Head Transmission and Distribution Systems

94 Grounding / Bonding
95 Lighting Protection Systems

96 LV Induction Motors

M.V. Induction Motors (Nameplate Voltage: 4kV, 6.6kV


97
& 13.2kV)

98 Diesel-Generator Set
99 Cranes, Hoists and Elevators

100
Annunciator Metering and Protection Relaying Cabinets

101 MV Switchgear
102 MV Control gear

103 LV Switchgear and Switchboards

104 LV Control gear TIP


105 Switchracks and Distribution Racks

106 Fire Water Pump / Motor / Controller

107 LV Panelboards

108 MV (max 35kV) Non-seg Busduct

109 MV (max. 15kV) Cable bus)

110 LV Non-seg Busduct


111 LV Cable bus

112 VSD Equipment


113 HV Switchyard

114 Dry Type Transformers

115 Power Transformers


116 Overhead Transformers

117 Pad Mounted Transformers

118 Light Fixtures and Lighting Systems


Factory Assembled (Packaged) Auxiliary Electrical
119
Equipment

120
Portland Cement Concrete - Batch Plant Management

121 Cast-In-Place Portland Cement Concrete

122
Pre-Cast Concrete Fence Posts at Fabrication Yards
Structural Precast / Prestressed Concrete at Fabrication
123
Yard

124 Installation of Piles for Offshore Structures

125 Asphalt Paving - Batch Plants Management

126 Asphalt Paving


127 Foamed Asphalt Stabilization

128 Cement Based Non-Shrink Grouting

129 Epoxy Grout for Machinery Support

130 Radiographic Testing

131 Gravity sanitary Sewer Piping and Sewer Manhole

132 Sanitary sewage lift station and piping/force main


133 Storm water drainage systems

Water Distribution Piping system [upstream and down


134
stream of isolation valve] and its supports

135 Building Sprinklers and Standpipe System

136 Electric Water Heaters

137 Electric drinking water coolers

138 Skid Mounted Reverse Osmosis System

139 Plumbing Fixtures and Fittings


140 Roof Drain and Drainage Piping

141 Building Drain Waste and Vent (DWV) Pipe

142 Neutralization Tank and apparatuses

143 Copper Piping

Earthwork - Excavation and Backfill for Underground


144
Utilities

145 Irrigation piping

146 Thermo plastic & RTR Piping


147
Duct bank Excavation & Backfilling for Non-traffic Areas

148 Direct Current Power Systems (-48 and -24 VDC)

149 Powered In-Plant Communications Systems

150 Communications Systems


151 Fiber Optic Communications Cable

152 Copper Communications Cable (OSP/ISP/CO)

153 Communication Tower and Facilities (ISP/CO)


154 Telecommunication facilities
155 Outside Plant (OSP) Duct banks

156 Building Premises Distribution System (PDS)


157 Outside Plant (OSP) System

158 Ultrasonic Testing

159 Welding of On-plot Piping


160 Welding of Pipelines
161 Welding of Overlays and Cladding Restoration
162 Off-Plot Galvanic Cathodic Protection

163 Off-Plot Impressed Current Cathodic Protection


164 On-plot Galvanic Cathodic Protection
165 Installation of Metering Skid for Hydrocarbon Gas

166 Valves
167 Installation of storm drains
168 Valves
o Add or remove Remove Items to be in line with the Contractors scope of works.
P List must be submitted as an Appendix when Submitting the PQP.
Check Lists ITP Number Discipline

MEP
Review of Pneumatic Testing Procedure MEP
Filling & Pressurization for Pneumatic Testing MEP
Visual Inspection of Pneumatic Test MEP
Depressurization of Pneumatic Test MEP
MEP
Review of Hydrostatic Pressure Testing Procedure for
MEP
Plant Piping
Review of Test Packages MEP
Review of Lay-up Procedures MEP
Verification of Test Medium MEP
Verification of Test Equipment and Test Instruments for
MEP
Pressure Testing
Pre-Test Punch listing MEP
Inspection of Pressure Test Preparation MEP
Internal Cleanliness Inspection of Piping & Vessels MEP
Inspection of Filling & Pressurization for Pressure Testing
MEP
of Piping
Visual Inspection of Pressure Test MEP
Pneumatic Testing of Reinforcing Pads MEP
Depressurization & Disposal of Hydrotest Water MEP
Lay-up Application for Piping and Vessels MEP
MEP
Review of Hydrostatic Pressure Testing Procedure for
MEP
Pipelines
MEP
Review of Hydrotest Procedure for Pressure Vessels MEP
Inspection of Filling & Pressurization for Pressure Testing
MEP
of Vessels
Pre-Test Inspection of Pressure Vessels MEP
MEP
Review of Leak Testing Procedure MEP
Pressurization for Leak Testing MEP
Inspection of Leaks for Tightness Testing MEP

Civil

Sieve Analysis and Atterberg Limits Test Reports Civil


Fill, Select-Fill and Marl Cap Materials Receiving
Civil
Inspection
Soil Protection and Control, Drainage and De-watering
Civil
Inspection
Fill Placement and Compaction Inspection Civil
Compaction Testing Civil
Final Fill Inspection Civil
Civil
Storage/Preservation Inspection Civil
Pre-placement/site preparation inspection Civil

Application/Placement Inspection, Sampling and Testing Civil

Final Inspection Civil


MEP

Review of Intumescent Fireproofing Material for Approval MEP


Review of Installation Procedure for Intumescent
MEP
Fireproofing Material
Verification/Inspection of Intumescent Fireproofing
MEP
Material
Storage, Handling & Preservation of Intumescent
MEP
Fireproofing Materials
Performance Verification of Equipment & Applicators of
MEP
Intumescent Fireproofing Materials
Pre-Application Inspection of Intumescent Fireproofing
MEP
Materials
In-Process Inspection of Intumescent Fireproofing
MEP
Material Application
Post-Application Inspection of Intumescent Fireproofing
MEP
Material
Top Coating Application on Intumescent Fireproofing MEP

Final Inspection of Intumescent Fireproofing Application MEP

MEP
Fire Alarm System - Cable and Accessories - Material
MEP
Receiving
Fire Alarm System - Control Panel - Material Receiving MEP
Fire Alarm System - Audible / Visual Annunciators -
MEP
Material Receiving
Fire Alarm System - Smoke/Heat Detector - Material
MEP
Receiving
Fire Alarm System - Smoke/Heat Detector - Installation MEP

Fire Alarm System - Water Flow Switch and Water Valve


MEP
Position Switch- Material Receiving and Instrumentation
Fire Alarm System - Manual Pull Station - Material
MEP
Receiving and Installation
Fire Alarm System - Pre-Commissioning Inspection MEP
Fire Alarm System - Heat Detector - Fixed Temperature -
MEP
Material Receiving and Installation
Fire Alarm System - Heat Detector - Rate of Rise -
MEP
Material Receiving and Installation
Fire Alarm System - Heat Detector - Infrared Flame -
MEP
Material Receiving and Installation
Fire Alarm System - Heat Detector - FT / RoR - Material
MEP
Receiving and Installation
Fire Alarm System - Heat Detector - Rate Compensation -
MEP
Material Receiving and Installation
Fire Alarm System - Duct Smoke Detector - Material
MEP
Receiving and Installation
Fire Alarm System - Water Flow Switch - Material
MEP
Receiving and Installation
Fire Alarm System - Water Valve Position Switch -
MEP
Material Receiving and Installation
Fire Alarm System - Manual Pull Station - Material
MEP
Receiving and Installation
Fire Alarm System - Pre-Commissioning Inspection MEP
MEP
Material Receiving Inspection - Portable Fire Protection
MEP
Equipment
Storage, Handling & Preservation of Portable Fire
MEP
Protection Equipment
Portable Fire Extinguishers- Installation Inspection MEP
Foam Generating Equipment - Installation Inspection MEP
Special Fixed Extinguishing Equipment - Installation
MEP
Inspection
Access and Platforms for Portable Fire Protection System MEP

Re-Instatement of Portable Fire Protection System MEP


MEP
Emergency Eyewash / Shower and its accessories
MEP
Receiving, Handling, Storage and Preservation
Emergency Eyewash / Shower, its accessories and Piping
MEP
Connection Installation Inspection
MEP

Review of Vessel Data Sheet & Safety Instruction Sheet MEP

Receiving Inspection of Pressure Vessels- External MEP


Receiving Inspection of Pressure Vessels- Internal MEP
Receiving Inspection of Ladders, Platforms & other
MEP
Structural Steel Attachments of Vessels and Tanks
Vessel Storage, Handling & Preservation MEP
Equipment Pre-Installation Inspection MEP
Equipment Installation-Alignment & Elevation Survey
MEP
(Vertical Vessels )
Vessel Trim Installation Inspection MEP
Tray Installation in Vessels MEP
Tray Testing (Vessels & Columns) MEP
Vessel Closure Inspection MEP
Final Inspection of Vessels (Re-Instatement) MEP
Catalyst/Packing Installation MEP
Receiving Inspection of Tanks- External MEP
Receiving Inspection of Tanks- Internal MEP
Inspection of Buried Tank Installation MEP
Inspection of Under-Tank Leak Detection & Sub-Grade
MEP
Protection
Inspection of Above Ground Tank Installation MEP
Tank Trim Installation MEP
Final Inspection of Tank Installation MEP
Equipment Installation-Alignment & Elevation Survey
MEP
(Horizontal Vessel)
MEP
Review of Tank Data Sheet & Safety Instruction Sheet MEP
MEP
Review of SIS for Shell & Tube Heat Exchanger MEP
Receiving Inspection of Shell & Tube Heat Exchangers MEP
Storage, Handling & Preservation of Heat Exchangers MEP
Nitrogen and Pearlite Application on BAHE Frame MEP
MEP
Review of SIS for Air Cooled Heat Exchanger MEP
Receiving Inspection of Air Cooled Heat Exchanger MEP
Fin Fan Cooler Shroud Assembly Inspection MEP
Inspection of Fan Installation for Air Cooled Heat
MEP
Exchanger
Re-instatement of Air Cooled Heat Exchanger. MEP
Vessel Internal Cleanliness of this Air Cooled Heat
MEP
Exchanger
In-Situ Strength Test of Fin Fan Coolers MEP
MEP
Review of Erection Plan for Fired Heaters MEP
Review of Drawings for Ultrasonic Thickness Record of
MEP
the Fired Heater's Component
Review of Data Sheet and Safety Instruction Sheet for
MEP
Fired Heater
Material Receiving Inspection of Fired Heater &
MEP
Accessories
Handling, Storage and Preservation of Fired Heater and
MEP
Its Components
Installation of Fired Heater & Components MEP
Closure Inspection of Heater Boxes MEP

Final Punch Listing of Fired Heater and its Components MEP

MEP

Review of Safety Instruction Sheet for Forced Draft Fan MEP


Material Receiving Inspection of forced Draft Fan, Driver
MEP
and Ductworks
Storage, Handling & Preservation of Forced Draft Fam
MEP
and its Components
Installation of Ducting for Forced Draft Fan MEP
Installation of Auxiliary Piping of Forced Draft Fan MEP
Final Punch Listing of Forced Draft Fan and Its
MEP
Components
MEP
Review of Safety Instruction Sheet for Centrifugal Pump MEP

Receiving Inspection of Centrifugal Pumps MEP


Storage Handling & Preservation of Centrifugal Pumps MEP
Inspection of Auxiliary Piping Installation for Pumps MEP
Pump Suction and Discharge Piping Installation MEP

Driver Shaft/Coupling Alignment for Rotating Equipment MEP

Final Punch Listing of Centrifugal Pumps MEP

Equipment Mounting Plate Installation (Prior to Grouting) MEP

Final Pump/Driver Alignment MEP


MEP
Review of Safety Instruction Sheet for Positive
MEP
Displacement Pump
Receiving Inspection of Positive Displacement Pump MEP
Storage Handling & Preservation of Positive Displacement
MEP
Pump

MEP

Review of Chemical Cleaning and Flushing Procedure For


Lubrication, Shaft Sealing and Oil Systems for Rotating MEP
Equipment
Receiving Inspection of Mechanical Components of
Lubrication, Shaft Sealing and Oil Systems for Rotating MEP
Equipment
Storage, Handling & Preservation of Lubrication, Shaft
MEP
Sealing and Oil Systems for Rotating Equipment
Installation of Mechanical Components of Lubrication,
MEP
Shaft Sealing and Oil Systems for Rotating Equipment
Final Punch Listing of Lubrication, Shaft Sealing and Oil
MEP
Systems for Rotating Equipment
Pre-Cleaning Inspection of the Lube and/or Seal Oil
MEP
System
Mechanical Cleaning of Lube and/or Seal Oil System MEP
Chemical Cleaning of Lube and/or Seal Oil System MEP
Flushing and Cleanliness Inspection of the Lube and/or
MEP
Seal Oil System
Final System Re-Instatement and Inspection of the Lube
MEP
and/or Seal Oil System
MEP

Review of Cement Lining Procedure and Inspection Plan MEP

Receiving Inspection of Raw Materials for Cement Lining MEP


Storage, Handling and Preservation of Raw Materials for
MEP
Cement Lining
Verification of Cement Lining Equipment MEP
Pre-Application Inspection of Cement Lining MEP
In-Process Inspection of Cement Lining MEP
Post Application Inspection of Cement Lining MEP
Final Inspection for Acceptance of Cement Lined
MEP
Pipe/Piping
MEP

Review of Field Applied FBE Coating & Repair Procedure MEP


Review of Coating Personnel Qualification and
MEP
Certification
Material Inspection of FBE Powder & Abrasives MEP
Storage, Handling and Preservation of FBE Powder and
MEP
Abrasive Materials
Inspection and Performance Verification of FBE Powder
MEP
Application Equipment
Surface Preparation for Ext FBE on field girth welds MEP
In-Process Inspection of FBE Powder Application on Ext.
MEP
Field Girth Welds
Holiday Testing and Inspection MEP

In-Process Inspection of Repair on External FBE Coating MEP

Final Inspection Prior to Backfill MEP


MEP
MEP
MEP
MEP
MEP
Civil
Coating Material's Approval by the Responsible
Civil
Standardization Agency Representative (RSA)
Concrete repair and coating material receiving inspection Civil

Storage and Preservation inspection Civil


MEP
General Tubing and Accessories - Handling, Storage and
MEP
Preservation
General Tubing - Hard Drawn Copper Pipe and Fittings -
MEP
Material Receiving
General Tubing - Brass Valves for Pipe - Material
MEP
Receiving
General Tubing - Tubing - Material Receiving MEP
General Tubing - Compression Fittings and Accessories -
MEP
Material Receiving
General Tubing - Pipe Installation and Pre-Commissioning MEP
General Tubing - Tubing and Fittings Installation and Pre-
MEP
Commissioning
General Tubing - Copper/Brass Compression Fittings and
MEP
Accessories - Material Receiving
General Tubing - Hard Drawn Copper Pipe - Installation
MEP
and Pre-Commissioning
General Tubing - Hard Drawn Copper Fittings -
MEP
Installation and Pre-Commissioning
General Tubing - Brass Valves for Pipe - Installation and
MEP
Pre-Commissioning
General Tubing - Stainless Steel Tubing - Installation and
MEP
Pre-Commissioning
General Tubing - Soft Drawn Copper Tubing - Installation
MEP
and Pre-Commissioning
General Tubing - Stainless Steel Compression Fittings and
MEP
Accessories - Installation and Pre-Commissioning
General Tubing - Copper/Brass Compression Fittings and
MEP
Accessories - Installation and Pre-Commissioning
MEP
General - Recorder / Indicator - Material Receiving MEP
Flow - Orifice Plate - Material Receiving MEP
Flow - Orifice Meter - Material Receiving MEP
Flow Nozzle - Material Receiving MEP
Flow - Venturi - Material Receiving MEP
Flow - Averaging Pitot Element - Material Receiving MEP
Flow - Integral Orifice - Material Receiving MEP
Flow - Turbine Meter - Material Receiving MEP

Flow - Positive Displacement Meter - Material Receiving MEP

Flow - Magnetic Flow Meter - Material Receiving MEP


Flow - Mass Meter (Coriolis and Thermal) - Material
MEP
Receiving
Flow - Ultrasonic (Transit Time & Doppler) - Material
MEP
Receiving
Flow - Vortex Shedding Meter - Material Receiving MEP
Flow - Variable Area Meter (Rotameter) - Material
MEP
Receiving
MEP
General - Instrumentation Accessories - Material
MEP
Receiving
Pressure Gauges - Material Receiving MEP
Pressure Switches - Material Receiving MEP
Pressure Transmitters - Material Receiving MEP
Differential Pressure Transmitter - Material Receiving MEP
General-Instrumentation Accessories-Installation MEP
MEP
Level - Sight Glass Gauges / Switches - Material
MEP
Receiving
Level - Magnetic Gauges / Switches - Material Receiving MEP

Level - Displacement Instruments - Material Receiving MEP


Level - Automatic Tank Gauging (ATG) - Material
MEP
Receiving
Level - Ball Float Instrument - Material Receiving MEP
Level - Diff. Pressure Instruments - Material Receiving MEP
Level - Capacitance Instruments - Material Receiving MEP
Level- Automatic Tank Gauge (ATG)-Hydrostatic Tank
MEP
Gauging-M R and Installation- Material Receiving
Level-Switches-Material Receiving MEP
MEP
Temperature - Thermo-Wells - Material Receiving MEP
Temperature - Thermo-Couples - Material Receiving MEP
Temperature - Resistance Temperature Detectors -
MEP
Material Receiving
Temperature - Filled System Instruments - Material
MEP
Receiving
Temperature - Bimetallic Instruments - Material Receiving MEP

Temperature - Infrared Instruments - Material Receiving MEP

MEP

Valves - MOV / CV Storage, Handling, and Preservation MEP

Valves - Motor Operated Valve E&I Material Receiving MEP


Valves - Control Valve E&I Material Receiving MEP
MEP
Instrumentation and Control Loop Check Procedure -
MEP
Document Review
Instrument Loop Inputs - Control Circuit Test MEP
MEP

Instrument Cable - I&C Copper Cable - Material Receiving MEP


Instrument Cable - Thermo-Couple Extension Cable -
MEP
Material Receiving
Instrument Cable - Coaxial and Twinaxial Data Cable -
MEP
Material Receiving
Instrument Cable Accessories - Material Receiving MEP
Instrument Cable - Installation, Termination,
MEP
Identification, and Pre-Commissioning

MEP

General - Mechanical Equipment Skid - Zone or Div 1


MEP
Locations - Material Receiving
General - Mechanical Equipment Skid - Zone or Div 2
MEP
Locations - Material Receiving
General - Mechanical Equipment Skid - Non-Hazardous
MEP
Locations - Material Receiving
General - Mechanical Equipment Skid - Corrosive
MEP
locations - Material Receiving
General - Instrumentation Workspace Clearances MEP
MEP
Fiber Optic Cable - Single-mode Fiber Cable - Material
MEP
Receiving
Fiber Optic Cable - Fiber Cable - Material Receiving MEP
Fiber Optic Cable - Fiber Splicing/Testing Tools and
MEP
Accessories - Material Receiving
Fiber Optic Cable - Cable Continuity Installed Testing MEP
MEP
Electronic Control Systems - ESD/DCS Operator Console -
MEP
Material Receiving
Electronic Control Systems - DCS/ESD - I/O and CPU
MEP
Cabinets and Operator Consoles - Material Receiving
Electronic Control Systems - PLC - Material Receiving MEP
Electronic Control Systems - DCS/ESD Manufacturer's
MEP
Data Highway Cable - Material Receiving
Electronic Control Systems - DCS/ESD - I/O and CPU
Cabinets and Operator Consoles - Installation and Pre- MEP
Commissioning
Electronic Control Systems - PLC - Installation and Pre-
MEP
Commissioning
Electronic Control Systems - DCS/ESD Manufacturer's
MEP
Data Highway Cable - Installation and Pre-Commissioning

MEP

General - Non-Hazardous Inst. Enclosure - Material


MEP
Receiving
General - Manufactured Instrument Enclosures, Panels
MEP
and Racks - Material Receiving
General - Instrument Rack and Panel Fabrication MEP
General - Instrumentation Enclosures, Racks and Panels -
MEP
Installation and Pre-Commissioning
MEP

Intrinsically Safe Circuit - Notification - Document Review MEP


Intrinsically Safe Circuit - Design / Procurement Package -
MEP
Document Review
Intrinsically Safe Circuit - Instruments, Barriers, & TB's
MEP
Material Receiving
Intrinsically Safe Circuit - Instrumentation, Box, and
MEP
Barrier Installation and Pre-Commissioning
Intrinsically Safe Circuit - Cable Installation, Termination,
MEP
Identification, and Pre-Commissioning
Intrinsically Safe Circuit - Circuit Final Inspection MEP
MEP
Exhaust and Supply Fan
MEP
Receiving, Handling, Storage and Preservation
Exhaust and Supply Fan Installation MEP
Air Moving / Cooling Equipment
MEP
Duct / Pipe Connection Installation
MEP
AHU Receiving, Handling, Storage and Preservation MEP
AHU Installation MEP
Essential Operating Facilities HVAC Requirements MEP
Condensate Drain Lay-out Inspection MEP
Pressurized Building HVAC Requirements MEP
Communication Facilities HVAC Requirements MEP
Battery Room HVAC Requirements MEP
MEP
Metal Duct, Metal Duct Insulation,
MEP
Metal Duct Hangers and Supports Receiving
Air Terminal Devices and Duct System Accessories
MEP
Receiving
Fire Damper Receiving MEP
Ducting System Storage, Handling and Preservation MEP
Metal Duct Hangers and Supports Installation MEP
Metal Duct Installation MEP
Metal Grease Duct MEP
Metal duct Insulation Installation MEP
Metal duct System accessories Installation MEP
Air Terminal Devices Installation MEP
Fire Damper Installation MEP
MEP
Chilled Water Piping lay-out and Supports Installation MEP
Chilled Water Piping two-way and Three Way Control
MEP
Valve Arrangement Installation
MEP
Chilled Water System Components Receiving MEP
Chilled Water System Components Installation MEP
MEP
MEP
Refrigerant Receiving, Storage, Handling and
MEP
Preservation
Refrigerant Piping, Fittings and Support Lay-out
MEP
Installation
Air Moving / Cooling Valve and
MEP
Apparatus Arrangement Installation
MEP
Filter Receiving, Handling, Storage and Preservation MEP
Filter Installation MEP
Grease Filter Installation MEP

MEP

Wall Mounted Air Conditioner


MEP
Receiving, Handling, Storage and Preservation
Wall Mounted Air Conditioner Installation MEP

MEP

Local Exhaust Hood


MEP
Receiving, Handling, Storage and Preservation
Passively Cooled Shelter Receiving MEP
Passively Cooled Shelter Installation MEP
Exhaust Hood Installation MEP
MEP
Air Cooled Condenser
MEP
Receiving, Handling, Storage and Preservation
Fan Coil Receiving, Handling, Storage and Preservation
MEP
Inspection
Air Cooled Condenser Installation MEP
Fan Coil Installation MEP

MEP

HVAC Systems Testing Organization Qualifications MEP


HVAC System Testing, Adjusting, and Balancing
MEP
Procedures
Final Inspection of HVAC Systems MEP
MEP
Civil
Grades, Elevation and Surface Preparation Inspection Civil
Civil
Trench Excavation and Preparation Inspection Civil
Pipe Lowering Inspection (Buried Pipeline) Civil
Backfilling and Berm Construction Inspection Civil
MEP
Review of Liquid Penetrant Testing Procedure MEP
Review of Personnel Qualification For Liquid Penetrant
MEP
Testing
Verification, Handling and Storage of LPT Materials MEP
In-Process Verification of Water Washable Fluorescent
MEP
Penetrant Examination
In-Process Verification of Solvent-Removable Fluorescent
MEP
Penetrant Examination
In-Process Verification of Water Washable Color Contrast
MEP
(Visible Dye) Penetrant Examination
In-Process Verification of Solvent-Removable Color
MEP
Contrast (Visible Dye) Penetrant Examination
MEP
Review of Leak Test Procedure MEP
Review of Personnel Qualification for Leak Testing MEP
Inspection/Verification of Leak Testing Devices MEP
Verification of Test Medium for Leak Testing MEP
Inspection/Verification of Pressure/Temperature
MEP
Indicating Instruments
Inspection/Verification Requirements Prior to Leak Test
MEP
Application
In-Process Inspection of Leak Testing Application MEP
Visual Inspection/Leak Detection MEP

Structural

Structural
Structural

Civil
Fence and Gates Components Receiving Inspection Civil
Pre-Cast Posts Receiving Inspection Civil
Location, Depth of Trench / Boreholes and Elevations
Civil
Inspection
Pre-pour Inspection Civil
Final Inspection Civil
Civil
Concrete Masonry Unit (CMU) compressive strength and
Civil
aggregate test reports
Concrete Masonry Units/Bricks Receiving Inspection Civil
Concrete Surface Preparation Inspection Civil
Concrete Masonry Units (CMUs)/Brick Walls and Plaster
Civil
Installation Inspection
Concrete and CMU Surface Preparation and Protection Civil

Masonry and Plaster Installation Civil


Civil

Waterproofing Roofs Receiving and Storage Inspection Civil

Surface Preparation, EDPM and Insulation Inspection Civil


Leak-Proof Testing and Final Inspection Civil
Structural
Structural Steel - Procedure for Pretensioning High
Structural
Strength Bolt Assemblies
Structural Steel Materials Receiving Inspection Structural
Structural Steel Materials - Storage, Handling &
Structural
Preservation Inspection
Structural Steel - Foundation or Connection Point
Structural
Inspection
Structural Steel - Erection Inspection Structural
Structural Steel - Final Bolt Tightening Inspection and
Structural
Testing
Structural Steel - Final Inspection Structural
Receiving Inspection of Fabricated Steel and Aluminum
Structural
Structure
Receiving Inspection - Bolts, Nuts & Washers for
Structural
Structural Connections
Review of Procedure for Tightening of High Strength
Structural
Bolts
Review of Procedure for Localized Heating to correct
Structural
Warping
Receiving Inspection Structural Steel, Shapes & Plates Structural
Storage Handling and Preservation of Structural Steel
Structural
Materials
Inspection of Support Foundation Prior to Structural
Structural
Installation
Inspection of Structural Alignment During Erection Structural
Repair/Correction of Errors of Structural Alignment Structural
High Strength Bolts Tightening Inspection and Testing Structural
Inspection of Structure Installations Structural
Structural Re-Instatement Punchlisting Structural
Structural
Building Components/Material Inspection Structural
Prefab Buildings -Foundations and Pre-Installation
Structural
Inspection
Prefab Buildings-Accessories and Installation Inspection Structural

Prefab Buildings - Interior and Exterior Final Inspection Structural

Prefab Buildings-Accessories and Installation Inspection Structural

Prefab Buildings - Interior and Exterior Final Inspection Structural

Civil
Gypsum Wall Board System Receiving and Storage
Civil
Inspection
Gypsum Wall Board Pre-Installation Inspection Civil
Gypsum Wall Board Framing, Insulation and Pre-closing
Civil
Inspections
Gypsum Wall Board System Plastering, Finishing and
Civil
Final Insp.
Civil
Ceramic Wall and Floor Tiles and Accessories Receiving
Civil
and Storage Inspection
Ceramic Wall and Floor Tile Pre-Installation and Surface
Civil
Preparation Inspection
Ceramic Wall and Floor Tiles Installation and Final
Civil
Inspection
Civil
Metal Doors and Windows Receiving Inspection Civil
Metal Doors and Windows Pre- Installation Inspection Civil
Metal Doors and Windows Installation Inspection Civil
Metal Doors and Windows Final Inspection Civil
Civil

Acoustical False Ceiling Receiving and Storage Inspection Civil


Acoustical False Ceiling suspension System Installation
Civil
Insp.
Acoustical False Ceiling Installation and Final Inspection Civil

Raised Equipment Floor Installation Inspection Civil


Civil
Glass and Glazing Receiving and Storage Inspection Civil
Glass and Glazing Pre-Installation Inspection Civil
Glass and Glazing Installation and Final Inspection Civil
Civil
Resilient Vinyl Floor Tile & Base Receiving & Storage
Civil
Inspection
Resilient Vinyl Floor Tile Installation and Final Inspection Civil

MEP
Review of Magnetic Particle Testing Procedure MEP
Review of Personnel Qualification for Magnetic Particle
MEP
Testing
Inspection/Verification of Magnetic Particle Testing
MEP
Devices
Storage and Handling of Magnetic Particle Testing
MEP
Devices
Inspection/Verification Requirements Prior to MPI
MEP
Application
In-Process Inspection of Magnetic Particle Testing MEP
Evaluation of Test and Test Report MEP
Demagnetization & Post Cleaning (MPT) MEP
Civil
Fence and Gates Components Receiving Inspection-
Civil
SSD/1 Fence
Pre-Cast Posts Receiving Inspection for SSD/1 Fence Civil
SSD/1 Location, Depth of Trench/Boreholes & Elevation
Civil
Inspection
Pre-Pour Inspection for SSD/1 Fence Civil
Final Inspection for SSD/1 Fence Civil
MEP
MEP
MEP
MEP
MEP
MEP
General - Electronic Equipment, Storage Handling &
MEP
Preservation
General - Electrical Equipment, Storage Handling &
MEP
Preservation
General - Switchgear Room / Substation, Equipment Pre-
MEP
Installation Inspection
UPS/DC Vented Ni-Cad Wet Cell, Storage Handling &
MEP
Preservation
UPS/DC Vented Lead-Acid Wet Cell, Storage Handling &
MEP
Preservation
UPS/DC Valve Regulated Lead-Acid (VRLA) Gelatin Cell,
MEP
Storage Handling & Preservation
UPS/DC Aqueous Sulfuric Acid Electrolyte, Storage
MEP
Handling & Preservation
UPS/DC Dry Potassium or Sodium Hydroxide Electrolyte,
MEP
Storage Handling & Preservation
UPS DC/AC Inverter, Material Receiving MEP
UPS Static Switch, Material Receiving MEP
UPS Transfer Switch Material Receiving MEP
UPS Bypass Line Transformer Material Receiving MEP
UPS Maintenance Bypass Switch Material Receiving MEP
UPS Panelboards / CB's Material Receiving MEP
UPS/DC Battery Rectifier / Charger Material Receiving MEP
UPS/DC Vented Ni-Cad Wet Cell Material Receiving MEP
UPS/DC Vented Lead-Acid Wet Cell Material Receiving MEP
UPS/DC VRLA Gelatin Cell Material Receiving MEP
UPS/DC Aqueous Sulfuric Acid Electrolyte Material
MEP
Receiving
UPS/DC Dry Potassium or Sodium Hydroxide Material
MEP
Receiving
UPS/DC System and Battery Accessories, Material
MEP
Receiving
UPS/DC Battery Room, Equipment Pre-Installation
MEP
Inspection
UPS/DC Equipment and Battery Rack, Installation and
MEP
Pre-Commissioning
UPS/DC System Electrochemical Battery Installation and
MEP
Pre-Commissioning
MEP
DC Switchboard / CB's, Material Receiving MEP
DC Panelboard / CB's, Material Receiving MEP
MEP
General - Hazardous Location Conduit and Cable Sealing
MEP
Special Work Procedure, Document Review
Cable Storage, Handling, & Preservation MEP
Low Voltage UL / NEC Power and Control Cable, Material
MEP
Receiving
Low Voltage NEC / SASO / IEC Unjacketed Wire, Material
MEP
Receiving
Low Voltage IEC Armored Cable, Material Receiving MEP
Low Voltage IEC Unarmored Cable, Material Receiving MEP

Low Voltage Power Cable Accessories, Material Receiving MEP


Low Voltage Power and Control Cable, Installation and
MEP
Pre-Commissioning
Low Voltage Building Wire, Installation and Pre-
MEP
Commissioning
Hazardous Location Conduit / Cable Seal Fitting
MEP
Installation and Sealing
MEP
Medium Voltage UL / NEC Cable, Material Receiving MEP
Medium Voltage IEC Cable, Material Receiving MEP
Medium Voltage Power Cable Accessories, Material
MEP
Receiving
Medium Voltage Cable, Installation and Pre-
MEP
Commissioning
MEP
Cable Tray and Accessories, Storage Handling &
MEP
Preservation
Cable Tray, Metallic Tray Systems, Material Receiving MEP
Cable Tray, Non-Metallic Tray Systems, Material
MEP
Receiving
Cable Tray, Non-Metallic Tray Accessories, Material
MEP
Receiving
Cable Tray Firewall Barriers, Material Receiving MEP
Cable Tray, Metallic Tray Systems, Installation and Pre-
MEP
Commissioning
Cable Tray, Non-Metallic Tray Systems, Installation and
MEP
Pre-Commissioning
Cable Tray Firewall Barriers, Installation and Pre-
MEP
Commissioning

MEP

General Boxes and Enclosures - Material Receiving MEP


General Boxes and Enclosures - Metallic Wireways and
MEP
Access, Material Receiving
General Boxes and Enclosures - Non-metallic Wireways
MEP
and Access, Material Receiving
General Boxes and Enclosures - Pushbutton and Pilot
MEP
light Control Stations and Access, Material Receiving
General Boxes and Enclosures - Non-Hazardous Indoor
MEP
Enclosures, Installation and Pre-Commissioning

General Boxes and Enclosures - Non-Hazardous Outdoor


MEP
Enclosures, Installation and Pre-Commissioning

General Boxes and Enclosures - Class I, Division 1 or


Zone 1, Hazardous Location Enclosures (Indoor and MEP
Outdoor), Installation, and Pre-Commissioning
General Boxes and Enclosures - Class I, Division 2 or
Zone 2, Hazardous Location Enclosures (Indoor and MEP
Outdoor), Installation, and Pre-Commissioning
MEP
Conduit - Storage, Handling, and Preservation MEP
Conduit - Galvanized Rigid Steel (GRS) Conduit, Material
MEP
Receiving
Conduit - Flexible Metal Conduit (FMC), Material
MEP
Receiving
Conduit - Liquid-Tight Flexible Metal Conduit (LT Flex),
MEP
Material Receiving
Conduit - Explosion-Proof Flexible Metal Couplings (EXP
MEP
Flex), Material Receiving
Conduit - Electrical Metallic Tubing (EMT), Material
MEP
Receiving
Conduit - EXP Fittings and Accessories, Material Receiving MEP
Conduit - EMT & FMC Fittings and Accessories, Material
MEP
Receiving
Conduit - GRS Fittings and Accessories, Material
MEP
Receiving
Conduit - LT Flex Fittings and Accessories, Material
MEP
Receiving
Conduit - Hazardous Location GRS & LT Flex Conduit
Systems (Class I, Zone or Div 2), Installation and Pre- MEP
Commissioning
Conduit - Hazardous Location GRS & EXP Flex Conduit
Systems (Class I, Zone or Div 1), Installation and Pre- MEP
Commissioning
Conduit - PVC-Coated GRS Conduit Systems (HL and
MEP
NHL), Installation and Pre-Commissioning
Conduit - GRS & LT Flex Conduit Systems (NHL),
MEP
Installation and Pre-Commissioning
Conduit - EMT & FMC Raceway Systems (NHL),
MEP
Installation and Pre-Commissioning
MEP
Pre-cast Duct bank / MH / HH, Jobsite Storage, Handling
MEP
and Preservation
Duct bank PVC Conduit, Material Receiving MEP
Pre-cast Duct bank, Fabrication and Jobsite Material
MEP
Receiving
Duct bank / MH / HH Excavation, Trenching, and
MEP
Backfilling
Cast-in-Place Duct bank Fabrication MEP
Manhole / Handhole Fabrication (Pre-Cast and Cast in
MEP
Place)
Duct bank Installation and Conduit Termination and
MEP
Capping
Duct bank / MH / HH Grounding and Bonding, Installation
MEP
and Pre-Commissioning
MEP
HVAC - Control Panel - Material Receiving, Installation
MEP
and Pre-Commissioning
HVAC - Air Cooled Condenser - Material Receiving,
MEP
Installation and Pre-Commissioning
HVAC - Air Handler Unit (AHU) - Material Receiving,
MEP
Installation, and Pre-Commissioning
HVAC - Centrifugal and Axial Fan - Material Receiving,
MEP
Installation, and Pre-Commissioning
HVAC - Air Cooled Chiller - Material Receiving,
MEP
Installation, and Pre-Commissioning
HVAC - E & I Installation for Pressurized Building
MEP
Inspection
MEP
Heat Tracing - Control Panel - Material Receiving MEP

Heat Tracing - Thermostat, Ambient - Material Receiving MEP


Heat Tracing - Thermostat, Capillary Tube & Bulb -
MEP
Material Receiving
Heat Tracing - Thermostat, RTD - Material Receiving MEP
Heat Tracing - Contactor - Material Receiving MEP
Heat Tracing - Tank Heating Pads - Material Receiving MEP

Heat Tracing - Instrument Housing - Material Receiving MEP


Heat Tracing - Mineral Insulated (MI) Cable - Material
MEP
Receiving
Heat Tracing - Self-Regulating Cable - Material Receiving MEP
Heat Tracing - Constant-Wattage Cable - Material
MEP
Receiving
Heat Tracing - Power-Limiting Cable - Material Receiving MEP

Heat Tracing - Cable Accessories - Material Receiving MEP

Heat Tracing System - Pre-Installation Visual Inspection MEP


Heat Tracing - Mineral Insulated (MI) Cable - Installation
MEP
and Pre-Commissioning
Heat Tracing - Self-Regulating Cable - Installation and
MEP
Pre-Commissioning
Heat Tracing - Constant-Wattage Cable - Installation and
MEP
Pre-Commissioning
Heat Tracing - Power-Limiting Cable - Installation and
MEP
Pre-Commissioning
Heat Tracing - Tank Heating Pads - Installation and Pre-
MEP
Commissioning
Heat Tracing - Instrument Housing - Installation and Pre-
MEP
Commissioning
Heat Tracing - Pre-Traced Tubing - Installation and Pre-
MEP
Commissioning
Heat Tracing - Power Connection Kit - Installation and
MEP
Pre-Commissioning
Heat Tracing - Tee Kit - Installation and Pre-
MEP
Commissioning
Heat Tracing - Spice Kit - Installation and Pre-
MEP
Commissioning
Heat Tracing - End Seal and End-of-Circuit Kit -
MEP
Installation and Pre-Commissioning
Heat Tracing - Control Panel - Installation and Pre-
MEP
Commissioning
Heat Tracing - Thermostat, Ambient - Installation and
MEP
Pre-Commissioning
Heat Tracing - Thermostat, Capillary Tube & Bulb -
MEP
Installation and Pre-Commissioning
Heat Tracing - Thermostat, RTD - Installation and Pre-
MEP
Commissioning
Heat Tracing - Contactor - Installation and Pre-
MEP
Commissioning
MEP
High Voltage Cable - Material Receiving MEP
High Voltage Cable Accessories - Material Receiving MEP

High Voltage Cable - Installation and Pre-Commissioning MEP

MEP
Very High Voltage Cable - Material Receiving MEP

Very High Voltage Cable Accessories - Material Receiving MEP


Very High Voltage Cable - Installation and Pre-
MEP
Commissioning
MEP
Receptacles & Cords - Pin-and-Sleeve Receptacle / Plug -
MEP
Material Receiving
Receptacles & Cords - NEMA Receptacle / Plug - Material
MEP
Receiving
Receptacles & Cords - Flexible Cord - Material Receiving MEP

Receptacles & Cords - Cable Reels - Material Receiving MEP


Receptacles & Cords - Festoon Systems - Material
MEP
Receiving
Receptacles & Cords - Festoon Systems - Installation MEP
MEP
Overhead T&D Cable Termination and Splicing Special
MEP
Work Procedure, Document Review
Overhead T&D Power Pole - Wood, Storage and Material
MEP
Receiving
Overhead T&D Power Pole - Galvanized Steel, Storage
MEP
and Material Receiving
Overhead T&D Power Structure - Galv. Lattice Steel,
MEP
Storage and Material Receiving
Overhead T&D ACSR/AW Cable, Material Receiving MEP
Overhead T&D Surge Arresters, Material Receiving MEP
Overhead T&D Capacitor Banks, Material Receiving MEP
Overhead T&D Metering Cabinet, Material Receiving MEP
Overhead T&D Circuit Accessories, Material Receiving MEP
Overhead T&D Power Pole, Installation MEP
Overhead T&D Power Structure, Installation MEP
Overhead T&D Equipment Installation and Pre-
MEP
Commissioning
Overhead T&D Cable, Installation and Pre-Commissioning MEP

MEP
General - Exothermic (Thermite) Welding Materials,
MEP
Molds, & Tools - Material Receiving
GES - DCS/ESD/PLC/SCADA Grounding Installation MEP
GEC/EGC - AC UPS System Grounding MEP
GEC/EGC - DC System Grounding Installation MEP
Grounding - GES - Ground Rods - Material Receiving MEP
Electrical Grounding System - Final Inspection MEP
Grounding - GES - Zinc and Magnesium Anode Electrodes
MEP
- Material Receiving
Grounding - GES - Ground Electrode Cable - Material
MEP
Receiving
Grounding - Bare Copper Ground Conductor - Material
MEP
Receiving
Grounding - Bare Tinned Copper Ground Conductor -
MEP
Material Receiving
Grounding - Hydraulic Compression Fittings and Tools -
MEP
Material Receiving
Grounding and Bonding Accessories - Material Receiving MEP

Grounding - Neutral Ground Resistor - Material Receiving MEP


Grounding - GES - Copper, Copper-Clad Steel, Galvanized
MEP
Steel Rod Installation
Grounding - GES - Zinc and Magnesium Anode Electrode
MEP
Installation
Grounding - GES/GEC - Exothermic (Thermite) Welding
MEP
Installation
Grounding - GES/GEC/EGC - Hydraulic Compression
MEP
Connectors Installation
Grounding - GES - Concrete Embedded Copper Electrode
MEP
Installation
Grounding - GES - Piping Electrode Installation MEP

Grounding - GES - Structural Steel Electrode Installation MEP


Grounding - GES - Copper Conductor Ground Ring
MEP
Installation
Grounding - GES - Power Ground Electrode System (GES)
MEP
Installation
Grounding - GES - Substation Grounding Installation MEP
Grounding - GES - Cathodic Protection Grounding
MEP
Installation
GES - Offshore Grounding Installation MEP

GES - Telecommunications Grounding System Installation MEP

GEC - High Resistance Grounding Installation MEP


GEC - LV Dry Transformer Grounding Installation MEP
GEC/EGC - Panelboard Grounding Installation MEP
GEC/EGC - Switchgear / Control gear Grounding
MEP
Installation
GEC/EGC - DG Set System Grounding Installation MEP
GEC/EGC - ATS / MTS System Grounding Installation MEP
GEC/EGC - Pad-Mounted Transformer Grounding
MEP
Installation
GEC/EGC - Power Transformer Grounding Installation MEP

GEC/EGC - Variable Speed Drive Grounding Installation MEP

EGC - Cable Tray Grounding / Bonding Installation MEP


EGC - Conduit Grounding / Bonding Installation MEP
EGC - Buried Cable Grounding / Bonding Installation MEP
EGC - Duct bank Grounding / Bonding Installation MEP
EGC - Electrical Eqpt. Grounding / Bonding Installation MEP
EGC - Instrumentation Grounding / Bonding / Shielding
MEP
Installation
EGC - Surge Arrestor Grounding / Bonding Installation MEP
EGC - Process Eqpt. Grounding / Bonding Installation MEP

EGC - Structural Steel Grounding / Bonding Installation MEP

EGC - LV Cable Grounding / Bonding Installation MEP


EGC - MV Cable Grounding / Bonding / Shielding
MEP
Installation
EGC - Raised Floor Grounding / Bonding Installation MEP
EGC - Offshore Grounding / Bonding Installation MEP
EGC - Fence Grounding / Bonding Installation MEP
EGC - Tank Grounding / Bonding Installation MEP

EGC - Static Electricity Grounding / Bonding Installation MEP

EGC - Isolated Grounding / Bonding Installation MEP


MEP
Lightning Protection Air Terminals Material Receiving MEP

Lightning Protection Ground Terminals Material Receiving MEP

Lightning Protection Cable Material Receiving MEP


Lightning Protection Accessories Material Receiving MEP
Lightning Protection Air Terminals Installation MEP
Lightning Protection Ground Terminals Installation MEP
Lightning Protection Loop / Down / Bonding Conductor
MEP
Installation
MEP
LV SCIM - Motor Storage, Handling, and Preservation MEP
LV SCIM - Explosion-Proof Motor Material Receiving MEP
LV SCIM - Severe Duty TE Motor Material Receiving MEP
LV SCIM - API Air-Cooled H/E Fan Motor Material
MEP
Receiving
LV SCIM - Non-Industrial Facilities Motor Material
MEP
Receiving
LV SCIM - Squirrel-Cage Induction Motor Installation and
MEP
Pre-Commissioning

MEP

MV Motor - Storage, Handling, and Preservation MEP


MV Motor - Form Wound Squirrel Cage Induction Motor
MEP
(SCIM) Material Receiving
MV Motor - Form Wound Synchronous Motor Material
MEP
Receiving
MV Motor - Non-industrial Facilities Motor Material
MEP
Receiving
MV Motor - Motor Accessories Material Receiving MEP
MV Motor - Motor Installation and Pre-Commissioning MEP
MEP
DG Set - Storage, Handling, and Preservation MEP
DG Set - Engine and Synchronous Generator Material
MEP
Receiving
DG Set - GCB, Voltage Regulator, Enclosure, Load Test
MEP
Set, and DG Accessories Material Receiving
DG Set - Installation and Pre-Commissioning MEP
MEP
Cranes, Hoists, Elevators - Specialty Equipment and
MEP
Accessories Material Receiving
Cranes, Hoists, Elevators - Installation and Pre-
MEP
Commissioning

MEP

Protection & Metering - Annunciator Panel Material


MEP
Receiving
Protection & Metering - Metering Cabinet Material
MEP
Receiving
Protection & Metering - Relay Cabinet Material Receiving MEP
Protection & Metering - Current Transformer Material
MEP
Receiving
Protection & Metering - Potential Transformer Material
MEP
Receiving
Protection & Metering - Protection Relay Material
MEP
Receiving
Protection & Metering - Electric Meter / Recorder Material
MEP
Receiving
Protection & Metering - Accessories Material Receiving MEP
Protection & Metering - Equipment Installation and Pre-
MEP
Commissioning
Protection & Metering - CT and PT Installation and Pre-
MEP
Commissioning
Protection & Metering - Relay Installation and Pre-
MEP
Commissioning
Protection & Metering - Meter / Recorder Installation and
MEP
Pre-Commissioning
MEP
MV Switchgear - Metal-Clad Switchgear (Indoor/Outdoor)
MEP
Material Receiving
MV Switchgear - SF6 Switchgear (Outdoor) Material
MEP
Receiving
MV Switchgear - Manual SF6 Circuit Breaker Material
MEP
Receiving
MV Switchgear - Vacuum Circuit Breaker (Motor Load)
MEP
Material Receiving
MV Switchgear - Vacuum Circuit Breaker (Feeder Load)
MEP
Material Receiving
MV Switchgear - Accessories Material Receiving MEP
MV Switchgear - Metal-Clad Switchgear Installation and
MEP
Pre-Commissioning
MV Switchgear - SF6 Switchgear Installation and Pre-
MEP
Commissioning
MV Switchgear - MV Manual SF6 Circuit Breaker Pre-
MEP
Commissioning
MV Switchgear - MV Vacuum Circuit Breaker - Motor Load
MEP
Pre-Commissioning
MV Switchgear - MV Vacuum Circuit Breaker - Feeder
MEP
Pre-Commissioning
MEP
MV Control gear - Metal-Enclosed Equipment
MEP
(Indoor/Outdoor) Material Receiving
MV Control gear - Power Circuit Breaker Material
MEP
Receiving
MV Control gear - Metal-Enclosed Equipment Installation
MEP
and Pre-Commissioning
MV Control gear - Power Circuit Breaker Pre-
MEP
Commissioning
MV Control gear - Fused Motor Controller Pre-
MEP
Commissioning
MV Control gear - Fused Switching Assembly Pre-
MEP
Commissioning
MEP
LV Switchgear - Indoor/Outdoor Equipment Material
MEP
Receiving
LV Switchboard - Material Receiving MEP

LV Switchgear - Power Circuit Breaker Material Receiving MEP


LV Switchgear / Switchboard - Molded Case Breaker
MEP
Material Receiving
LV Switchgear / Switchboard - Accessories Material
MEP
Receiving
LV Switchgear - Power Circuit Breaker Pre-Commissioning MEP
LV Switchgear / Switchboard - Molded Case Breaker Pre-
MEP
Commissioning
LV Switchgear - Metal-Enclosed Equipment Installation
MEP
and Pre-Commissioning
LV Switchboard - Installation and Pre-Commissioning MEP
MEP
LV Control gear - Metal-Enclosed Equipment
MEP
(Indoor/Outdoor) Material Receiving
LV Control gear - Power Circuit Breaker Material
MEP
Receiving
LV Control gear - Full Voltage Motor Controller Material
MEP
Receiving
LV Control gear - Reduced Voltage Motor Controller
MEP
Material Receiving
LV Control gear - Feeder Contactor Material Receiving MEP
LV Control gear - ATS / MTS Material Receiving MEP
LV Control gear - Accessories Material Receiving MEP
LV Control gear - Metal-Enclosed Equipment Installation
MEP
and Pre-Commissioning
LV Control gear - Power Circuit Breaker Pre-
MEP
Commissioning
LV Control gear - Full Voltage Motor Controller Pre-
MEP
Commissioning
LV Control gear - Reduced Voltage Motor Controller Pre-
MEP
Commissioning
LV Control gear - Feeder Contactor Pre-Commissioning MEP

LV Control gear - ATS / MTS Pre-Commissioning MEP


MEP
Switchrack Material Receiving MEP
Switchrack Pre-Commissioning MEP
MEP

LV SCIM for Fire Water Pump Service Material Receiving MEP

LV Severe Duty TE SCIM Material Receiving MEP


LV SCIM for Non-Industrial Facilities (Jockey Pump
MEP
Service) Material Receiving
LV Motor Controller for Fire Service Material Receiving MEP
Fire / Jockey Pump Motors & Controller Installation and
MEP
Pre-Commissioning
MEP
LV Panelboard-Industrial Outdoor
MEP
Panelboard(≤400A)Material Receiving
LV Panelboard - Non-Industrial Panelboard Material
MEP
Receiving
LV Panelboard - Industrial Explosion-Proof Panelboard
MEP
(≤400A) Material Receiving
LV Panelboard - Non-Hazardous AC/DC Panelboard
MEP
Installation and Pre-Commissioning
LV Panelboard - Explosion-Proof Panelboard Installation
MEP
and Pre-Commissioning
MEP
MV Non-Seg Busduct Material Receiving MEP

MV Non-Seg Busduct Installation and Pre-Commissioning MEP


MV Non-Seg Busduct Bulkhead Fire Barrier Installation
MEP
and Pre-Commissioning
MEP
MV Cable bus Framework Material Receiving MEP
MV Cable bus Conductor Material Receiving MEP
MV Cable bus Accessories Material Receiving MEP
MV Cable bus Installation and Pre-Commissioning MEP
MV Cable bus Bulkhead Fire Barrier Installation and Pre-
MEP
Commissioning
MEP
LV Non-Seg Busduct Material Receiving MEP
LV Non-Seg Busduct Accessories Material Receiving MEP

LV Non-Seg Busduct Installation and Pre-Commissioning MEP


LV Non-Seg Busduct Bulkhead Fire Barrier Installation
MEP
and Pre-Commissioning
MEP
LV Cable bus Framework Material Receiving MEP
LV Cable bus Conductor Material Receiving MEP
LV Cable bus Accessories Material Receiving MEP
LV Cable bus Installation and Pre-Commissioning MEP
LV Cable bus Bulkhead Fire Barrier Installation and Pre-
MEP
Commissioning
MEP
VSD - Air Cooled LV Adjustable Frequency Drive (AFD)
MEP
Material Receiving
VSD - Liquid Cooled LV AFD Material Receiving MEP
VSD - Air Cooled MV AFD Material Receiving MEP
VSD - Liquid Cooled MV AFD Material Receiving MEP

VSD - Source Isolation Transformer Material Receiving MEP

VSD - Induction Motors Material Receiving MEP


VSD - DC Link Reactor Material Receiving MEP
VSD - Cooling Liquid Pumps Material Receiving MEP
VSD - Cooing Fans Material Receiving MEP
VSD - Cooling Liquid Piping Material Receiving MEP
VSD - Cooling System Valves Material Receiving MEP

VSD - Painting / Coating / Insulation Material Receiving MEP

VSD - Cooling System Heat Exchanger Material Receiving MEP

VSD - Cooling Control System Material Receiving MEP


VSD - Air Cooled LV Adjustable Frequency Drive (AFD)
MEP
Material Receiving
VSD - Liquid Cooled LV AFD Installation and Pre-
MEP
Commissioning
VSD - Air Cooled MV AFD Installation and Pre-
MEP
Commissioning
VSD - Liquid Cooled MV AFD Installation and Pre-
MEP
Commissioning
VSD - Source Isolation Transformer Installation and Pre-
MEP
Commissioning
VSD - Induction Motors Installation and Pre-
MEP
Commissioning
VSD - DC Link Reactor Installation and Pre-
MEP
Commissioning
VSD - Cooling Liquid Pumps Installation and Pre-
MEP
Commissioning
VSD - Cooing Fans Installation and Pre-Commissioning MEP
VSD - Cooling Liquid Piping Installation and Pre-
MEP
Commissioning
VSD - Cooling System Valves Installation and Pre-
MEP
Commissioning
VSD - Painting / Coating / Insulation Installation and Pre-
MEP
Commissioning
VSD - Cooling System Heat Exchanger Installation and
MEP
Pre-Commissioning
VSD - Cooling Control System Installation and Pre-
MEP
Commissioning
MEP
Switchyard - ACSR Cable and Accessories Storage,
MEP
Handling, and Preservation
Switchyard - HV Equipment Storage, Handling, and
MEP
Preservation
Switchyard - Seamless Aluminum Bus Pipe and
MEP
Accessories Material Receiving and Storage
Switchyard - Aluminum Conductor Steel Reinforced
MEP
(ACSR) Cable and Accessories Material Receiving
Switchyard - HV SF6 C/B's and Switchgear Material
MEP
Receiving
Switchyard - HV Post Insulators Material Receiving MEP
Switchyard - HV Surge Arrestors and Capacitors Material
MEP
Receiving
Switchyard - HV Disconnect Switches (Motor-operated
MEP
and manual) Material Receiving
Switchyard - HV Metering and Protection CT's & PT's
MEP
Material Receiving
Switchyard - HV SF6 C/B's and Switchgear Installation
MEP
and Pre-Commissioning
Switchyard - HV Post Insulators Installation and Pre-
MEP
Commissioning
Switchyard - HV Surge Arrestors and Capacitors
MEP
Installation and Pre-Commissioning
Switchyard - HV Disconnect Switches (Motor-operated
MEP
and manual) Installation and Pre-Commissioning
Switchyard - HV Metering and Protection CT's & PT's
MEP
Installation and Pre-Commissioning
Switchyard - Seamless Aluminum Bus Pipe and
MEP
Accessories Installation and Pre-Commissioning
Switchyard - Aluminum Conductor Steel Reinforced
(ACSR) Cable and Accessories Installation and Pre- MEP
Commissioning
MEP
Dry Transformer - LV Non-Vented Xfmr (≤500 kVA, LV
MEP
Pri) Material Receiving and Storage
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Material
MEP
Receiving and Storage
Dry Transformer - LV Xfmr (≤500 kVA, LV Pri) Assembly,
MEP
Installation and Pre-Commissioning
Dry Transformer - MV Xfmr (MV or ≥501 kVA) Assembly,
MEP
Installation and Pre-Commissioning
MEP

Power Transformer - Storage, Handling, and Preservation MEP


Power Transformer - Material Receiving MEP
Power Transformer Accessories - Material Receiving MEP

Power Transformer - Installation, Assembly, and Filling MEP

Power Transformer - Pre-Commissioning and Energization MEP

MEP
Overhead Transformer - Material Receiving MEP

Overhead Transformer Accessories - Material Receiving MEP


Overhead Transformer - Installation, Assembly, and
MEP
Filling
Overhead Transformer - Pre-Commissioning and
MEP
Energization
MEP
Self-Cooled Pad-Mounted MV Transformer - Material
MEP
Receiving
Self-Cooled Pad-Mounted MV Transformer Accessories -
MEP
Material Receiving
Self-Cooled Pad-Mounted MV Transformer - Installation,
MEP
Assembly, and Filling
Self-Cooled Pad-Mounted MV Transformer - Pre-
MEP
Commissioning and Energization
MEP
Fluorescent Light Fixtures - Material Receiving MEP
HID Light Fixtures - Material Receiving MEP
Emergency Light Fixtures - Material Receiving MEP
Incandescent Light Fixtures - Material Receiving MEP
12V High Intensity Incandescent Fixtures - Material
MEP
Receiving
Aviation / Obstruction Light Fixtures - Material Receiving MEP

Lighting Accessories - Material Receiving MEP


Light Pole Assembly and Installation MEP
Hung Ceiling Light Fixtures - Assembly, Installation, and
MEP
Pre-Commissioning
Surface Mounted Light Fixtures - Assembly, Installation,
MEP
and Pre-Commissioning
Flush Mounted Light Fixtures - Assembly, Installation,
MEP
and Pre-Commissioning
HID High-bay Light Fixtures - Assembly, Installation, and
MEP
Pre-Commissioning
HID Low-bay Light Fixtures - Assembly, Installation, and
MEP
Pre-Commissioning
Lighting Control System - Installation and Pre-
MEP
Commissioning
Pole-Mounted Light Fixtures - Assembly, Installation, and
MEP
Pre-Commissioning
Security Light Fixtures (Fence, Area, and Checkpoint Ltg.)
MEP
- Assembly, Installation, and Pre-Commissioning
Aviation / Obstruction Light Fixtures - Assembly,
MEP
Installation, and Pre-Commissioning
Offshore Light Fixtures - Assembly, Installation, and Pre-
MEP
Commissioning

MEP

General Mechanical Equipment Skid for Zone or Div 1 -


MEP
Material Receiving
General Mechanical Equipment Skid for Zone or Div 2 -
MEP
Material Receiving
General Mechanical Equipment Skid for Non-Hazardous
MEP
Locations - Material Receiving
General Mechanical Equipment Skid for Corrosive
MEP
locations - Material Receiving
General Electrical Workspace Clearances MEP

Civil

Review Monthly Aggregate & Water Test Reports and


Civil
Calibration Certificate
Concrete Batch Plant/Equipment Inspection Civil
Concrete Ingredients (Cement, Aggregates, Water and
Civil
admixture Inspection
Freshly-Mixed Concrete Inspection Civil
Plant QC Lab Inspection Civil
Civil
Concrete Mix Design Approval Civil
Epoxy Coated Steel Bars and Embedded Items Receiving
Civil
Inspection
Handling, Storage and Preservation of Epoxy Coated
Civil
Steel Bars Inspection
Cast-in-Place Ready Mix Concrete Receiving Inspection Civil

Concrete Pump / Transit Mixer Inspection Civil


Grade & Site Preparation Inspection Civil
Formwork Inspection Civil
Installation of Epoxy Coated Steel Bars, Embedded Items
Civil
and Form Closure Inspection
Placement/Pouring and Testing Inspection Civil
Concrete Finishing & Curing Inspection Civil
Formwork Stripping Inspection Civil
Concrete Final Acceptance Inspection Civil
Concrete Sampling, Testing & Placement Inspection Civil

Civil

Epoxy Coated Steel Bars and Formwork Inspection Civil


Pre-Cast Concrete Posts at Fabrication Yards Concrete
Civil
Placement, Sampling and Testing Inspection
Demolding and Concrete Curing Inspection Civil
Final Inspection Civil
Structural

Pre-Cast & Prestressed Pre-Concreting Inspection Structural


Pre-Cast & Prestressed Concrete Casting Beds Set-Up
Structural
Inspection (Prestressed)
Tensioning & Releasing Inspection for Prestressed/Pre-
Structural
tensioned Concrete
Precast & Prestressed Concrete Placement, Sampling and
Structural
Testing Inspection
Tensioning & Grouting Inspection for Prestressed/Post
Structural
Tensioned Concrete
Precast & Post Tensioned Concrete Final Inspection Structural
Structural
Grout Mix Design Structural
Pile Driving Equipment Inspection Structural
Drilling Equipment Inspection Structural
Pile Grouting Equipment Inspection Structural
Grouting Material Inspection Structural
Fixing Piles Structural
Drilling Activity Structural
Pile & Pile Marking Structural
Pile Installation Structural
Grout-Pile to Jacket Leg Structural
Grout Plug Structural
Civil
Monthly Aggregate Test Reports and Calibration
Civil
Certificate
Plant Equipment and Plant Set Up Inspection Civil

Asphaltic Concrete Ingredients Inspection at Batch Plants Civil

Hot Mix Asphalt Inspection Civil


Plant QC Lab Inspection (Asphalt) Civil
Civil
Aggregate Subbase and Base Course Materials Test
Civil
Reports
Asphalt Mix Design Review Civil
Subbase and Aggregate Base Course Material Receiving
Civil
Inspection
Asphaltic Binder & Wearing Course Receiving Inspection Civil

Grades, Elevation and Surface Preparation Inspection Civil


Placement and Compaction of Subbase and Aggregate
Civil
Base Course Material Inspection
Prime Coating and Tack Coating Inspection Civil
Asphaltic Concrete Receiving, Placement/Compaction of
Civil
Asphaltic Binder and Wearing Courses Inspection
Asphalt Core Density Testing Civil
Asphaltic Pavement Final Inspection Civil
Asphaltic Concrete Receiving, Placement / Compaction of
Civil
Binder and Wearing Courses Inspection

Civil
Review of Engineering Properties of
Civil
Foamed Stabilizing Agents and Subbase Materials
Stabilization Equipment Set-Up Inspection Civil
Placement Compaction & Quality Control of
Civil
Foamed Stabilization Materials
Civil
Grout Samples Compressive strength test reports Civil

Material Components & Ingredients Receiving Inspection Civil

Storage and preservation Inspection Civil


Cement Based Non-Shrink Grout Surface Preparation &
Civil
Formwork Inspection
Mixing, Placement, Sampling and Testing Inspection Civil
Grout Curing Inspection Civil
Final Inspection Civil
Civil

Epoxy Grout Samples Compressive Strength Test Reports Civil

Epoxy Grout Materials Receiving and Storage Inspection Civil

Surface Preparation And Formwork Inspection Civil

Grout Mixing, Placement, Sampling & Testing Inspection Civil


Foundation and Grout Curing/Protection & Final
Civil
Inspection
MEP
Review of Radiographic Testing Procedure MEP
Review and Approval of RT Personnel Qualifications MEP
Review of Radiation Safety Procedure MEP
Inspection/Verification of Radiographic Testing Devices,
MEP
Monitors and Safety Equipment
Inspection of RT Films and Developing Equipment MEP
Storage, Handling and Preservation of Radiographic
MEP
Testing Equipment
In-Process Verification of Techniques & Procedure
MEP
Implementation of RT
Verification of Film Processing MEP
Film Evaluation, Reporting and Storage of Film MEP
MEP
Sewer Manhole Receiving, Handling, Storage and
MEP
Preservation Inspection
Sanitary Sewer Pipe Lay-Out MEP
Sanitary manhole Installation inspection MEP
MEP
Wet Well and Wet Well / Dry Well Receiving, handling,
MEP
storage and preservation
Lift Station Electrical and Control Receiving, Handling,
MEP
Storage and Preservation
Force Main / Piping lay-out MEP
Thrust Block Installation MEP

Wet Well and Wet Well / Dry Well lift stations installation MEP

Lift Station Control System Installation inspection MEP


Lift Station Enclosure Installation Inspection MEP
Final Inspection of sanitary sewage lift station MEP
MEP
Storm water drainage systems installation MEP

MEP

Water Distribution Piping Lay-Out (Upstream) MEP


Piping Hangers and Support Receiving, Handling and
MEP
storage
Water Distribution Piping Lay-Out (downstream) MEP
Hangers and Support Installation MEP
Disinfection of newly constructed water mains MEP
Final Inspection of Water Distribution System MEP
MEP
Sprinkler and Standpipe System Receiving, Handling,
MEP
Storage and Preservation
Sprinkler Piping and fitting Installation MEP
Location and Spacing of sprinkler MEP
Valve Installation MEP
Final Inspection of building sprinkler and stand pipe
MEP
system
Fire Sprinkler System [Hanging, bracing and restraint of
MEP
system piping]+B1321
Sprinkler Installation MEP
Water Flow Alarm and Fire Department Connections MEP
MEP
Electric Water Heater Receiving, Handling, Storage and
MEP
Preservation
Electric Water Heater Installation and piping connection MEP

MEP
Receiving and Storage of electric water coolers MEP
Installation of electric drinking water coolers MEP
MEP

Skid Mounted R.O. System Receiving, Handling, Storage MEP

Installation of reverse osmosis system MEP


Final inspection of reverse osmosis system MEP
MEP
Plumbing Fixture Receiving and Storage MEP
Plumbing Fixtures Installation MEP
MEP
Roof Drain Installation Inspection MEP
Roof Drain Receiving and storage MEP
MEP
Drainage system layout MEP
Vent Piping connection MEP
Trap Inspection MEP
MEP
Indirect waste piping installation MEP
Neutralization Tank & its accessories Receiving, Handling,
MEP
Storage and Preservation Inspection
Neutralization Tank and its piping connection MEP

Neutralization Tank and its accessories Final Inspection MEP

MEP
Brazer Qualifications Document Review MEP
Brazing Procedures Document Review MEP
Copper Pipe and Brazing wire receiving MEP
Copper Pipe Installation MEP

Civil

Clean Sand and Aggregate Base Course Test Reports Civil


Clean Sand and Aggregate Base Course Receiving
Civil
Inspection
Excavation Bracing And De-Watering Inspection Civil

Excavation, Placement and Compaction in Subkha Areas Civil


Excavation, Placement and Compaction in Non-Subkha
Civil
Areas
Excavation, Placement and Compaction in Trenches With
Civil
High Pressure Piping
Final Inspection Civil
MEP
Control wire installation MEP
Irrigation Piping lay-out MEP
Irrigation system Installation MEP
MEP
RTR & Thermoplastic Pipe Installer Qualifications MEP
RTR and Thermoplastic Pipe Receiving [Pressure and
MEP
sewer pipe]
RTR and Thermoplastic Pipe Handling, Storage and
MEP
Preservation Inspection
Assembly of Thermoplastic Piping (UPVC, PVC, CPVC and
MEP
HDPE)
Assembly and laying of RTR Piping MEP
Civil

OSP Duct bank Excavation & Backfilling for Non-Traffic


Civil
Areas
MEP
General - Indoor Electronic Equipment - Storage,
MEP
Handling, and Preservation
DC System - DC Master Ground Busbar (MGB) - Material
MEP
Receiving
DC System - DC MGB - Installation and Pre-
MEP
Commissioning
MEP
Page-Party P.A. System - Manufacturer's Page-Party-
MEP
Power Cable - Material Receiving
Page-Party P.A. System - Manufacturer's Speaker Cable -
MEP
Material Receiving
Page-Party P.A. System - Speaker - Material Receiving MEP
Page-Party P.A. System - Page-Party Station - Indoor -
MEP
Material Receiving
Page-Party P.A. System - Page-Party Station - Outdoor -
MEP
Material Receiving
Page-Party P.A. System - Speaker Amplifier - Material
MEP
Receiving
Page-Party P.A. System - Line Balance Assembly -
MEP
Material Receiving
Page-Party P.A. System - Page-Party Accessories -
MEP
Material Receiving
Page-Party P.A. System - Installation and Pre-
MEP
Commissioning
MEP
Communication Systems - Equipment Racks - Material
MEP
Receiving
Communication Systems - RF Equipment - Material
MEP
Receiving
Communications Systems - Antenna - Material Receiving MEP
Communications Systems - PBX / Distribution Equipment
MEP
- Material Receiving
Communications Systems - Transmission Equipment -
MEP
Material Receiving
Equipment Material Receiving Visual Inspection User-
MEP
Premise Equipment
Communications Systems - RF Waveguide / Coaxial Cable
MEP
- Material Receiving
Communications Systems Accessories - Material
MEP
Receiving
Communications Systems - Equipment Racks -
MEP
Installation and Pre-Commissioning
Communications Systems - RF Equipment - Installation
MEP
and Pre-Commissioning
Communications Systems - PBX / Distribution Equipment
MEP
- Installation and Pre-Commissioning
Communications Systems - Transmission Equipment -
MEP
Installation and Pre-Commissioning
Equipment Installation Visual Inspection User Premise
MEP
Equipment
Communications Systems - Antenna - Installation and
MEP
Pre-Commissioning
Communications Systems - Waveguide Bulkhead -
MEP
Installation and Pre-Commissioning
Communications Systems - RF Waveguide / Cox -
MEP
Installation and Pre-Commissioning
MEP
Fiber Optic Circuits - OSP Single-mode FOC Cable -
MEP
Material Receiving
Fiber Optic Circuits - OSP- Multi mode FOC Cable -
MEP
Material Receiving
Fiber Optic Circuits - Bldg. Single-mode FOC Cable -
MEP
Material Receiving
Fiber Optic Circuits - Bldg Multi mode FOC Cable -
MEP
Material Receiving
Fiber Optic Circuits - Optical Fiber Splicing Accessories -
MEP
Material Receiving
Fiber Optic Circuits - Optical Fiber Testing Accessories -
MEP
Material Receiving
Fiber Optic Circuits - Cable Accessories - Material
MEP
Receiving
Fiber Optic Circuits - OSP FOC Cable - Installation,
MEP
Termination, and Identification
Fiber Optic Circuits - Inter- and Intra-Building FO Cable -
MEP
Installation, Termination, and Identification
Fiber Optic Cable Installation Procedure MEP
MEP
Copper Circuits - Cable Storage, Handling, and
MEP
Preservation
Copper Circuits - OSP Feeder Cable - Material Receiving MEP

Copper Circuits - ISP Building Cable - Material Receiving MEP

Copper Circuits - Cable Accessories - Material Receiving MEP

Copper Circuits - Excavation, Trenching & Backfilling MEP


Copper Circuits - OSP Cable -Under ground Installation
MEP
and Pre-Commissioning
Copper Circuits - ISP Building Cable - Installation and
MEP
Pre-Commissioning
MEP
Copper Circuits -OSP Cable - Direct buried Installation
MEP
and Pre-Commissioning
Indoor Pre-Installation Visual Inspection MEP
Comm Facilities - Self-Supporting Communication Tower -
MEP
Material Receiving
Comm Facilities - Guyed Steel Communication Tower -
MEP
Material Receiving
Comm Facilities - Cable Rack Material Receiving MEP
Comm Facilities - Communication Tower - Installation and
MEP
Pre-Commissioning
Comm Facilities - HVAC Systems - Installation and Pre-
MEP
Commissioning
Comm Facilities - Security IDAS / CACS - Installation and
MEP
Pre-Commissioning
Comm Facilities - Vault Cable Rack - Installation and Pre-
MEP
Commissioning
MEP
MEP
OSP Duct bank - Plastic Conduit / Sleeves / Innerduct -
MEP
Storage, Handling, and Preservation
OSP Duct bank - Man hole & Hand hole hardware -
MEP
Storage, Handling, and Preservation
OSP Duct bank - Conduit Plugs / Seal Fittings / Innerduct
MEP
Accessories - Storage, Handling, and Preservation
OSP Duct bank - PVC Plastic Conduit / Sleeves - Material
MEP
Receiving
OSP Duct bank - Manhole & Handhole Hardware -
MEP
Material Receiving
OSP Duct bank - Plastic Innerduct / Accessories -
MEP
Material Receiving
OSP Duct bank - Conduit Fittings and Accessories -
MEP
Material Receiving
OSP Duct bank - Duct bank Fabrication, Installation, and
MEP
Mandrel Test
OSP Duct bank - Manhole Fabrication and Installation MEP
OSP Duct bank - Inner duct Installation and
MEP
Identification
OSP Duct bank - Conduit ID Termination MEP
MEP
BPDS Cable Tray Systems - Material receiving MEP
BPDS Square "D" Ducting System - Material receiving MEP
BPDS Cellular and Underfloor Ducting Systems - Material
MEP
receiving
BPDS Distribution Conduit System - Material receiving MEP
BPDS UTP/STP Copper Cable - Material receiving MEP
BPDS Indoor Fiber Optic Cable - Material receiving MEP

BPDS Equipment Racks & Accessories - Material receiving MEP

BPDS Cable Management Trays - Material receiving MEP


BPDS Horizontal Connecting Hardware - Material
MEP
receiving
BPDS Backbone Connecting Software - Material receiving MEP

TC/TER Size and Location MEP


TC Miscellaneous Requirements MEP
TER Miscellaneous Requirements MEP
TC Power Requirements MEP
TER Power Requirements MEP
Installation Backbone Cable Tray System MEP
Installation Backbone Conduits System MEP
Installation Sleeve and Slots System MEP
Installation Horizontal Cable Tray Systems MEP
Installation Square "D" Ducting System MEP
Installation Cellular and Underfloor Systems MEP
Installation Horizontal Distribution Conduit System MEP
Installation Conduit for Home Run Ceiling System MEP
Installation Sizing & Installation Indoor Pull Boxes MEP
Work area outlet Boxes Installation MEP
BPDS Sizing & Installation Outdoor Pull Boxes MEP
BPDS Horizontal UTP/STP Copper Cable MEP
Installation Horizontal Fiber Optic Cable MEP
Installation Horizontal Connecting Hardware MEP
BPDS Backbone UTP/STP Copper Cable MEP
Installation Backbone Fiber Optic Cable MEP
Installation Backbone Connecting Software MEP
Installation Equipment Racks & Accessories MEP
Installation Cable Management Trays MEP
MEP
OSP Circuits - Pedestal and Accessories - Material
MEP
Receiving
OSP Circuits - Pedestal Installation and Pre-
MEP
Commissioning
MEP
Review of Ultrasonic Testing Procedure/Method
MEP
Statement
Review of UT Personnel Qualifications MEP
Review of TKY Technique Procedure & Mock-Up Design
MEP
for Ultrasonic Testing
Verification of Ultrasonic Testing Equipment MEP
Verification and/or Set-Up of Mock-Up of TKY Joints (Test
MEP
Pieces)
Performance Qualification of UT Personnel on the TKY
MEP
Mock-Up
Inspection of Requirements Prior to UT Application MEP
In-Process Verification of Techniques & Procedure
MEP
Implementation of UT
Evaluation of Ultrasonic Test and Test Report MEP
MEP
MEP
Inspection/Verification of Weld Modification or Repair
MEP
(Re-Work) after Weld Acceptance
Inspect Welding of Socket Joint and Seal Welding
MEP
Threaded Jts.
Review of Welding Procedure for Pipelines MEP
Review of Welding & Welding Operator Certifications MEP
Review of Method Statement & WPS for Weld Repair MEP

Review of Procedure for Weld Joint Identification System MEP

Review of Post Weld Heat Treatment Procedure MEP

Review of Production Weld Hardness Testing Procedure MEP

Receiving Inspection of Welding Consumables MEP


Verification/Calibration of Welding Machines MEP
Control of Welding
MEP
Consumables(Storage/Handling/Issuance)
Buttering and/or Weld Buildup MEP
Pre-Welding Inspection MEP
In-Process Welding Inspection MEP
Post-Welding Visual Inspection MEP
Weld Repair Inspection MEP
Post-Weld Heat Treatment Application for Plant Piping &
MEP
Pipelines
Verification of Hardness Testing Application & Test Result MEP

Production Weld and Welder Repair Rate Assessment MEP


MEP
MEP
Exothermic Welding Tools & Materials - Material
MEP
Receiving
CP Accessories - Material Receiving MEP
Exothermic Welding MEP
Galvanic Anodes for CP (Aluminum, Magnesium, and Zinc
MEP
Anodes) - Material Receiving
Galvanic CP Test Stations / Junction Boxes - Material
MEP
Receiving
Galvanic CP Anode Installation and Pre-Commissioning MEP
Galvanic CP Test Station Installation and Pre-
MEP
Commissioning
Galvanic CP Cable Installation, Termination, and
MEP
Identification
MEP
MEP
CP Rectifier - Material Receiving MEP
Impressed Current Anode - Material Receiving MEP
Impressed Current CP Cable - Material Receiving MEP
DC Rectifier Installation and Pre-Commissioning MEP
Impressed Current CP Anode Installation and Pre-
MEP
Commissioning
Impressed Current CP Deep Anode Bed Installation and
MEP
Pre-Commissioning
Impressed Current CP Cable Installation, Termination,
MEP
and Identification
MEP
Receiving Inspection-Metering Skid MEP
Storage, Handling & Preservation of Metering Skids and
MEP
Its Components
Inspection of Mechanical Component Installation and/or
MEP
Assembly
Piping Re-Instatement of Metering Skid MEP
Final visual inspection and testing [For energization
MEP
certificate] LV AC/DC panel board
MEP
MEP
MEP

You might also like