Anexo 3.2 Hoja de Datos Del Reactor 3401 DA - DB
Anexo 3.2 Hoja de Datos Del Reactor 3401 DA - DB
OBM: 3149
PROYECTO:
ESTE DOCUMENTO CONTIENE INFORMACIÓN DE
PROPIEDAD DE AESA, SU REPRODUCCIÓN TOTAL O GASOIL Y GASOLINA
PARCIAL ESTA PROHIBIDA.
DE BAJO AZUFRE
PROYECTO DIBUJO REVISO APROBO
TITULO:
3401 D A/B
INICIAL JVM JVM MCA GVR
FECHA 25/08/09 25/08/09 25/08/09 25/08/09
SHU REACTORS
HOJA ESCALA VERSION
AESA N°:
FIRMA 3149-02-3400-IG-PR-HD-0001 2
REVISION
1 DE 16 S/E
REALIZADO EN WORD 2003. NO MODIFICAR
MANUALMENTE ANCAP N°
0
PROJECTO: AESA N° 3149-02-3400-IG-PR-HD-0001
OBM 3149
GASOIL Y GASOLINA
DE BAJO AZUFRE ANCAP N°
Ver Rev
3401 D A/B 2 0 Hoja 2 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 3 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 4 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
CATALYST DATA
Ver Rev
3401 D A/B 2 0 Hoja 5 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
TABLE OF CONNECTIONS
Ref. Qty Size Sch Rating Type/Face Projection Function / Service Notes
I1 1 6” 80 300# WN/RF 250 Feed Inlet
MH 1 Diam. - 300# WN/RF 250 Manhole Min 900 mm I.D.
O1 1 6” 80 300# WN/RF 250 Product Outlet
O2 1 6” 120 300# WN/RF 250 Catalyst Unloading Nozzle With blind flange
T1-8 8 1½” 160 300# WN/RF 250 Thermowell
WIND ACTION
Characteristic Wind Speed (VK m/s) 43.9 Dimension Factor (KD) MET-ET-045
Topographic Factor (KT) 1 Safety Factor (KK) 1.15
Roughness (Type) 1 Load Design Basis CIV-ET-001/CIV-ET-002
Ver Rev
3401 D A/B 2 0 Hoja 6 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
GENERAL ARRANGEMENT
PROJECTO: AESA N° 3149-02-3400-IG-PR-HD-0001
OBM 3149
GASOIL Y GASOLINA
DE BAJO AZUFRE ANCAP N°
Ver Rev
3401 D A/B 2 0 Hoja 7 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
FEED DIFFUSER
PROJECTO: AESA N° 3149-02-3400-IG-PR-HD-0001
OBM 3149
GASOIL Y GASOLINA
DE BAJO AZUFRE ANCAP N°
Ver Rev
3401 D A/B 2 0 Hoja 8 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 9 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 10 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 11 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 12 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
OUTLET COLLECTOR
PROJECTO: AESA N° 3149-02-3400-IG-PR-HD-0001
OBM 3149
GASOIL Y GASOLINA
DE BAJO AZUFRE ANCAP N°
Ver Rev
3401 D A/B 2 0 Hoja 13 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 14 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
Ver Rev
3401 D A/B 2 0 Hoja 15 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
NOZZLE ORIENTATION
PROJECTO: AESA N° 3149-02-3400-IG-PR-HD-0001
OBM 3149
GASOIL Y GASOLINA
DE BAJO AZUFRE ANCAP N°
Ver Rev
3401 D A/B 2 0 Hoja 16 de 16
SHU REACTORS FECHA DE
EMISION: 28/08/2009
NOTES
1) Reactors operating conditions are modified according to catalyst activity: SOR (Start of run) and EOR (End of run).
Top and bottom operating conditions corresponds to first reactor inlet and second reactor outlet respectively.
2) H2S is not present at reactors. Feed sulfur content: 1550 ppm %w/w.
3) Vendor shall comply with the following Client specifications:
MET ET 001 – Pressure Vessels
MET ET 003 – Typical details of Vessels
MET ET 004 – Fabrication Requirements for Vessels Less Than 25mm Thickness
MET ET 005 – Fabrication Requirements for Vessels More Than 25mm Thickness and Low Alloy Steel (if
applicable)
MET ET 006 – Welding Procedure
MET ET 007 – Impact Tests in Base Materials and Weldings
MET ET 032 – Welding Requirements for Equipment and Piping
MET ET 036 – General Specification for Columns and Pressure Vessels
CIV ET 001 – Accion de Viento (Wind effects)
CIV ET 002 – Cargas de Diseño para Equipos, Estructuras, Edificios y Fundaciones
MET ET 045 – Wind Loads in Tall Vertical Vessels
CIV ET 009 – Calorifugado (Insulation)
4) Please refer to general arrangement drawing.
5) Design pressure in accordance with 3401 J A/B Feed Pumps shut-off pressure. Full Vacuum design condition at
ambient temperature.
6) All components welded to pressure parts shall be made of the same material as shell’s.
7) All dimensions are shown in mm.
8) All internals shall be introduced through a manhole (Min 900 mm internal diameter). If necessary, they shall be
made of several pieces to be introduced inside the reactor.
9) C.A.: 3 mm on each exposed surface if internal is welded to reactor.
C.A.: 0 mm if internal is removable.
10) Internals supporting members shall allow a man to step/hang on for maintenance purpose (1500N as concentrated
load).
11) In accordance with Operating Instructions Manual and Process Data Book, activation “in situ sulfiding” of the
catalyst is not foreseen. “Ready to use” catalyst, HR-845 S should be loaded in the reactor.
12) In accordance with Process Data Book, “ex situ” catalyst regeneration is foreseen.
13) Vessel shall be subjected to steam out at atmospheric pressure with medium pressure steam at 300ºC.
14) For Painting System details see doc. 3149-00-0000-IG-GE-LP-0002, Table 3.
15) Equipment shall be suitable for outdoor service, marine and corrosive environment.